Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (executiveengineer61@yahoo.in)
|
24/09/2020
|
Kindly fix a date for joint inspection and intimate to this office
|
|
2
|
User Agency (executiveengineer61@yahoo.in)
|
REPLY
|
DFO (Jammu Forest Division)
|
19/11/2020
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
10/12/2020
|
Kindly modify the detail of trees/poles/saplings within 2 days.
|
|
4
|
CF (East Circle Jammu)
|
EDS
|
DFO (Jammu Forest Division)
|
17/12/2020
|
kindly modify the details of trees ,poles and saplings
|
|
5
|
DFO (Jammu Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
18/12/2020
|
Sir, Trees details have been updated
|
|
6
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
19/12/2020
|
Sir. As desired, the Trees detail have been updated.
|
|
7
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
24/12/2020
|
Kindly upload the detail of trees/poles/saplings involved in the proposed project in part-II of Form-A as per the enumeration of the trees/poles/saplings
|
|
8
|
CF (East Circle Jammu)
|
EDS
|
DFO (Jammu Forest Division)
|
24/12/2020
|
Upload the detail of trees/poles/saplings involved in the proposed project in part-II of Form-A as per the enumeration of the trees/poles/saplings
|
|
9
|
DFO (Jammu Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
24/12/2020
|
details of trees/poles/sapling have been uploaded on parivesh portal in part-II as per the enumeration list
|
|
10
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
24/12/2020
|
Sir, As desired ,the details have been updated.
|
|
11
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
02/01/2021
|
Kindly upload the requisite information please.
|
|
12
|
CF (East Circle Jammu)
|
EDS
|
DFO (Jammu Forest Division)
|
02/01/2021
|
Upload the requisite information.
|
|
13
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (executiveengineer61@yahoo.in)
|
08/01/2021
|
As directed by higher authorites,kindly find enclosed h herewith the letter wherein user agency are required to upload documents on Parivesh portal.
|
|
14
|
User Agency (executiveengineer61@yahoo.in)
|
REPLY
|
DFO (Jammu Forest Division)
|
15/01/2021
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (executiveengineer61@yahoo.in)
|
22/01/2021
|
Kindly refer this office letter no5208-12 Dt07-01-21,wherein you are required to upload/submit the information on parivesh portal, since the desired information has not been uploaded/submitted by your office .As such you are requested to do the same
|
|
16
|
User Agency (executiveengineer61@yahoo.in)
|
REPLY
|
DFO (Jammu Forest Division)
|
22/01/2021
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Jammu Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
27/01/2021
|
Sir, As desired all the required documents have been uploaded on parivesh portal.
|
|
18
|
CF (East Circle Jammu)
|
EDS
|
DFO (Jammu Forest Division)
|
28/01/2021
|
please provide the checklists signed by DFO and UA,authourity letter of UA with name ,Calculation area and layout plan with dimensions.
|
|
19
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (executiveengineer61@yahoo.in)
|
29/01/2021
|
lease provide the checklists signed by DFO and UA,authourity letter of UA with name ,Calculation area and layout plan with dimensions.
|
|
20
|
User Agency (executiveengineer61@yahoo.in)
|
REPLY
|
DFO (Jammu Forest Division)
|
29/01/2021
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (executiveengineer61@yahoo.in)
|
29/01/2021
|
please provide the checklists signed by DFO and UA,authourity letter of UA with name ,Calculation area and layout plan with dimensions
|
|
22
|
User Agency (executiveengineer61@yahoo.in)
|
REPLY
|
DFO (Jammu Forest Division)
|
30/01/2021
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (executiveengineer61@yahoo.in)
|
02/02/2021
|
Kindly upload docuents as per Check list and Calculation area and layout plan with dimensions.
|
|
24
|
User Agency (executiveengineer61@yahoo.in)
|
REPLY
|
DFO (Jammu Forest Division)
|
02/02/2021
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Jammu Forest Division)
|
EDS
|
User Agency (executiveengineer61@yahoo.in)
|
04/02/2021
|
Sir, Kindly upload GEO-Reference Map of the road
|
|
26
|
User Agency (executiveengineer61@yahoo.in)
|
REPLY
|
DFO (Jammu Forest Division)
|
04/02/2021
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Jammu Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
04/02/2021
|
Sir, the all the documents have been uploaded as per the instructions
|
|
28
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
05/02/2021
|
The requisite information have been uploaded as per EDS.
|
|
29
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
05/02/2021
|
The requisite information have been uploaded as per EDS.
|
|