TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/ROAD/24850/2017              (ii). Name of Project for which Forest Land is required : SUPPLEMENTARY PROPOSAL for Widening of Existing NH – 4B, NH-348 (Previous SH-54 AND Amra Marg) to Six/Eight Lanes on The Boundaries of Proposed Navi Mumbai International Airport And JNPT On DBFOT Pattern              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The project consists of 3 roads NH – 4B (A1-E and D-G Sections), part of SH – 54 (Km. 5.300 to Km. 14.850) and Amra Marg (Km.0.000 to Km. 6.200) in the state of Maharastra. The Project roads connect Jawaharlal Nehru Port and are present on boundaries of proposed Navi Mumbai International Airport. Th              (iv). State : Maharashtra              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.036
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MH/ROAD/24850/201707/03/201725/01/2018  12/01/2018  01/01/2018  22/12/2017  10/03/2017   01/02/2018  25/01/2018  02/01/2018  29/12/2017  20/12/2017   01/02/2018   01/02/2018 Alibag :01/02/2018Thane:
  16/12/2021 (Alibag)

Maharashtra:
23/06/2022
Maharashtra:
29/06/2022
Nagpur:
12/07/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:13/08/2022  
Replied by State Government(Maharashtra) on:07/05/2023  
Query raised by Regional Office (Nagpur) on:25/07/2023  
Replied by State Government(Maharashtra) on:25/08/2025  
Query raised by State Government (Maharashtra) on:21/08/2022  
Replied by Nodal Officer (Maharashtra) on:27/04/2023  
Query raised by State Government (Maharashtra) on:08/08/2023  
Replied by Nodal Officer (Maharashtra) on:22/08/2025  
Query raised by Nodal Officer (Maharashtra) on:22/08/2022  
Replied by Circle(Thane) on:26/04/2023  
Query raised by Nodal Officer (Maharashtra) on:08/08/2023  
Replied by Circle(Thane) on:21/08/2025  
Query raised by Circle (Thane) on:11/01/2022  
Replied by DFO (Alibag) on:31/05/2022  
Query raised by Circle (Thane) on:14/09/2022  
Replied by DFO (Alibag) on:26/04/2023  
Query raised by Circle (Thane) on:11/08/2023  
Replied by DFO (Alibag) on:06/08/2024  
Query raised by Circle (Thane) on:06/08/2024  
Replied by DFO (Alibag) on:21/08/2025  
Query raised by DFO (Alibag) on:03/02/2018  
Replied by UA on :05/06/2018  
Query raised by DFO (Alibag) on:10/07/2018  
Replied by UA on :26/07/2021  
Query raised by DFO (Alibag) on:20/10/2021  
Replied by UA on :29/11/2021  
Query raised by DFO (Alibag) on:18/01/2022  
Replied by UA on :27/01/2022  
Query raised by DFO (Alibag) on:02/02/2022  
Replied by UA on :16/02/2022  
Query raised by DFO (Alibag) on:21/02/2022  
Replied by UA on :13/04/2022  
Query raised by DFO (Alibag) on:24/05/2022  
Replied by UA on :31/05/2022  
Query raised by DFO (Alibag) on:14/09/2022  
Replied by UA on :13/10/2022  
Query raised by DFO (Alibag) on:17/10/2022  
Replied by UA on :20/10/2022  
Query raised by DFO (Alibag) on:20/10/2022  
Replied by UA on :26/04/2023  
Query raised by DFO (Alibag) on:11/09/2023  
Replied by UA on :12/06/2024  
Query raised by DFO (Alibag) on:30/10/2024  
Replied by UA on :21/08/2025  
NOTE:- Proposal is pending at Regional Office .