Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Khasi&Jaintia Hills)
|
EDS
|
DFO (Jaintia Hills)
|
17/12/2019
|
Kindly submit the duly signed hard copies of the application at the earliest for necessary action at this level.
|
|
2
|
DFO (Jaintia Hills)
|
REPLY
|
CF (Khasi&Jaintia Hills)
|
20/12/2019
|
signed hard copies of application with attachment sent
|
|
3
|
CF (Khasi&Jaintia Hills)
|
EDS
|
DFO (Jaintia Hills)
|
17/02/2020
|
During site inspection in january 2020, no demarcation of approach road was found on the ground. Also wildlife details need to be incorporated into the proposal. Kindly do the needful and revert.
|
|
4
|
DFO (Jaintia Hills)
|
EDS
|
User Agency (anil.singh@greenvalliey.com)
|
06/03/2020
|
Please comply with CF comments and resubmit
|
|
5
|
User Agency (anil.singh@greenvalliey.com)
|
REPLY
|
DFO (Jaintia Hills)
|
11/12/2020
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Jaintia Hills)
|
REPLY
|
CF (Khasi&Jaintia Hills)
|
21/12/2020
|
UA has complied to the query raised your office. U/s has inspected the same and enclosed the site inspection report as attachment for further necessary action
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
26/04/2022
|
The State Govt. is requested to provide following additional information for further
processing of the case: (i) The status of 'forest land' as identified by JIT-I & JIT-II and the progress with
respect to FC application of all lands may be furnished. (ii) Scanned Sol toposheet map depicting the diversion area and duly signed by the DFO concerned. (iii) The detail breakup of land requirement submitted in the proposal is for mining area is 9.6 ha, safety zone is 1.11 ha and approach road is 0.3 ha; whereas others are also required i.e. Green Belt and dumping yard which may be submitted.
(iv) The length and width of approach road proposed over 0.3 ha may be submitted. (v) The date of issue of Letter of Intent (LOI) for grant of mining lease is 04.01.2018; its validity may be furnished. (v
|
|
8
|
State secretary
|
REPLY
|
Regional Office
|
16/03/2023
|
Additional information sought has been submitted vide letter dated 20.08.2022
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
27/06/2023
|
I am to inform you that this instant proposal has been received back in IRO from Ministry, New Delhi. It is to be mentioned that the proposal has been examined in detailed at all level in the Ministry, New Delhi where Ministry has also observed on the following: i. Since the land for Compensatory Afforestation has been identified in non-forest land, Ministry has observed that no documentary details and its status such as revenue records or other government records are available. The State Govt may furnish details along with documentary evidences in support of the proposed CA land. ii. There is discrepancy in the enumeration list of trees as reported by DFO (581 nos.) and RFO (588 nos.). The State Govt may clarify on the number of trees to be felled. iii. DSS analysis of CA area shows 11.05
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
17/10/2024
|
Stage-I granted by MoEF&CC
|
|