TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/MIN/20225/2016              (ii). Name of Project for which Forest Land is required : Bina Kakari Amalgamation OCP mine              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This proposal envisages diversion of 390.264 ha forest land under section 2 of Forest Conservation Act 1980 for Bina Kakari Amalgamation coal mine project of Northern Coalfields Limited, Singrauli. The above forest land includes 370.152 Ha of notified forest land and 20.112 ha of revenue forest land              (iv). File no. : 8-69/2018-FC              (v). State : Madhya Pradesh              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 390.264
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MP/MIN/20225/201607/07/201625/01/2017  04/01/2017  08/11/2016  15/07/2016   28/01/2017  09/01/2017  22/12/2016  05/11/2016   30/01/2017   24/03/2017 Singrauli :25/03/2017Rewa(T):
  13/02/2018 (Singrauli)

Madhya Pradesh:
03/05/2018
Madhya Pradesh:
09/08/2018
31/10/201805/12/2018
23/01/2019
13/01/2020
By :Head Office
Madhya Pradesh
03/02/2021
16/04/2024
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 06/05/2019  
Replied by State Government (Madhya Pradesh) on:09/12/2019  
Query raised by State Government (Madhya Pradesh) on:24/05/2019  
Replied by Nodal Officer (Madhya Pradesh) on:09/12/2019  
Query raised by Nodal Officer (Madhya Pradesh) on:11/05/2018  
Replied by Circle(Rewa(T)) on:02/07/2018  
Query raised by Nodal Officer (Madhya Pradesh) on:06/08/2018  
Replied by Circle(Rewa(T)) on:06/08/2018  
Query raised by Nodal Officer (Madhya Pradesh) on:24/05/2019  
Replied by Circle(Rewa(T)) on:09/12/2019  
Query raised by Circle (Rewa(T)) on:11/05/2018  
Replied by DFO (Singrauli) on:16/05/2018  
Query raised by Circle (Rewa(T)) on:14/06/2018  
Replied by DFO (Singrauli) on:15/06/2018  
Query raised by Circle (Rewa(T)) on:18/06/2018  
Replied by DFO (Singrauli) on:20/06/2018  
Query raised by Circle (Rewa(T)) on:02/07/2018  
Replied by DFO (Singrauli) on:02/07/2018  
Query raised by Circle (Rewa(T)) on:02/07/2018  
Replied by DFO (Singrauli) on:02/07/2018  
Query raised by Circle (Rewa(T)) on:06/08/2018  
Replied by DFO (Singrauli) on:06/08/2018  
Query raised by Circle (Rewa(T)) on:24/05/2019  
Replied by DFO (Singrauli) on:09/12/2019  
Query raised by DFO (Singrauli) on:18/04/2017  
Replied by UA on :16/08/2017  
Query raised by DFO (Singrauli) on:27/09/2017  
Replied by UA on :13/01/2018  
Query raised by DFO (Singrauli) on:06/08/2018  
Replied by UA on :06/08/2018  
Query raised by DFO (Singrauli) on:24/05/2019  
Replied by UA on :09/12/2019  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 19/02/2021  
Replied by State Government (Madhya Pradesh) on:10/06/2021  
Query raised by MoEFCC,New Delhi 01/07/2021  
Replied by State Government (Madhya Pradesh) on:21/10/2022  
Query raised by MoEFCC,New Delhi 28/11/2022  
Replied by State Government (Madhya Pradesh) on:18/01/2023  
Query raised by MoEFCC,New Delhi 20/02/2023  
Replied by State Government (Madhya Pradesh) on:29/03/2023  
Query raised by MoEFCC,New Delhi 16/05/2023  
Replied by State Government (Madhya Pradesh) on:28/06/2023  
Query raised by MoEFCC,New Delhi 10/07/2023  
Replied by State Government (Madhya Pradesh) on:24/01/2024  
Query raised by MoEFCC,New Delhi 15/03/2024  
Replied by State Government (Madhya Pradesh) on:21/03/2024  
NOTE:- Stage-II Approval accorded by : Head Office .