TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/ROAD/156454/2022              (ii). Name of Project for which Forest Land is required : UPGRADATION/CONSTRUCTION OF TIKARIYA-SINGODHA-PATHA-CHUTKA ROAD              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : UPGRADATION/CONSTRUCTION OF TIKARIYA PATHA CHUTKA ROAD IN MANDLA DISTRICT.              (iv). File no. : 6-MPR044/2023-BHO              (v). State : Madhya Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 8.2
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MP/ROAD/156454/202202/09/2022aa02/09/2022   21/09/2022 Mandla West(T) :21/09/2022Jabalpur(T):
  26/07/2023 (Mandla West(T))

Madhya Pradesh:
09/08/2023
Madhya Pradesh:
28/08/2023
Bhopal:
02/11/2023
24/04/2025
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bhopal) on:28/12/2023  
Replied by State Government(Madhya Pradesh) on:17/02/2025  
Query raised by State Government (Madhya Pradesh) on:15/01/2024  
Replied by Nodal Officer (Madhya Pradesh) on:17/02/2025  
Query raised by Nodal Officer (Madhya Pradesh) on:15/01/2024  
Replied by Circle(Jabalpur(T)) on:15/02/2025  
Query raised by Circle (Jabalpur(T)) on:31/07/2023  
Replied by DFO (Mandla West(T)) on:31/07/2023  
Query raised by Circle (Jabalpur(T)) on:15/01/2024  
Replied by DFO (Mandla West(T)) on:15/02/2025  
Query raised by DFO (Mandla West(T)) on:15/01/2024  
Replied by UA on :15/02/2025  
Query raised by DFO (Mandla West(T)) on:15/02/2025  
Replied by UA on :15/02/2025  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...