TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/MIN/154749/2022              (ii). Name of Project for which Forest Land is required : Sarangapani Iron and Manganese Ore Mine              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 1. The present application is for seeking permission in re-grant mining area as a larger area including this area was granted to one Sri. Sarangapani Mudaliyar in 1950’s. 2. The Govt of Karnataka issued a public advertisement inviting applicants for re-grant of mining lease during 1999. 3. We appl              (iv). File no. : 8-05/2025-FC              (v). State : Karnataka              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Hybrid              (viii). Area of forest land proposed for diversion(in ha.): 48.2
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onStage-II Approval on
FP/KA/MIN/154749/202222/04/202219/05/2022   03/06/2022   15/06/2022   29/06/2022 Tumkur :30/06/2022Hassan:
  12/12/2024 (Tumkur)

Karnataka:
30/12/2024
Karnataka:
02/06/2025
07/08/2025
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 05/09/2025  
Query raised by State Government (Karnataka) on:10/09/2025  
Query raised by Nodal Officer (Karnataka) on:20/01/2025  
Replied by Circle(Hassan) on:06/02/2025  
Query raised by Circle (Hassan) on:21/01/2025  
Replied by DFO (Tumkur) on:05/02/2025  
Query raised by DFO (Tumkur) on:30/07/2022  
Replied by UA on :26/12/2022  
Query raised by DFO (Tumkur) on:31/01/2023  
Replied by UA on :14/09/2023  
Query raised by DFO (Tumkur) on:05/04/2024  
Replied by UA on :01/10/2024  
Query raised by DFO (Tumkur) on:15/10/2024  
Replied by UA on :18/10/2024  
Query raised by DFO (Tumkur) on:29/11/2024  
Replied by UA on :29/11/2024  
Query raised by DFO (Tumkur) on:07/12/2024  
Replied by UA on :10/12/2024  
Query raised by DFO (Tumkur) on:22/01/2025  
Replied by UA on :29/01/2025  
NOTE:- Proposal is pending at Nodal Officer due to EDS raised by Head Office .