Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Central Forest Circle)
|
23/02/2016
|
Proposal submitted by Director, Education, School vide letter No. 24/1/1-2/07-DE, school vol-I dt. 5/12/2015 for diversion of 0.99 ha. forest land at Chingkheiching, RF has been processed through DFO, Central Forest Divn. & CF, Central Circle. The processing authorities have reported that forest land cleared and used in violation of FC, Act for const. of Residential School by the Education School Deptt., is 1.63 ha forest land against the proposal of Director Education, School for diversion of 0.99 ha forest land. As such, your proposal for diversion of 0.99 ha. of forest land at Chingkheiching RF for const. of Residential School cannot be processed further.
You are, therefore, informed to submit a revised proposal on factual basis.
|
|
2
|
CF (Central Forest Circle)
|
EDS
|
DFO (Central Forest Division,Imphal)
|
17/02/2017
|
Proposal submitted by Director, Education, School vide letter No. 24/1/1-2/07-DE, school vol-I dt. 5/12/2015 for diversion of 0.99 ha. forest land at Chingkheiching, RF has been processed through DFO, Central Forest Divn. & CF, Central Circle. The processing authorities have reported that forest land cleared and used in violation of FC, Act for const. of Residential School by the Education School Deptt., is 1.63 ha forest land against the proposal of Director Education, School for diversion of 0.99 ha forest land. As such, your proposal for diversion of 0.99 ha. of forest land at Chingkheiching RF for const. of Residential School cannot be processed further. You are, therefore, informed to submit a revised proposal on factual basis.
|
|
3
|
DFO (Central Forest Division,Imphal)
|
EDS
|
User Agency (praveennaorem01@yahoo.com)
|
27/02/2018
|
Director (Education) Manipur had been requested to submit revised proposal as the actual area of forest land cleared and being used by the School and other structures is 1.63 ha against the proposal of 0.99 Ha vide letter No.7/147/2015/Forests dated 17.2.2016 of the Nodal Officer FCA, Manipur and letter No.4/3(a)/2015-16/DFO/C (Chingkheiching-SSA) dated 1.9.2016 of the DFO, Central Forest Division. Till date neither revised proposal nor any response has been received from the User Agency. The proposal is returned to the UA for favor of further necessary action. Scanned copies of the letters and map showing proposed and actual position of land is enclosed.
|
|
4
|
User Agency (praveennaorem01@yahoo.com)
|
REPLY
|
DFO (Central Forest Division,Imphal)
|
25/10/2018
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Central Forest Division,Imphal)
|
REPLY
|
CF (Central Forest Circle)
|
27/02/2024
|
User Agency
Director (Education) Manipur had been requested to submit revised proposal as the actual area of forest land cleared and being used by the School and other structures is 1.63 ha against the proposal of 0.99 Ha vide letter No.7/147/2015/Forests dated 17.2.2016 of the Nodal Officer FCA, Manipur and letter No.4/3(a)/2015-16/DFO/C (Chingkheiching-SSA) dated 1.9.2016 of the DFO, Central Forest Division. Till date neither revised proposal nor any response has been received from the User Agency. The proposal is returned to the UA for favor of further necessary action
|
|
6
|
CF (Central Forest Circle)
|
EDS
|
DFO (Central Forest Division,Imphal)
|
28/02/2024
|
Proposal submitted by Director, Education, School vide letter No. 24/1/1-2/07-DE, school vol-I dt. 5/12/2015 for diversion of 0.99 ha. forest land at Chingkheiching, RF has been processed through DFO, Central Forest Divn. & CF, Central Circle. The processing authorities have reported that forest land cleared and used in violation of FC, Act for const. of Residential School by the Education School Deptt., is 1.63 ha forest land against the proposal of Director Education, School for diversion of 0.99 ha forest land. As such, your proposal for diversion of 0.99 ha. of forest land at Chingkheiching RF for const. of Residential School cannot be processed further. You are, therefore, informed to submit a revised proposal on factual basis
|
|
7
|
DFO (Central Forest Division,Imphal)
|
EDS
|
User Agency (zeo.zone2.imphaleast@gmail.com)
|
28/02/2024
|
Proposal submitted by Director, Education, School vide letter No. 24/1/1-2/07-DE, school vol-I dt. 5/12/2015 for diversion of 0.99 ha. forest land at Chingkheiching, RF has been processed through DFO, Central Forest Divn. & CF, Central Circle. The processing authorities have reported that forest land cleared and used in violation of FC, Act for const. of Residential School by the Education School Deptt., is 1.63 ha forest land against the proposal of Director Education, School for diversion of 0.99 ha forest land. As such, your proposal for diversion of 0.99 ha. of forest land at Chingkheiching RF for const. of Residential School cannot be processed further. You are, therefore, informed to submit a revised proposal on factual basis
|
|
8
|
User Agency (zeo.zone2.imphaleast@gmail.com)
|
REPLY
|
DFO (Central Forest Division,Imphal)
|
16/04/2024
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Central Forest Division,Imphal)
|
REPLY
|
CF (Central Forest Circle)
|
21/04/2024
|
The user agency has submitted proposal of 0.99 ha. Site was inspected on 28.02.2024 and the site was within the propose area. Violation has been made by the UA and necessary Penal NPV shall be charged.
|
|