Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (CCF Northern Circle)
|
EDS
|
DFO (Kozhikode)
|
21/08/2020
|
felled tree details to be fill the form II
|
|
2
|
DFO (Kozhikode)
|
REPLY
|
CF (CCF Northern Circle)
|
22/09/2020
|
The details has been corrected and pro[posal submitted herewith for procesing
|
|
3
|
CF (CCF Northern Circle)
|
EDS
|
DFO (Kozhikode)
|
09/11/2020
|
CA scheme should be prepared for 10 years. Site inspection report and recommendation should be detailed.
|
|
4
|
DFO (Kozhikode)
|
REPLY
|
CF (CCF Northern Circle)
|
21/01/2021
|
The required changes have been made
|
|
5
|
Nodal Officer
|
EDS
|
CF (CCF Northern Circle)
|
01/02/2021
|
Correct errors and resubmit
|
|
6
|
CF (CCF Northern Circle)
|
REPLY
|
Nodal Officer
|
02/02/2021
|
Required corrections have been made
|
|
7
|
Nodal Officer
|
EDS
|
CF (CCF Northern Circle)
|
26/02/2021
|
Correct the site inspection report of CCF as well as recommendation of CCF and DFO
|
|
8
|
CF (CCF Northern Circle)
|
REPLY
|
Nodal Officer
|
26/02/2021
|
Site inspection report of CCF has been updated. The recommendation of CCF and DFO may be updated through nic
|
|
9
|
Nodal Officer
|
EDS
|
CF (CCF Northern Circle)
|
25/03/2021
|
Site suitability certificate is not seen with CA
|
|
10
|
CF (CCF Northern Circle)
|
EDS
|
DFO (Kozhikode)
|
25/03/2021
|
Include Site Suitability Certificate for CA Scheme
|
|
11
|
DFO (Kozhikode)
|
REPLY
|
CF (CCF Northern Circle)
|
25/03/2021
|
Corrections made
|
|
12
|
CF (CCF Northern Circle)
|
REPLY
|
Nodal Officer
|
25/03/2021
|
Corrections made
|
|
13
|
Nodal Officer
|
EDS
|
CF (CCF Northern Circle)
|
25/03/2021
|
georeferenced map of ca site is wrong
|
|
14
|
CF (CCF Northern Circle)
|
EDS
|
DFO (Kozhikode)
|
25/03/2021
|
georeferenced map of ca site is wrong
|
|
15
|
DFO (Kozhikode)
|
REPLY
|
CF (CCF Northern Circle)
|
25/03/2021
|
Corrected
|
|
16
|
CF (CCF Northern Circle)
|
REPLY
|
Nodal Officer
|
25/03/2021
|
Corrections made
|
|
17
|
Nodal Officer
|
EDS
|
CF (CCF Northern Circle)
|
26/05/2021
|
Please submit the KML file of the non forest land for CA after verification.
|
|
18
|
CF (CCF Northern Circle)
|
EDS
|
DFO (Kozhikode)
|
09/06/2021
|
Please submit the KML file of the non forest land for CA after verification.
|
|
19
|
DFO (Kozhikode)
|
EDS
|
User Agency (dirkhtc@kseb.in)
|
09/06/2021
|
Please submit the KML file of the non forest land for CA . letter from the HQ is attached here.
|
|
20
|
User Agency (dirkhtc@kseb.in)
|
REPLY
|
DFO (Kozhikode)
|
29/06/2021
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Kozhikode)
|
REPLY
|
CF (CCF Northern Circle)
|
30/06/2021
|
completed the up loading by UA .Resubmitted
|
|
22
|
CF (CCF Northern Circle)
|
EDS
|
DFO (Kozhikode)
|
09/07/2021
|
The non-forest land identified for CA seems to be part of forest. Get it verified and if confirmed to be part of forest the User Agency may be asked to provide alternate land.
|
|
23
|
DFO (Kozhikode)
|
REPLY
|
CF (CCF Northern Circle)
|
05/11/2021
|
submitted area is a part of forest. hence please submit the details of another suitable land,
|
|
24
|
CF (CCF Northern Circle)
|
EDS
|
DFO (Kozhikode)
|
23/11/2021
|
Please return the proposal to User Agency for uploading the CA land
|
|
25
|
DFO (Kozhikode)
|
EDS
|
User Agency (dirkhtc@kseb.in)
|
23/11/2021
|
CA land submitted is a part of forest. hence please submit the details of another suitable non forest land may be uploaded
|
|
26
|
User Agency (dirkhtc@kseb.in)
|
REPLY
|
DFO (Kozhikode)
|
27/04/2022
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Kozhikode)
|
EDS
|
User Agency (dirkhtc@kseb.in)
|
06/05/2022
|
No objction certificate from the competent authority has to be otained . pl. submit
|
|
28
|
User Agency (dirkhtc@kseb.in)
|
REPLY
|
DFO (Kozhikode)
|
16/09/2022
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Kozhikode)
|
EDS
|
User Agency (dirkhtc@kseb.in)
|
13/10/2022
|
The tax receipts submitted are different. You are directed to submit the correct land tax receipts
|
|
30
|
User Agency (dirkhtc@kseb.in)
|
REPLY
|
DFO (Kozhikode)
|
14/10/2022
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Kozhikode)
|
EDS
|
User Agency (dirkhtc@kseb.in)
|
08/11/2022
|
User agency given CA land details on submitted for further approval
|
|
32
|
User Agency (dirkhtc@kseb.in)
|
REPLY
|
DFO (Kozhikode)
|
08/11/2022
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Kozhikode)
|
REPLY
|
CF (CCF Northern Circle)
|
08/11/2022
|
CA land uploaded ,Land verified by the South Wayanad division .
|
|
34
|
CF (CCF Northern Circle)
|
REPLY
|
Nodal Officer
|
18/11/2022
|
KML File uploaded. The sanction order of KSEB regarding their willingness to transfer 1.9801 Ha land for compensatory afforestation is enclosed. DFO South Wayanad has informed that proposed land for CA is under the ownership of KSEB.
|
|
35
|
Nodal Officer
|
EDS
|
CF (CCF Northern Circle)
|
31/01/2023
|
Furnish the remarks
|
|
36
|
CF (CCF Northern Circle)
|
REPLY
|
Nodal Officer
|
04/02/2023
|
The remarks with regard to the letter G2-4119/2021 dated 07-01-2023 of DFO South Wayanad, is attached here with for further necessary action.
|
|
37
|
Nodal Officer
|
EDS
|
CF (CCF Northern Circle)
|
24/02/2023
|
Details of CA Land May be added
|
|
38
|
CF (CCF Northern Circle)
|
EDS
|
DFO (Kozhikode)
|
24/02/2023
|
Details of CA Land May be added
|
|
39
|
DFO (Kozhikode)
|
REPLY
|
CF (CCF Northern Circle)
|
24/02/2023
|
Details of CA is uploaded
|
|
40
|
CF (CCF Northern Circle)
|
REPLY
|
Nodal Officer
|
24/02/2023
|
Details of Compensatory Afforestation Land is uploaded By DFO
|
|
41
|
Regional Office
|
EDS
|
State secretary
|
24/03/2023
|
Justification, alternatives, DPR, clarification on CA land etc
|
|
42
|
State secretary
|
EDS
|
Nodal Officer
|
12/04/2023
|
for furnishing the details sought by GoI
|
|
43
|
Nodal Officer
|
EDS
|
CF (CCF Northern Circle)
|
27/04/2023
|
The query raised by Regional Office, Bangalore may be replied to. The UA may be asked to furnish the particulars against Sl. No. 1 to 4 and the DFO Kozhikode may be asked to provide the response for Sl. No. 5
|
|
44
|
CF (CCF Northern Circle)
|
EDS
|
DFO (Kozhikode)
|
27/04/2023
|
Refer the EDS letter from the regional office enclosed herewith. DFO Kozhikkode is to be covey to the user agency to furnish the reply to the queries 1 to 4. Query No 5 may be addressed by DFO KKD.
|
|
45
|
DFO (Kozhikode)
|
EDS
|
User Agency (dirkhtc@kseb.in)
|
27/04/2023
|
Kindly furnish the detials of quries 1 to 4 and resubmit
|
|
46
|
User Agency (dirkhtc@kseb.in)
|
REPLY
|
DFO (Kozhikode)
|
28/04/2023
|
The correction have been made as per the instruction received
|
|
47
|
DFO (Kozhikode)
|
EDS
|
User Agency (dirkhtc@kseb.in)
|
12/05/2023
|
Kindly upload the details sought in letter No. FC1-713/2021 dated 24.02.2023 of APCCF, Nodal Officer, FA Act & ECO, CAMPA
|
|
48
|
User Agency (dirkhtc@kseb.in)
|
REPLY
|
DFO (Kozhikode)
|
12/05/2023
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Kozhikode)
|
EDS
|
User Agency (dirkhtc@kseb.in)
|
12/05/2023
|
please clarify the queries sought from Nodal Offcier , & CEO CAMPA, as per letter No, FC1 -713/2021 dated 24.2.2023
|
|
50
|
User Agency (dirkhtc@kseb.in)
|
REPLY
|
DFO (Kozhikode)
|
12/05/2023
|
The correction have been made as per the instruction received
|
|
51
|
DFO (Kozhikode)
|
REPLY
|
CF (CCF Northern Circle)
|
12/05/2023
|
It is precribed in managemnet plan of Malabar Wild Life Sanctuary to remove the weed growth and augment the Chootuhupara area proposed for d augmnet the area. The details of the same is attached herewith in pdf format
|
|
52
|
CF (CCF Northern Circle)
|
EDS
|
DFO (Kozhikode)
|
12/05/2023
|
Returned for correction
|
|
53
|
DFO (Kozhikode)
|
REPLY
|
CF (CCF Northern Circle)
|
12/05/2023
|
The degraded forest land proposed for compensatory afforestation is a part Malabar wildlife sanctuary and managed by valid management plan. Planting is prescribed for the proposed area. Details are provided separately in pdf format.
|
|
54
|
CF (CCF Northern Circle)
|
REPLY
|
Nodal Officer
|
17/05/2023
|
Reply received from User Agency and DFO Kozhikode pertaining to the query raised by regional office, Banglore is attached here with for further necessary action.
|
|
55
|
Nodal Officer
|
REPLY
|
State secretary
|
22/05/2023
|
The queries raised by MoEFCC are replied by the User Agency and the DFO concerned. The copies of their reply are enclosed. The same may be forwarded to MoEFCC for consideration and according clearance.
|
|
56
|
State secretary
|
REPLY
|
Regional Office
|
23/05/2023
|
The queries raised by MoEFCC are replied by the User Agency and the DFO concerned. The copies of their reply are enclosed. The same is forwarded to MoEFCC for consideration and according clearance.
|
|
57
|
RO/HQ
|
EDS
|
( ROBANG )
|
22/08/2024
|
EDS
|
|
58
|
Regional Office
|
EDS
|
State secretary
|
23/08/2024
|
Ministry vide letter dated 16.02.2024 requested the State Government to
provide the details of the hydro-electric projects in the river basin along with their
status.
|
|
59
|
State secretary
|
EDS
|
Nodal Officer
|
18/09/2024
|
For furnishing the details sought by the Ministry
|
|