TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/TRANS/42309/2019              (ii). Name of Project for which Forest Land is required : Re Diversion and change in land use of 7.53 Ha forest land for 220 kV Transmission line work of Upper Bhadra Project, Package-1 from diverted forest land of Upper Tunga Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Upper Bhadra Project is a major lift irrigation scheme under implementation in the central region of Karnataka State. It envisages lifting of water in first stage from Tunga to Bhadra and lifting of water in second stage from Bhadra reservoir and providing it to Tunnel near Ajjampura through gravity              (iv). State : Karnataka              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 7.53
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/TRANS/42309/201901/10/201917/10/2019   27/11/2019   02/01/2020   14/01/2020

Shimoga :20/01/2020


Koppa :20/01/2020

Chikkamagalur:
  17/11/2020 (Koppa)

Shimoga:
  21/11/2020 (Shimoga)

Karnataka:
08/12/2020
Karnataka:
19/04/2021
Bangalore:
16/06/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:02/07/2021  
Query raised by State Government (Karnataka) on:31/08/2021  
Query raised by Nodal Officer (Karnataka) on:19/01/2021  
Replied by Circle(Chikkamagalur) on:27/01/2021  
Query raised by Nodal Officer (Karnataka) on:19/01/2021  
Replied by Circle(Shimoga) on:04/03/2021  
Query raised by Nodal Officer (Karnataka) on:15/03/2021  
Replied by Circle(Chikkamagalur) on:18/03/2021  
Query raised by Nodal Officer (Karnataka) on:02/09/2021  
Replied by Circle(Chikkamagalur) on:15/12/2022  
Query raised by Nodal Officer (Karnataka) on:02/09/2021  
Replied by Circle(Shimoga) on:21/12/2022  
Query raised by Nodal Officer (Karnataka) on:30/01/2023  
Replied by Circle(Shimoga) on:24/01/2025  
Query raised by Nodal Officer (Karnataka) on:30/01/2023  
Replied by Circle(Chikkamagalur) on:29/01/2025  
Query raised by Circle (Shimoga) on:21/11/2020  
Replied by DFO (Shimoga) on:26/11/2020  
Query raised by Circle (Shimoga) on:26/11/2020  
Replied by DFO (Shimoga) on:26/11/2020  
Query raised by Circle (Shimoga) on:25/01/2021  
Replied by DFO (Shimoga) on:02/03/2021  
Query raised by Circle (Chikkamagalur) on:16/03/2021  
Replied by DFO (Koppa) on:17/03/2021  
Query raised by Circle (Shimoga) on:04/09/2021  
Replied by DFO (Shimoga) on:18/11/2022  
Query raised by Circle (Chikkamagalur) on:07/09/2021  
Replied by DFO (Koppa) on:30/11/2022  
Query raised by Circle (Shimoga) on:31/01/2023  
Replied by DFO (Shimoga) on:17/01/2025  
Query raised by Circle (Shimoga) on:24/01/2025  
Replied by DFO (Shimoga) on:24/01/2025  
Query raised by DFO (Shimoga) on:19/05/2020  
Replied by UA on :22/05/2020  
Query raised by DFO (Koppa) on:26/06/2020  
Replied by UA on :09/09/2020  
Query raised by DFO (Shimoga) on:09/11/2022  
Replied by UA on :10/11/2022  
Query raised by DFO (Shimoga) on:08/01/2025  
Replied by UA on :09/01/2025  
Query raised by DFO (Shimoga) on:24/01/2025  
Replied by UA on :24/01/2025  
Query raised by DFO (Shimoga) on:24/01/2025  
Replied by UA on :24/01/2025  
NOTE:- Proposal is pending at Nodal Officer due to EDS raised by Regional Office .