Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
28/06/2018
|
Regarding CA land
|
|
2
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
30/07/2019
|
The correction have been made as per the instruction received
|
|
3
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
21/08/2019
|
Plz Attach Required Document.
|
|
4
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
21/08/2019
|
Required Document is enclosed
|
|
5
|
State secretary
|
EDS
|
Nodal Officer
|
23/10/2019
|
|
|
6
|
Nodal Officer
|
EDS
|
CF (Ujjain(T))
|
23/10/2019
|
|
|
7
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
23/10/2019
|
|
|
8
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
23/10/2019
|
|
|
9
|
CF (Ujjain(T))
|
REPLY
|
Nodal Officer
|
23/10/2019
|
|
|
10
|
Nodal Officer
|
REPLY
|
State secretary
|
23/10/2019
|
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
04/03/2020
|
EDS on 3.032020
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
09/03/2020
|
|
|
13
|
Nodal Officer
|
EDS
|
CF (Ujjain(T))
|
09/03/2020
|
|
|
14
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
09/03/2020
|
|
|
15
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
09/03/2020
|
|
|
16
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
16/07/2020
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
07/09/2020
|
As per letter No./DM/2020/5634 Date 07-09-2020
|
|
18
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
11/11/2020
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
18/11/2020
|
As per enclosed letter
|
|
20
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
17/12/2020
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
23/12/2020
|
The correction have been made as per the instruction received
|
|
22
|
CF (Ujjain(T))
|
REPLY
|
Nodal Officer
|
24/12/2020
|
DFO Neemuch Has been fulfill all the necessary Information as per HQ Bhopal Instructions. Hence it is recommended for acceptance.
|
|
23
|
Nodal Officer
|
EDS
|
CF (Ujjain(T))
|
10/03/2021
|
|
|
24
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
10/03/2021
|
|
|
25
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
24/03/2021
|
As per letter No./DM/2021/1949 Date 24-03-2021 sought By APCCF (land Management) Bhopal
|
|
26
|
CF (Ujjain(T))
|
REPLY
|
Nodal Officer
|
03/04/2021
|
Forwarded for necessary Action
|
|
27
|
Nodal Officer
|
EDS
|
CF (Ujjain(T))
|
02/06/2021
|
|
|
28
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
02/06/2021
|
|
|
29
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
02/06/2021
|
|
|
30
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
25/06/2021
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
01/07/2021
|
In accordance to the instructions given by the Nodal Officer.
|
|
32
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
19/12/2021
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
20/12/2021
|
In accordance to the instructions given by the Nodal Officer.
|
|
34
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
23/12/2021
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
23/12/2021
|
|
|
36
|
CF (Ujjain(T))
|
REPLY
|
Nodal Officer
|
23/12/2021
|
|
|
37
|
Nodal Officer
|
EDS
|
CF (Ujjain(T))
|
24/12/2021
|
|
|
38
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
24/12/2021
|
|
|
39
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
24/12/2021
|
|
|
40
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
16/02/2022
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
16/02/2022
|
|
|
42
|
CF (Ujjain(T))
|
REPLY
|
Nodal Officer
|
16/02/2022
|
|
|
43
|
Nodal Officer
|
EDS
|
CF (Ujjain(T))
|
16/02/2022
|
|
|
44
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
16/02/2022
|
|
|
45
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
16/02/2022
|
|
|
46
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
16/02/2022
|
The correction have been made as per the instruction received
|
|
47
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
23/02/2022
|
Submit hard copy of proposal of area 39.39 hac.
|
|
48
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
31/03/2022
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
06/05/2022
|
As per instruction
|
|
50
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
06/05/2022
|
Pls Check
|
|
51
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
06/05/2022
|
The correction have been made as per the instruction received
|
|
52
|
CF (Ujjain(T))
|
REPLY
|
Nodal Officer
|
18/05/2022
|
Forest Land Required for the project is bare minimum, Hence recommended for acceptance.
|
|
53
|
Nodal Officer
|
EDS
|
CF (Ujjain(T))
|
26/05/2022
|
|
|
54
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
26/05/2022
|
|
|
55
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
26/05/2022
|
|
|
56
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
26/05/2022
|
The correction have been made as per the instruction received
|
|
57
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
26/05/2022
|
|
|
58
|
CF (Ujjain(T))
|
REPLY
|
Nodal Officer
|
26/05/2022
|
|
|
59
|
Nodal Officer
|
REPLY
|
State secretary
|
27/05/2022
|
Nodal officer letter dated 27/05/2022 enclosed.
|
|
60
|
State secretary
|
REPLY
|
Regional Office
|
27/05/2022
|
Nodal officer letter dated 27/05/2022 enclosed.
|
|
61
|
Regional Office
|
EDS
|
State secretary
|
26/07/2022
|
EDS letter on 26.07.2022
|
|
62
|
State secretary
|
EDS
|
Nodal Officer
|
08/08/2022
|
|
|
63
|
Nodal Officer
|
EDS
|
CF (Ujjain(T))
|
08/08/2022
|
Nodal officer letter dated 08/08/2022 enclosed.
