Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Koppal)
|
EDS
|
User Agency (natesh@mspllimited.com)
|
14/03/2019
|
according to G.O. no. apj 88 fll 2016,bangalore dated 31/08/2016,private user agencies have to purchase land adjacent to forest land & hand over to forest dept for compensatory afforestation. user agency has proposed govt. C&D land for compensatory afforestation, which is not according to the said G.O. please propose the CA land as per the guidelines of the said G.O.
|
|
2
|
User Agency (natesh@mspllimited.com)
|
REPLY
|
DFO (Koppal)
|
21/03/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Koppal)
|
EDS
|
User Agency (natesh@mspllimited.com)
|
21/07/2020
|
CA LAND SHOULD BE IDENTIFY AS PER 2016 GOVERNMENT ORDER. AND SUITABLE CERTIFICATE FOR CA LAND SHOLD BE OBTAINED FORM DAVANAGERA DIVISION
|
|
4
|
User Agency (natesh@mspllimited.com)
|
REPLY
|
DFO (Koppal)
|
18/08/2020
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
22/01/2021
|
EDS query regarding CA land
|
|
6
|
CF (Bellary)
|
EDS
|
DFO (Koppal)
|
27/01/2021
|
EDS as raised by the Nodal Officer should be submitted.
|
|
7
|
DFO (Koppal)
|
EDS
|
User Agency (natesh@mspllimited.com)
|
09/04/2021
|
Ensure that necessary modifications / Corrections, wherever warranted, are incorporated in relevant items of pART-1 on FC web portal.
|
|
8
|
User Agency (natesh@mspllimited.com)
|
REPLY
|
DFO (Koppal)
|
10/04/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Koppal)
|
REPLY
|
CF (Bellary)
|
06/07/2021
|
As per directions of Nodal Office the link is forwarded to Circle Office and reply for EDS query will be submitted by the offline letter
|
|
10
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
12/07/2021
|
As per the directions issued by the Nodal Officer in the letter No.A5(4).GFL.CR-13/2017-18 dated:12-07-2021, to forwarded the online link to their login. Hence, the link in forwarded herewith.
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
01/04/2022
|
State Government has been requested vide IRO letter 31-03-2022 to furnish the details, information viz., alternatives examined, feasibility of laying pipeline on elevated structure so as to minimize the felling of trees, relocating the location of break pressure tank to non-forest area or periphery of the forest area, validity of consent given by Water Resources Dept. for drawl of water from Tungabhadra river, revised CA scheme for 10 years as per FC guidelines, FRA compliance certificate in proper format, resolving the discrepancies in the uploaded KML file.
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
19/04/2022
|
eds
|
|
13
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
27/04/2022
|
communication of the EDS Query
|
|
14
|
CF (Bellary)
|
EDS
|
DFO (Koppal)
|
23/05/2022
|
Submit the EDS as sought for by the Nodal Officer.
|
|
15
|
DFO (Koppal)
|
EDS
|
User Agency (natesh@mspllimited.com)
|
23/05/2022
|
Submit the pointwise details with documents as query raised by the nodal officer as early as possible.
|
|
16
|
User Agency (natesh@mspllimited.com)
|
REPLY
|
DFO (Koppal)
|
19/11/2022
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Koppal)
|
REPLY
|
CF (Bellary)
|
07/12/2022
|
THE REVISED COMPLIENCE REPORT SUBMITTED AGAIST THE QUERY RAISED BY THE NODAL OFFICER.
|
|
18
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
12/12/2022
|
Additional information submitted as per your office letter dt. 27-4-2022
|
|
19
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
24/01/2023
|
You are hereby directed to obtained and submit the GoI required information
|
|
20
|
CF (Bellary)
|
EDS
|
DFO (Koppal)
|
03/02/2023
|
Submit replies to EDS Query .
|
|
21
|
DFO (Koppal)
|
EDS
|
User Agency (natesh@mspllimited.com)
|
16/02/2023
|
Respond to objections
|
|
22
|
User Agency (natesh@mspllimited.com)
|
REPLY
|
DFO (Koppal)
|
19/04/2023
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Koppal)
|
EDS
|
User Agency (natesh@mspllimited.com)
|
24/04/2023
|
area, kml file and annexures
|
|
24
|
User Agency (natesh@mspllimited.com)
|
REPLY
|
DFO (Koppal)
|
01/07/2023
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Koppal)
|
EDS
|
User Agency (natesh@mspllimited.com)
|
15/09/2023
|
Please provide CA land as per the G.O. number APG 88 FLL 2016, Bengaluru dated 31/08/2016, wherein it is mentioned that private organizations can not provide govt. lands for CA.
|
|
26
|
User Agency (natesh@mspllimited.com)
|
REPLY
|
DFO (Koppal)
|
09/10/2023
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Koppal)
|
REPLY
|
CF (Bellary)
|
22/11/2023
|
The replies have been submitted against EDS query
|
|
28
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
07/12/2023
|
Addl. information submitted
|
|
29
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
25/01/2024
|
EDS query regarding Overlapping
|
|
30
|
CF (Bellary)
|
EDS
|
DFO (Koppal)
|
30/01/2024
|
Directed to take immediate action as per instructions of the nodal officer and submit the report.
|
|
31
|
DFO (Koppal)
|
EDS
|
User Agency (natesh@mspllimited.com)
|
01/02/2024
|
PLEASE SUBMIT THE REPORT / NOC AS PER EDS RAISED BY NODAL OFFICER.
|
|
32
|
User Agency (natesh@mspllimited.com)
|
REPLY
|
DFO (Koppal)
|
03/02/2024
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Koppal)
|
REPLY
|
CF (Bellary)
|
03/02/2024
|
THE REPAY FOR EDS RAISED BY NODAL OFFICER HAS BEEN SUBMITTED.
|
|
34
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
16/02/2024
|
Information submitted
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
22/03/2024
|
EDS reply
|
|
36
|
State secretary
|
REPLY
|
Regional Office
|
09/05/2024
|
eds
|
|
37
|
Regional Office
|
EDS
|
State secretary
|
30/05/2024
|
State Govt. has been requested vide letter dtd 29.05.2024 to make necessary change in the Part-I, since the user agency name has been changed, clarification on the no. of trees to be felled due to change in alignment etc.
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
09/07/2024
|
eds
|
|
39
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
19/07/2024
|
eds query
|
|
40
|
CF (Bellary)
|
EDS
|
DFO (Koppal)
|
21/08/2024
|
Submit the asked information
|
|
41
|
DFO (Koppal)
|
EDS
|
User Agency (natesh@mspllimited.com)
|
04/09/2024
|
EDS query
|
|
42
|
User Agency (natesh@mspllimited.com)
|
REPLY
|
DFO (Koppal)
|
06/09/2024
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Koppal)
|
EDS
|
User Agency (natesh@mspllimited.com)
|
10/09/2024
|
EDS QUERRY
|
|
44
|
User Agency (natesh@mspllimited.com)
|
REPLY
|
DFO (Koppal)
|
19/09/2024
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Koppal)
|
REPLY
|
CF (Bellary)
|
05/12/2024
|
As per DCF Koppal letter dated 5/12/2024 reply has been sent regarding four points of queries raised by MoEF&CC Bangalore.
|
|
46
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
17/12/2024
|
Information submitted
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
20/01/2025
|
The EDS reply is submitted for further needfull action
|
|
48
|
State secretary
|
REPLY
|
Regional Office
|
28/01/2025
|
eds
|
|