Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Vidisha(T))
|
EDS
|
User Agency (sdowrdbasoda@gmail.com)
|
24/05/2018
|
|
|
2
|
User Agency (sdowrdbasoda@gmail.com)
|
REPLY
|
DFO (Vidisha(T))
|
19/02/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Vidisha(T))
|
EDS
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
07/12/2020
|
Suitable Land required Compensatory afforstation scheme
|
|
4
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
REPLY
|
DFO (Vidisha(T))
|
29/11/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Vidisha(T))
|
EDS
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
12/06/2023
|
Peruse the letter and make the desired information available to this office immediately.
|
|
6
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
REPLY
|
DFO (Vidisha(T))
|
20/07/2023
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Vidisha(T))
|
EDS
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
21/07/2023
|
|
|
8
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
REPLY
|
DFO (Vidisha(T))
|
21/07/2023
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Vidisha(T))
|
EDS
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
26/07/2023
|
Peruse the letter and make the desired information available to this office immediately.
|
|
10
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
REPLY
|
DFO (Vidisha(T))
|
04/08/2023
|
The correction have been made as per the instruction received
|
|
11
|
CF (Bhopal(T))
|
EDS
|
DFO (Vidisha(T))
|
21/08/2023
|
Hard copy of proposal is incorrect submitted and incorrect document attached in on line proposal
|
|
12
|
DFO (Vidisha(T))
|
EDS
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
24/08/2023
|
In the online proposal, deficiencies have been found by the senior office, fill the deficiencies and inform this office and also send a hard copy.
|
|
13
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
REPLY
|
DFO (Vidisha(T))
|
06/10/2023
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Vidisha(T))
|
EDS
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
06/10/2023
|
|
|
15
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
REPLY
|
DFO (Vidisha(T))
|
18/10/2023
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Vidisha(T))
|
EDS
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
23/10/2023
|
|
|
17
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
REPLY
|
DFO (Vidisha(T))
|
23/10/2023
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Vidisha(T))
|
REPLY
|
CF (Bhopal(T))
|
09/11/2023
|
After making corrections in the online proposal, it is submitted for further action
|
|
19
|
CF (Bhopal(T))
|
EDS
|
DFO (Vidisha(T))
|
23/11/2023
|
As per discussion, the number of patches proposed for compensatory afforestation should be improved. and upload CAT plan is not open
|
|
20
|
DFO (Vidisha(T))
|
EDS
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
24/11/2023
|
|
|
21
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
REPLY
|
DFO (Vidisha(T))
|
24/11/2023
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Vidisha(T))
|
REPLY
|
CF (Bhopal(T))
|
29/01/2024
|
|
|
23
|
Head Office
|
EDS
|
State secretary
|
08/03/2024
|
EDS
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
12/03/2024
|
|
|
25
|
Nodal Officer
|
EDS
|
CF (Bhopal(T))
|
12/03/2024
|
Nodal officer letter dated 12/03/2024 enclosed.
|
|
26
|
CF (Bhopal(T))
|
EDS
|
DFO (Vidisha(T))
|
12/03/2024
|
Nodal officer letter dated 12/03/2024 enclosed.
|
|
27
|
DFO (Vidisha(T))
|
EDS
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
12/03/2024
|
Nodal officer letter dated 12/03/2024 enclosed.
|
|
28
|
User Agency (eewrd.ganjbasoda@gmail.com)
|
REPLY
|
DFO (Vidisha(T))
|
30/05/2025
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Vidisha(T))
|
REPLY
|
CF (Bhopal(T))
|
30/05/2025
|
|
|
30
|
CF (Bhopal(T))
|
REPLY
|
Nodal Officer
|
30/05/2025
|
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
04/06/2025
|
Nodal officer letter dated 04/06/2025 enclosed.
|
|
32
|
State secretary
|
REPLY
|
Head Office
|
04/06/2025
|
Nodal officer letter dated 04/06/2025 enclosed.
|
|
33
|
Head Office
|
EDS
|
State secretary
|
30/06/2025
|
EDS
|
|
34
|
State secretary
|
EDS
|
Nodal Officer
|
01/07/2025
|
|
|
35
|
Nodal Officer
|
EDS
|
CF (Bhopal(T))
|
01/07/2025
|
Nodal officer letter dated 30/06/2025 enclosed.
|
|
36
|
CF (Bhopal(T))
|
EDS
|
DFO (Vidisha(T))
|
01/07/2025
|
Nodal officer letter dated 01/07/2025 enclosed.
|
|