Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Baripada)
|
EDS
|
User Agency (fdpsono@gmail.com)
|
28/11/2015
|
Due to non-submission of enumeration list of the trees by the user agency, timely submission of the diversion proposal is held up.
|
|
2
|
DFO (Balasore Wildlife)
|
EDS
|
User Agency (fdpsono@gmail.com)
|
09/12/2015
|
Demarcation of Forest land is required for site inspection
|
|
3
|
User Agency (fdpsono@gmail.com)
|
REPLY
|
DFO (Balasore Wildlife)
|
15/02/2016
|
We are complied as per your comments
|
|
4
|
User Agency (fdpsono@gmail.com)
|
REPLY
|
DFO (Balasore Wildlife)
|
29/02/2016
|
EDS by DFO, Baripada Letter no-7394, dated 28.11.15 has complied.
|
|
5
|
Nodal Officer
|
EDS
|
CF (Baripada)
|
20/07/2016
|
Five nos deficiencies are found.
|
|
6
|
CF (Baripada)
|
EDS
|
DFO (Baripada)
|
10/08/2016
|
DFO,Baripada is requested to submit compliance
|
|
7
|
DFO (Baripada)
|
REPLY
|
CF (Baripada)
|
10/08/2016
|
I furnish herewith necessary compliance for favour of your kind information and necessary action.
|
|
8
|
CF (Baripada)
|
REPLY
|
Nodal Officer
|
17/08/2016
|
Compliance submitted in respect of Sono Barrage Project.
|
|
9
|
State secretary
|
EDS
|
Nodal Officer
|
07/12/2016
|
total length of the canal, boundary description of RF land etc.
|
|
10
|
Nodal Officer
|
REPLY
|
State secretary
|
16/01/2017
|
The diversion proposal in triplicate are re-submitted for further necessary action at Government level.
|
|
11
|
Nodal Officer
|
REPLY
|
State secretary
|
16/01/2017
|
The diversion proposal in triplicate are re-submitted for further necessary action at Government level.
|
|
12
|
Regional Office
|
EDS
|
State secretary
|
28/02/2017
|
Clarification Sought From the State Govt.
|
|
13
|
State secretary
|
EDS
|
Nodal Officer
|
08/03/2017
|
EDC queries sought by ERO dated 23.02.2017.
|
|
14
|
Nodal Officer
|
EDS
|
CF (Baripada)
|
13/04/2017
|
Please comply the EDS vide Memo No.7240 dated 18.03.2017
|
|
15
|
CF (Baripada)
|
EDS
|
DFO (Balasore Wildlife)
|
19/04/2017
|
Please comply the discrepancies raised by the MoEF,Eastern Regional Office,BBSR at an early date.
|
|
16
|
CF (Baripada)
|
EDS
|
DFO (Baripada)
|
19/04/2017
|
Please comply the discrepancies raised by the MoEF,Eastern Regional Office,BBSR at an early date.
|
|
17
|
DFO (Baripada)
|
EDS
|
User Agency (fdpsono@gmail.com)
|
08/05/2017
|
Diversion of 14.928ha of Forest land for construction of Sono Barrage Project on River Sono at Jalda village of G.B.Nagar Block of Mayurbhanj District reg.
|
|
18
|
User Agency (fdpsono@gmail.com)
|
REPLY
|
DFO (Baripada)
|
09/05/2017
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Baripada)
|
REPLY
|
CF (Baripada)
|
16/05/2017
|
Proposal fro diversion of 14.928ha forest land for construction of Sono Barrage Project,
|
|
20
|
DFO (Balasore Wildlife)
|
REPLY
|
CF (Baripada)
|
25/05/2017
|
|
|
21
|
CF (Baripada)
|
REPLY
|
Nodal Officer
|
26/05/2017
|
Compliance report on observation of MoEF,Eastern Regional Office,BBSR submitted
|
|
22
|
Nodal Officer
|
REPLY
|
State secretary
|
28/06/2017
|
Compliance submitted to Government for onward transmission to Government, MOEF & CC, ERO, Bhubaneswar.
|
|
23
|
State secretary
|
REPLY
|
Regional Office
|
07/07/2017
|
Reply to observations of ERO dated 23.02.2017.
|
|