TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/TRANS/48321/2020              (ii). Name of Project for which Forest Land is required : 220 KV DC Tarapur- Borivali and Boisar - Ghodbandar Electrical Transmission line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The project also expected to help in minimizing development constraints in agriculture, E- Commerce,Education , Health, Social welfare and public safety.              (iv). File no. : FC-II/MH-227/2023-NGP              (v). State : Maharashtra              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 10.3391
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/MH/TRANS/48321/202005/08/2020aa05/08/2020   20/08/2020

Jawhar :20/08/2020


Dahanu :20/08/2020

Thane:
  26/11/2022 (Jawhar)

Thane:
  17/01/2023 (Dahanu)

Maharashtra:
30/01/2023
Maharashtra:
09/02/2023
Nagpur:
01/09/2023
08/07/2024
By :Regional Office
Maharashtra
03/10/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:24/11/2023  
Replied by State Government(Maharashtra) on:16/04/2024  
Query raised by State Government (Maharashtra) on:23/05/2023  
Replied by Nodal Officer (Maharashtra) on:27/06/2023  
Query raised by State Government (Maharashtra) on:28/11/2023  
Replied by Nodal Officer (Maharashtra) on:15/04/2024  
Query raised by Nodal Officer (Maharashtra) on:03/02/2023  
Replied by Circle(Thane) on:06/02/2023  
Query raised by Nodal Officer (Maharashtra) on:23/05/2023  
Replied by Circle(Thane) on:23/06/2023  
Query raised by Nodal Officer (Maharashtra) on:28/11/2023  
Replied by Circle(Thane) on:06/02/2024  
Query raised by Nodal Officer (Maharashtra) on:14/02/2024  
Replied by Circle(Thane) on:22/03/2024  
Query raised by Circle (Thane) on:25/05/2023  
Replied by DFO (Dahanu) on:15/06/2023  
Query raised by Circle (Thane) on:25/05/2023  
Replied by DFO (Jawhar) on:15/06/2023  
Query raised by Circle (Thane) on:30/11/2023  
Replied by DFO (Dahanu) on:23/01/2024  
Query raised by Circle (Thane) on:30/11/2023  
Replied by DFO (Jawhar) on:23/01/2024  
Query raised by DFO (Jawhar) on:23/04/2021  
Replied by UA on :01/03/2022  
Query raised by DFO (Dahanu) on:16/04/2022  
Replied by UA on :11/06/2022  
Query raised by DFO (Dahanu) on:07/12/2023  
Replied by UA on :20/12/2023  
NOTE:- Proposal is pending at RO for Stage-II .
Close(X)
Close(X)
Please wait ...