Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Singrauli)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
18/04/2017
|
file
|
|
2
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Singrauli)
|
16/08/2017
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Singrauli)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
27/09/2017
|
letter for cost benifit analysis
|
|
4
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Singrauli)
|
13/01/2018
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Rewa(T))
|
11/05/2018
|
|
|
6
|
CF (Rewa(T))
|
EDS
|
DFO (Singrauli)
|
11/05/2018
|
|
|
7
|
DFO (Singrauli)
|
REPLY
|
CF (Rewa(T))
|
16/05/2018
|
no EDS
|
|
8
|
CF (Rewa(T))
|
EDS
|
DFO (Singrauli)
|
14/06/2018
|
|
|
9
|
DFO (Singrauli)
|
REPLY
|
CF (Rewa(T))
|
15/06/2018
|
no qurey
|
|
10
|
CF (Rewa(T))
|
EDS
|
DFO (Singrauli)
|
18/06/2018
|
|
|
11
|
DFO (Singrauli)
|
REPLY
|
CF (Rewa(T))
|
20/06/2018
|
no query
|
|
12
|
CF (Rewa(T))
|
EDS
|
DFO (Singrauli)
|
02/07/2018
|
|
|
13
|
DFO (Singrauli)
|
REPLY
|
CF (Rewa(T))
|
02/07/2018
|
no Query
|
|
14
|
CF (Rewa(T))
|
EDS
|
DFO (Singrauli)
|
02/07/2018
|
|
|
15
|
DFO (Singrauli)
|
REPLY
|
CF (Rewa(T))
|
02/07/2018
|
|
|
16
|
CF (Rewa(T))
|
REPLY
|
Nodal Officer
|
02/07/2018
|
|
|
17
|
Nodal Officer
|
EDS
|
CF (Rewa(T))
|
06/08/2018
|
|
|
18
|
CF (Rewa(T))
|
EDS
|
DFO (Singrauli)
|
06/08/2018
|
|
|
19
|
DFO (Singrauli)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
06/08/2018
|
|
|
20
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Singrauli)
|
06/08/2018
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Singrauli)
|
REPLY
|
CF (Rewa(T))
|
06/08/2018
|
|
|
22
|
CF (Rewa(T))
|
REPLY
|
Nodal Officer
|
06/08/2018
|
|
|
23
|
Head Office
|
EDS
|
State secretary
|
06/05/2019
|
EDS
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
24/05/2019
|
|
|
25
|
Nodal Officer
|
EDS
|
CF (Rewa(T))
|
24/05/2019
|
|
|
26
|
CF (Rewa(T))
|
EDS
|
DFO (Singrauli)
|
24/05/2019
|
|
|
27
|
DFO (Singrauli)
|
EDS
|
User Agency (nodalofficerenvbina@gmail.com)
|
24/05/2019
|
|
|
28
|
User Agency (nodalofficerenvbina@gmail.com)
|
REPLY
|
DFO (Singrauli)
|
09/12/2019
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Singrauli)
|
REPLY
|
CF (Rewa(T))
|
09/12/2019
|
|
|
30
|
CF (Rewa(T))
|
REPLY
|
Nodal Officer
|
09/12/2019
|
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
09/12/2019
|
|
|
32
|
State secretary
|
REPLY
|
Head Office
|
09/12/2019
|
Nodal officer letter dated 09/12/2019 enclosed.
|
|
33
|
IG
|
EDS
|
( MOEFAIG2 )
|
14/01/2020
|
Stage-I issued on 13.01.2020
|
|
34
|
AIG
|
EDS
|
( MOEFTO5 )
|
14/01/2020
|
Stage-I issued on 13.01.2020
|
|