TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/ROAD/25848/2017              (ii). Name of Project for which Forest Land is required : Diversion of 33.420 ha. Forest Land for Up-gradation to Two Lanes with lpaved shoulder for Nanded-Kinwat-Mahur-Arni Road Network in the State of Maharasshtra (147.758km)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Present Proposal is for upgradation of existing National Highway from Bhoker to Dhanoda in Maharashtra State              (iv). File no. : FC-II/MH-140/2021-NGP              (v). State : Maharashtra              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 33.42
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MH/ROAD/25848/201725/04/2017aa26/04/2017   31/05/2017 Nanded :31/05/2017Aurangabad:
  02/03/2020 (Nanded)

Maharashtra:
25/06/2020
Maharashtra:
21/01/2021
Nagpur:
02/02/2021
28/02/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:24/02/2021  
Replied by State Government(Maharashtra) on:18/11/2021  
Query raised by Regional Office (Nagpur) on:02/01/2022  
Replied by State Government(Maharashtra) on:17/02/2022  
Query raised by State Government (Maharashtra) on:25/10/2021  
Replied by Nodal Officer (Maharashtra) on:18/11/2021  
Query raised by State Government (Maharashtra) on:11/01/2022  
Replied by Nodal Officer (Maharashtra) on:27/01/2022  
Query raised by Nodal Officer (Maharashtra) on:28/09/2020  
Replied by Circle(Aurangabad) on:28/09/2020  
Query raised by Nodal Officer (Maharashtra) on:28/09/2020  
Replied by Circle(Aurangabad) on:08/01/2021  
Query raised by Nodal Officer (Maharashtra) on:26/10/2021  
Replied by Circle(Aurangabad) on:27/10/2021  
Query raised by Nodal Officer (Maharashtra) on:28/10/2021  
Replied by Circle(Aurangabad) on:11/11/2021  
Query raised by Nodal Officer (Maharashtra) on:11/01/2022  
Replied by Circle(Aurangabad) on:17/01/2022  
Query raised by Circle (Aurangabad) on:12/03/2020  
Replied by DFO (Nanded) on:10/06/2020  
Query raised by Circle (Aurangabad) on:28/09/2020  
Replied by DFO (Nanded) on:07/01/2021  
Query raised by Circle (Aurangabad) on:11/01/2022  
Replied by DFO (Nanded) on:14/01/2022  
Query raised by DFO (Nanded) on:14/02/2020  
Replied by UA on :19/02/2020  
Query raised by DFO (Nanded) on:28/09/2020  
Replied by UA on :28/09/2020  
Query raised by DFO (Nanded) on:07/10/2020  
Replied by UA on :11/10/2020  
Query raised by DFO (Nanded) on:12/01/2022  
Replied by UA on :13/01/2022  
NOTE:- Stage-I Approval accorded by : Regional Office .