|
|
64
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
08/08/2022
|
Nodal officer letter dated 08/08/2022 enclosed.
|
|
65
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
08/08/2022
|
Nodal officer letter dated 08/08/2022 enclosed.
|
|
66
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
01/12/2023
|
The correction have been made as per the instruction received
|
|
67
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
08/12/2023
|
01. ?????? ??? 43.149 ???????? ?????? ???????? ???? ????? ??? ??? ???????? ???????? ??? ?????? ??????? ?? ???? , ??.??.?? ???? ??? ????? ?????????? ??? ?????? ?????? ?? ????? ???? ???? ????? ???????? 05 ???????? ??? ?? ???????? ?? ?????? ???????
02. ?????? ??? ?????????? ?????? ?? ???? ???????? ?????????? ????? ??????? ??????? ??? ?????? ?????????????? ???? ?? ?????????? ????? ???? ???? ???? ?????? ???????? ??? ?? ????? ?? ??? ?? ???-????? ????? ????, ??????? ????? ???? ??? ?? ???????? ????? ??? ???? ???? ?? ?????? ?? ???????, 1927 ?? ???? 29 ?? ??????? ???????? ?? ???????? ???? ?? ????? ??? ?????? ??????-???? ?? ???????? ?? ?????? ???????
|
|
68
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
22/01/2024
|
The correction have been made as per the instruction received
|
|
69
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
23/01/2024
|
As per instruction
|
|
70
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
09/02/2024
|
The correction have been made as per the instruction received
|
|
71
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
09/02/2024
|
|
|
72
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
09/02/2024
|
The correction have been made as per the instruction received
|
|
73
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
14/02/2024
|
As per attached descriptions.
|
|
74
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
26/03/2024
|
The correction have been made as per the instruction received
|
|
75
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
25/07/2024
|
Letter No/4592 date 25-07-2024
|
|
76
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
01/08/2024
|
The correction have been made as per the instruction received
|
|
77
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
02/08/2024
|
As Per Letter No. /2024/4743 date 02-08-2024
|
|
78
|
CF (Ujjain(T))
|
REPLY
|
Nodal Officer
|
06/08/2024
|
Forest land required is bare minimum for the project. Hence the proposal recommended for acceptance.
|
|
79
|
Nodal Officer
|
REPLY
|
State secretary
|
29/08/2024
|
Nodal officer letter dated 27/08/2024 enclosed.
|
|
80
|
State secretary
|
REPLY
|
Regional Office
|
29/08/2024
|
Nodal officer letter dated 27/08/2024 enclosed.
|
|
81
|
Head Office
|
EDS
|
State secretary
|
03/12/2024
|
EDS
|
|
82
|
State secretary
|
EDS
|
Nodal Officer
|
19/12/2024
|
|
|
83
|
Nodal Officer
|
EDS
|
CF (Ujjain(T))
|
19/12/2024
|
Nodal officer letter dated 10/12/2024 enclosed.
|
|
84
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
19/12/2024
|
Nodal officer letter dated 10/12/2024 enclosed.
|
|
85
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
02/01/2025
|
As per letter No/tech./2025/22 date 01-01-2025
|
|
86
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
15/05/2025
|
The correction have been made as per the instruction received
|
|
87
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
15/05/2025
|
|
|
88
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
REPLY
|
DFO (Neemach(T))
|
25/05/2025
|
The correction have been made as per the instruction received
|
|
89
|
DFO (Neemach(T))
|
REPLY
|
CF (Ujjain(T))
|
12/06/2025
|
EDS Reply By Letter no. 3498 Date 12-06-2025
|
|
90
|
CF (Ujjain(T))
|
REPLY
|
Nodal Officer
|
13/06/2025
|
Additional information fulfilled.
|
|
91
|
Nodal Officer
|
REPLY
|
State secretary
|
30/06/2025
|
Nodal officer letter dated 30/06/2025 enclosed.
|
|
92
|
State secretary
|
REPLY
|
Head Office
|
30/06/2025
|
Nodal officer letter dated 30/06/2025 enclosed.
|
|
93
|
Head Office
|
EDS
|
State secretary
|
14/08/2025
|
EDS
|
|
94
|
State secretary
|
EDS
|
Nodal Officer
|
20/08/2025
|
|
|
95
|
Nodal Officer
|
EDS
|
CF (Ujjain(T))
|
20/08/2025
|
|
|
96
|
CF (Ujjain(T))
|
EDS
|
DFO (Neemach(T))
|
20/08/2025
|
|
|
97
|
DFO (Neemach(T))
|
EDS
|
User Agency (eewrd_neemuch@yahoo.co.in)
|
26/08/2025
|
Letter NO /2024/4902 date 22-08-2025
|
|