Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Jharsuguda)
|
EDS
|
User Agency (fdpaherajore@gmail.com)
|
22/09/2015
|
1.Part-I narrating all pointwise details should enclosed with forest diversion proposal. You have only enclosed the online detail of Part-I.2. The requisite checklist should be enclosed with the proposals. 3. It is seen that degraded non- forest Govtland for CA has been identified in Kolabira range. The scheme should be prepared by the UA in consultation with Forest Deptt and should be enclosed with the proposal. 4.List of Flora & fauna should be enclosed with the proposals. 5.Species & Girth wise tree enumeration list should be enclosed with the proposal. 6. The land schedule of sabik kissam should be furnished per land records as on 25.10.1980existing within the land schedule apart from 14.275 ha of forest land for which Diversion proposal has been applied. 7. Administrative Approval
|
|
2
|
User Agency (fdpaherajore@gmail.com)
|
REPLY
|
DFO (Jharsuguda)
|
22/01/2016
|
As required by you we have completed all tasks and uploading the signed copy of letter showing reply.
|
|
3
|
Nodal Officer
|
EDS
|
CF (Sambalpur)
|
02/04/2016
|
Seven objection are found
|
|
4
|
CF (Sambalpur)
|
EDS
|
DFO (Jharsuguda)
|
05/04/2016
|
Seven objection are found
|
|
5
|
DFO (Jharsuguda)
|
REPLY
|
CF (Sambalpur)
|
06/04/2016
|
OFFICE OF THE DIVISIONAL FOREST OFFICER,
JHARSUGUDA FOREST DIVISION, JHARSUGUDA.
Memo No. 919 /Dated 18-03-2016
To
The Regional Chief Conservator of Forests,
Sambalpur Circle.
Sub: Diversion of 14.53 ha forest land for construction of Aherajore Barrage Project at village Debadarha (State Sl. No.OR-64/2015, dt.15.09.2015).
Ref: Memo No.4256, dt.04.03.2016 of Conservator of Forests(FC).
In inviting a kind reference to the memo cited above, I furnish below the point wise compliance on the shortcoming raised by the Chief Conservator of Forests(FC), O/O the PCCF, Odisha for favour of onward transmission.
(1) In compliance to the point, 14.53 ha has been recommended for diversion of forest land as per ROR. But as per DGPS survey, the said area comes to 14.695 h
|
|
6
|
CF (Sambalpur)
|
REPLY
|
Nodal Officer
|
06/04/2016
|
Complied all points as raised by Pr.CCF & DP forwarded to him.
|
|
7
|
Nodal Officer
|
EDS
|
CF (Sambalpur)
|
21/07/2016
|
Three nos deficiencies are found.
|
|
8
|
CF (Sambalpur)
|
EDS
|
DFO (Jharsuguda)
|
23/07/2016
|
Three nos deficiencies are found
|
|
9
|
DFO (Jharsuguda)
|
EDS
|
User Agency (fdpaherajore@gmail.com)
|
30/07/2016
|
All three deficiencies are cleared.
|
|
10
|
User Agency (fdpaherajore@gmail.com)
|
REPLY
|
DFO (Jharsuguda)
|
30/07/2016
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Jharsuguda)
|
REPLY
|
CF (Sambalpur)
|
30/07/2016
|
Recommendation for futher processing
|
|
12
|
CF (Sambalpur)
|
REPLY
|
Nodal Officer
|
03/08/2016
|
Revised DP submitted to Addl. PCCF,FD & NO,FC Act.O/o the PCCF,Odisha
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
28/02/2017
|
Clarication sought from the State Govt.
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
08/03/2017
|
EDS queries sought by ERO dated 23.02.2017
|
|
15
|
Nodal Officer
|
EDS
|
CF (Sambalpur)
|
13/04/2017
|
Please comply the EDS vide Memo No. 7242 18.03.2017
|
|
16
|
CF (Sambalpur)
|
EDS
|
DFO (Jharsuguda)
|
17/04/2017
|
requested DFO to submit the compliance report
|
|
17
|
DFO (Jharsuguda)
|
REPLY
|
CF (Sambalpur)
|
20/05/2017
|
OFFICE OF THE DIVISIONAL FOREST OFFICER, JHARSUGUDA FOREST DIVISION, JHARSUGUDA.
Memo No. /Dated -05-2017
To
The Addl. Principal Chief Conservator of Forests,
I/C Regional Chief Conservator of Forests, Sambalpur.
Sub: Diversion of 14.53 ha. of forest land for construction of Aherajore barrage project at village Debadarha in Lakhanpur block of Jharsuguda District, Odisha (Proposal No. FR/OR/IRRG/13364/2015).
Ref: Your memo No.7242, dt., dt.18.03.2017.
Sir,
In inviting a kind reference to your memo cited above, I submit herewith the point wise compliance on the following observations made by the Eastern Regional Office (ERO) of Ministry of Environment, Forest & Climate Change, Government of India.
1. During Power Point Presentation, it was observed that if the barrage i
|
|
18
|
CF (Sambalpur)
|
REPLY
|
Nodal Officer
|
29/05/2017
|
Objection comply
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
30/06/2017
|
Eds complied vide this Memo No. 15039 dt. 28.06.2017.
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
07/07/2017
|
Reply to the observations of ERO dated 23.02.2017.
|
|