  (i). Proposal No. : FP/MP/MIN/140863/2021              (ii). Name of Project for which Forest Land is required : Nigahi Expansion Opencast Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Nigahi Expansion Opencast Project (25 MTPA) is an expansion project of existing Nigahi OCP (22.50 MTPA). Total land requirement for the Nigahi Expansion OCP is 3582.723, out of which 3018.40 Ha has already been acquired for Nigahi OCP (22.50 MTPA), whereas 564.323 Ha land is additionally required,              (iv). File no. : 8-26/2015-FC Vol.              (v). State : Madhya Pradesh              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 229.348
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onStage-II Approval on
FP/MP/MIN/140863/202109/04/2021aa15/04/2021   20/04/2021 Singrauli :22/04/2021Rewa(T):
  25/01/2022 (Singrauli)

Madhya Pradesh:
09/02/2023
Madhya Pradesh:
17/02/2023
26/05/202306/10/2023
11/12/2023
29/12/2023
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 05/07/2023  
Replied by State Government (Madhya Pradesh) on:26/08/2023  
Query raised by State Government (Madhya Pradesh) on:07/07/2023  
Replied by Nodal Officer (Madhya Pradesh) on:26/08/2023  
Query raised by Nodal Officer (Madhya Pradesh) on:07/07/2023  
Replied by Circle(Rewa(T)) on:26/08/2023  
Query raised by Circle (Rewa(T)) on:01/02/2022  
Replied by DFO (Singrauli) on:28/12/2022  
Query raised by Circle (Rewa(T)) on:29/12/2022  
Replied by DFO (Singrauli) on:30/12/2022  
Query raised by Circle (Rewa(T)) on:07/07/2023  
Replied by DFO (Singrauli) on:26/08/2023  
Query raised by DFO (Singrauli) on:01/07/2021  
Replied by UA on :13/11/2021  
Query raised by DFO (Singrauli) on:01/02/2022  
Replied by UA on :16/02/2022  
Query raised by DFO (Singrauli) on:18/02/2022  
Replied by UA on :13/04/2022  
Query raised by DFO (Singrauli) on:26/05/2022  
Replied by UA on :21/06/2022  
Query raised by DFO (Singrauli) on:27/12/2022  
Replied by UA on :27/12/2022  
Query raised by DFO (Singrauli) on:07/07/2023  
Replied by UA on :16/08/2023  
Query raised by DFO (Singrauli) on:18/08/2023  
Replied by UA on :18/08/2023  