Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
State secretary
|
EDS
|
Nodal Officer
|
09/04/2019
|
|
|
2
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
09/04/2019
|
|
|
3
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Chhatarpur(T))
|
09/04/2019
|
|
|
4
|
DFO (Chhatarpur(T))
|
REPLY
|
CF (Chhatarpur(T))
|
09/04/2019
|
|
|
5
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
09/04/2019
|
|
|
6
|
Nodal Officer
|
REPLY
|
State secretary
|
09/04/2019
|
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
09/04/2019
|
|
|
8
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
09/04/2019
|
|
|
9
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Chhatarpur(T))
|
09/04/2019
|
|
|
10
|
DFO (Chhatarpur(T))
|
REPLY
|
CF (Chhatarpur(T))
|
09/04/2019
|
|
|
11
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
09/04/2019
|
|
|
12
|
Nodal Officer
|
REPLY
|
State secretary
|
09/04/2019
|
|
|
13
|
State secretary
|
EDS
|
Nodal Officer
|
30/04/2019
|
|
|
14
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
30/04/2019
|
|
|
15
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Chhatarpur(T))
|
30/04/2019
|
|
|
16
|
DFO (Chhatarpur(T))
|
EDS
|
User Agency (rdcnhdeepak@gmail.com)
|
30/04/2019
|
|
|
17
|
User Agency (rdcnhdeepak@gmail.com)
|
REPLY
|
DFO (Chhatarpur(T))
|
30/04/2019
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Chhatarpur(T))
|
REPLY
|
CF (Chhatarpur(T))
|
02/05/2019
|
|
|
19
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
02/05/2019
|
|
|
20
|
Nodal Officer
|
REPLY
|
State secretary
|
02/05/2019
|
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
27/05/2019
|
EDS on 24/05/19
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
29/05/2019
|
|
|
23
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
29/05/2019
|
Nodal officer letter dated 29/05/2019 enclosed.
|
|
24
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Chhatarpur(T))
|
29/05/2019
|
Nodal officer letter dated 29/05/2019 enclosed.
|
|
25
|
DFO (Chhatarpur(T))
|
EDS
|
User Agency (rdcnhdeepak@gmail.com)
|
29/05/2019
|
Nodal officer letter dated 29/05/2019 enclosed.
|
|
26
|
User Agency (rdcnhdeepak@gmail.com)
|
REPLY
|
DFO (Chhatarpur(T))
|
28/11/2022
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Chhatarpur(T))
|
EDS
|
User Agency (rdcnhdeepak@gmail.com)
|
06/01/2023
|
Nodal officer letter dated 29/05/2019 enclosed.
|
|
28
|
User Agency (rdcnhdeepak@gmail.com)
|
REPLY
|
DFO (Chhatarpur(T))
|
13/01/2023
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Chhatarpur(T))
|
REPLY
|
CF (Chhatarpur(T))
|
01/06/2023
|
The correction have been made as per the instruction of Nodal
|
|
30
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
14/06/2023
|
OK
|
|
31
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
05/07/2023
|
Nodal officer letter dated 05/07/2023 enclosed.
|
|
32
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Chhatarpur(T))
|
05/07/2023
|
Nodal officer letter dated 05/07/2023 enclosed.
|
|
33
|
DFO (Chhatarpur(T))
|
EDS
|
User Agency (rdcnhdeepak@gmail.com)
|
05/07/2023
|
Nodal officer letter dated 05/07/2023 enclosed.
|
|
34
|
User Agency (rdcnhdeepak@gmail.com)
|
REPLY
|
DFO (Chhatarpur(T))
|
10/08/2024
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Chhatarpur(T))
|
REPLY
|
CF (Chhatarpur(T))
|
28/08/2024
|
Latter No. 1121
|
|
36
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
09/09/2024
|
DFO HAS ALREADY UPLODED ESSENTIAL DOCUMENT
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
19/09/2024
|
Nodal officer letter dated 18/09/2024 enclosed.
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
19/09/2024
|
Nodal officer letter dated 18/09/2024 enclosed.
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
05/11/2024
|
EDS letter on 5.11.2024
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
11/11/2024
|
|
|
41
|
Nodal Officer
|
EDS
|
CF (Chhatarpur(T))
|
11/11/2024
|
Nodal officer letter dated 11/11/2024 enclosed.
|
|
42
|
CF (Chhatarpur(T))
|
EDS
|
DFO (Chhatarpur(T))
|
11/11/2024
|
Nodal officer letter dated 11/11/2024 enclosed.
|
|
43
|
DFO (Chhatarpur(T))
|
EDS
|
User Agency (rdcnhdeepak@gmail.com)
|
11/11/2024
|
Nodal officer letter dated 11/11/2024 enclosed.
|
|
44
|
User Agency (rdcnhdeepak@gmail.com)
|
REPLY
|
DFO (Chhatarpur(T))
|
17/04/2025
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Chhatarpur(T))
|
REPLY
|
CF (Chhatarpur(T))
|
19/06/2025
|
TS Report 61 ha.
|
|
46
|
CF (Chhatarpur(T))
|
REPLY
|
Nodal Officer
|
02/07/2025
|
CA SCHEME UPLODED BY DFO
|
|