A. General Details
  (i). Proposal No. : FP/MH/ROAD/148050/2021              (ii). Name of Project for which Forest Land is required : Construction of Balkum to Gaimukh DP Road (NH3 Connector Ghodbunder By-Pass) by Thane Municipal Corporation              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The DP road is proposed to start from Kharegaon Toll Naka at Mumbai Nashik Highway (NH-3) and ends at Ghodbunder Road (SH-42) near Gaimukh. The part of road section near Kharegaon Toll Naka is integrated with existing interchange facility available on NH-3. The part of road section near Ghodbunder              (iv). File no. : FC-II/MH-213/2023-NGP              (v). State : Maharashtra              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 12.2607
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MH/ROAD/148050/202105/10/202105/10/2021   08/10/2021   16/10/2021   30/10/2021 Mangrove :02/11/2021Mangrove:
  20/02/2023 (Mangrove)

Maharashtra:
01/03/2023
Maharashtra:
15/03/2023
Nagpur:
27/03/2023
24/11/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:06/06/2023  
Replied by State Government(Maharashtra) on:22/09/2023  
Query raised by State Government (Maharashtra) on:07/06/2023  
Replied by Nodal Officer (Maharashtra) on:13/09/2023  
Query raised by Nodal Officer (Maharashtra) on:08/06/2023  
Replied by Circle(Mangrove) on:25/08/2023  
Query raised by Circle (Mangrove) on:20/06/2023  
Replied by DFO (Mangrove) on:03/08/2023  
Query raised by DFO (Mangrove) on:21/12/2021  
Replied by UA on :06/12/2022  
Query raised by DFO (Mangrove) on:03/01/2023  
Replied by UA on :15/01/2023  
Query raised by DFO (Mangrove) on:27/06/2023  
Replied by UA on :04/07/2023  
Query raised by DFO (Mangrove) on:13/07/2023  
Replied by UA on :19/07/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .