| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Kundapur)
|
EDS
|
User Agency (eemescomudupi@gmail.com)
|
16/02/2021
|
The Part-I FC application submitted by the User Agency shows the survey numbers incorrectly. The transmission line is passing through survey numbers 198, 199 of Hebri village, but this stretch is instead shown as passing through survey no. 190 in the Part-I FC application. Please make necessary corrections and revert.
|
|
|
2
|
User Agency (eemescomudupi@gmail.com)
|
REPLY
|
DFO (Kundapur)
|
18/02/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
14/09/2021
|
Alternatives, mitigation measures of CWLW etc
|
|
|
4
|
State secretary
|
EDS
|
Nodal Officer
|
17/09/2021
|
eds
|
|
|
5
|
Nodal Officer
|
EDS
|
CF (Mangalore)
|
01/10/2021
|
please submit the information sought by GOI
|
|
|
6
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
11/10/2021
|
Kindly submit the information
|
|
|
7
|
DFO (Kundapur)
|
EDS
|
User Agency (eemescomudupi@gmail.com)
|
11/10/2021
|
Kindly submit required information ask by PCCF FC and Nodal Officer FCA Bangalore
|
|
|
8
|
User Agency (eemescomudupi@gmail.com)
|
REPLY
|
DFO (Kundapur)
|
02/02/2022
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Kundapur)
|
REPLY
|
CF (Mangalore)
|
07/02/2022
|
As per letter
|
|
|
10
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
10/02/2022
|
Kindly submit the information with DCF opinion
|
|
|
11
|
DFO (Kundapur)
|
REPLY
|
CF (Mangalore)
|
10/02/2022
|
As per letter
|
|
|
12
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
15/02/2022
|
kindly send all the documents in English language
|
|
|
13
|
DFO (Kundapur)
|
REPLY
|
CF (Mangalore)
|
04/04/2022
|
As per letter
|
|
|
14
|
CF (Mangalore)
|
REPLY
|
Nodal Officer
|
07/04/2022
|
Submitted the information sought by GOI
|
|
|
15
|
Nodal Officer
|
REPLY
|
State secretary
|
26/04/2022
|
the information here by submitted for your information
|
|
|
16
|
State secretary
|
REPLY
|
Regional Office
|
09/05/2022
|
EDS
|
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
02/06/2022
|
The proposal has been considered in the REC meeting held on 31-05-2022 and REC decided to seek certain essential information viz., i. User Agency shall explore the possibility of laying the underground cable, ii The exact number of trees to be felled, iii. Whether any existing lines can be upgraded in its existing alignment and iv. The degraded forest land identified for Compensatory Afforestation is in Chikkaballapur Division. The State Government may identify CA area in the Kundapur Division itself and furnish the details of the same including map, suitability certificate etc. Accordingly, the State Govt. has been requested vide letter dated 02-06-2022 to furnish the requisite information.
|
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
16/06/2022
|
eds
|
|
|
19
|
Nodal Officer
|
EDS
|
CF (Mangalore)
|
17/06/2022
|
please submit the information documents sought by GOI
|
|
|
20
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
20/06/2022
|
Kindly submit the information documents sought by GOI
|
|
|
21
|
DFO (Kundapur)
|
EDS
|
User Agency (eemescomudupi@gmail.com)
|
05/07/2022
|
as per letter
|
|
|
22
|
User Agency (eemescomudupi@gmail.com)
|
REPLY
|
DFO (Kundapur)
|
23/01/2023
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Kundapur)
|
REPLY
|
CF (Mangalore)
|
19/06/2023
|
As per letter
|
|
|
24
|
CF (Mangalore)
|
REPLY
|
Nodal Officer
|
16/12/2023
|
Submitted the information sought by GOI
|
|
|
25
|
Nodal Officer
|
EDS
|
CF (Mangalore)
|
12/04/2024
|
The user agency has uploaded the Withdraw letter through online hence you are directed to inspect the site and submi the report
|
|
|
26
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
06/05/2024
|
UA withdrawn the project
|
|