  (i). Proposal No. : FP/KA/Others/21113/2016              (ii). Name of Project for which Forest Land is required : Murnad power substation              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Renewal of lease for the existing 33kv station at kodamburu.              (iv). State : Karnataka              (v). Category of the Project : Others              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.4
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/Others/21113/201606/09/201606/10/2018  16/03/2018  19/10/2016  01/10/2016  19/09/2016   01/04/2019  05/10/2018  27/10/2016  04/10/2016  20/09/2016   19/11/2016   25/01/2018 Madikeri :18/05/2019Kodagu:
  31/08/2020 (Madikeri)

Karnataka:
19/10/2020
Karnataka:
02/01/2021
Bangalore:
15/07/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:18/08/2021  
Query raised by State Government (Karnataka) on:09/02/2021  
Replied by Nodal Officer (Karnataka) on:23/02/2021  
Query raised by State Government (Karnataka) on:08/04/2022  
Query raised by Nodal Officer (Karnataka) on:16/05/2022  
Replied by Circle(Kodagu) on:03/04/2025  
Query raised by Nodal Officer (Karnataka) on:28/08/2025  
Replied by Circle() on:  
Query raised by Circle (Kodagu) on:14/07/2022  
Replied by DFO (Madikeri) on:12/02/2025  
Query raised by Circle (Kodagu) on:26/03/2025  
Replied by DFO (Madikeri) on:28/03/2025  
Query raised by Circle (Kodagu) on:30/08/2025  
Replied by DFO () on:  
Query raised by DFO (Madikeri) on:28/07/2022  
Replied by UA on :04/02/2025  
Query raised by DFO (Madikeri) on:07/02/2025  
Replied by UA on :07/02/2025  
Query raised by DFO (Madikeri) on:28/03/2025  
Replied by UA on :28/03/2025  
Query raised by DFO (Madikeri) on:02/09/2025  
Replied by UA on :03/09/2025  
Query raised by DFO (Madikeri) on:06/09/2025  
Replied by UA on :11/09/2025  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .