Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Latehar)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
01/09/2020
|
Report after compliance.
|
|
2
|
DFO (Chatra South)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
03/02/2021
|
The proposal received in the divisional office hase many defects and shortcomings and list of the same containing 08 points has been communicated to the User Agency for defects removal and compliance vide the divisional office letter no. 395 dated 29.01.2021. The compliance is pending at User Agency Level.
|
|
3
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Latehar)
|
11/02/2021
|
The correction have been made as per the instruction received
|
|
4
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
11/02/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Latehar)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
20/02/2021
|
Report after compliance. Letter No. 311 dated 20.02.2021 attached.
|
|
6
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Latehar)
|
22/02/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Latehar)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
24/02/2021
|
Letter No. 348 dated 24.02.2021 attached.
|
|
8
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Latehar)
|
12/03/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Chatra South)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
13/03/2021
|
Proposal submitted by User Agency is incomplete in many respects about which the user agency has been communicated by DFO letter No. 335 dated 29.01.2021. The user agency has to submit the proposal complete in all respects without delay. No compliance by user agency in respect of the DFO aforesaid letter has been submitted so far to the office of DFO. The matter is pending at U.A. Level.
|
|
10
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
22/04/2021
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Chatra South)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
27/05/2021
|
The user agency was communicated vide DFO Letter No. 335 dated 29.01.2021 about the shortcomings and incompleteness of the proposal. The user agency , in response to his letter no. NKTLs/2020-21/F115 dated 22.04.2021 has been once again requested vide DFO letter no. 1322 dated 15.05.2021 to submit the proposal complete in all respects, which has yet not been submitted by user agency. The submission of offline proposal by user agency- is also pending at the level of User agency.
|
|
12
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
28/06/2021
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Chatra South)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
08/07/2021
|
The user agency was communicated vide DFO Letter No. 335 dated 29.01.2021 about the shortcomings and incompleteness of the proposal. The user agency , in response to his letter no. NKTLs/2020-21/F115 dated 22.04.2021 has been once again requested vide DFO letter no. 1322 dated 15.05.2021 to submit the proposal complete in all respects, which has yet not been submitted by user agency. The submission of offline proposal by user agency- is also pending at the level of User agency.
|
|
14
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
13/07/2021
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Chatra South)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
20/07/2021
|
The user agency was communicated vide DFO Letter No. 335 dated 29.01.2021 about the shortcomings and incompleteness of the proposal. The user agency , in response to his letter no. NKTLS/2020-21/F122 dated 13.07.2021 has been once again requested vide DFO letter no. 1770 dated 16.07.2021 to submit the proposal complete in all respects, which has yet not been submitted by user agency. The submission of offline proposal by user agency- is also pending at the level of User agency.
|
|
16
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
14/09/2021
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Chatra North)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
19/10/2021
|
Query Letter Attached
|
|
18
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra North)
|
11/12/2021
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Chatra South)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
23/12/2021
|
The divisional office cannot make any correction in the amended forest area of forest land diversion application. The user agency has to do it itself by submitting an online request to the system direction of GoI and therefore the online proposal in this regard is returned to do needful at the level of user agency.
|
|
20
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
16/02/2022
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Chatra North)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
06/08/2022
|
Query letter attached
|
|
22
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra North)
|
18/08/2022
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Chatra North)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
22/08/2022
|
Letter Attached
|
|
24
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra North)
|
30/08/2022
|
The correction have been made as per the instruction received
|
|
25
|
CF (Chatra)
|
EDS
|
DFO (Chatra South)
|
07/09/2022
|
uploaded recommendation is wrong. Please correct recommendation uploaded
|
|
26
|
DFO (Chatra South)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
08/09/2022
|
The proposal still showing at the level of DFO has been returned to the user agency vide DFO Letter no. 1957 dated 08.09.2022 for uploading revised signed documents by the user agency.
|
|
27
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
11/09/2022
|
The correction have been made as per the instruction received
|
|
28
|
DFO (Chatra South)
|
REPLY
|
CF (Chatra)
|
13/09/2022
|
The correction have been made as per the instruction received
|
|
29
|
CF (Chatra)
|
EDS
|
DFO (Chatra North)
|
16/09/2022
|
online part II Para 14 of column Forest Land including penal C.A in hect. - 0 but progress of compensatory afforestation as on date 31.07..2022 forest land 771.03 Hect. please correct data fill up and submit online proposal
|
|
30
|
DFO (Chatra North)
|
REPLY
|
CF (Chatra)
|
16/09/2022
|
The correction have been made as per the instruction received
|
|
31
|
State secretary
|
EDS
|
Nodal Officer
|
21/10/2022
|
Comment of CWLW Jharkhand has been sought.
|
|
32
|
Nodal Officer
|
EDS
|
CF (Chatra)
|
02/11/2022
|
Please take note on EDS by GOJ
|
|
33
|
Nodal Officer
|
EDS
|
CF (Daltonganj)
|
02/11/2022
|
Please take note on EDS by GOJ
|
|
34
|
CF (Chatra)
|
EDS
|
DFO (Chatra North)
|
04/11/2022
|
Please take note on EDS by GOJ
|
|
35
|
CF (Chatra)
|
EDS
|
DFO (Chatra South)
|
04/11/2022
|
Please take note on EDS by GOJ
|
|
36
|
DFO (Chatra North)
|
REPLY
|
CF (Chatra)
|
14/11/2022
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Chatra South)
|
REPLY
|
CF (Chatra)
|
19/11/2022
|
The report regarding the requirement of the site specific Wildlife Management in respect of Chandwa Gaya 400 KV DC Line proposal of MS NKTL was sent to CF Chatra vide DFO letter No. 2606 dated 18.10.2022.
|
|
38
|
CF (Chatra)
|
REPLY
|
Nodal Officer
|
19/11/2022
|
The report regarding the requirement of the site specific Wildlife Management in respect of Chandwa Gaya 400 KV DC Line proposal of MS NKTL was sent to RCCF Hazaribagh vide CF letter No. 784 dated 20.10.2022.
|
|
39
|
CF (Daltonganj)
|
REPLY
|
Nodal Officer
|
21/11/2022
|
sir,
Please see the attachment file.
|
|
40
|
Nodal Officer
|
REPLY
|
State secretary
|
29/11/2022
|
EDS Reply
|
|
41
|
Regional Office
|
EDS
|
State secretary
|
07/03/2023
|
some quarry raised
|
|
42
|
State secretary
|
EDS
|
Nodal Officer
|
14/03/2023
|
query raised by regional office.
|
|
43
|
Nodal Officer
|
EDS
|
CF (Chatra)
|
15/03/2023
|
Please take note on EDS by GOJ
|
|
44
|
Nodal Officer
|
EDS
|
CF (Daltonganj)
|
15/03/2023
|
Please take note on EDS by GOJ
|
|
45
|
CF (Chatra)
|
EDS
|
DFO (Chatra North)
|
16/03/2023
|
Please take note on EDS by GOJ
|
|
46
|
CF (Chatra)
|
EDS
|
DFO (Chatra South)
|
16/03/2023
|
Please take note on EDS by GOJ
|
|
47
|
DFO (Chatra North)
|
EDS
|
User Agency (northkaranpuratransco@gmail.com)
|
18/03/2023
|
Memo Attached
|
|
48
|
User Agency (northkaranpuratransco@gmail.com)
|
REPLY
|
DFO (Chatra North)
|
23/03/2023
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Chatra North)
|
REPLY
|
CF (Chatra)
|
19/04/2023
|
The correction have been made as per the instruction received
|
|
50
|
DFO (Chatra South)
|
REPLY
|
CF (Chatra)
|
24/04/2023
|
The correction have been made as per the instruction received
|
|
51
|
CF (Daltonganj)
|
REPLY
|
Nodal Officer
|
24/04/2023
|
Sir ,
Please see the Letter No. 231 Dated 13.04.2023
|
|
52
|
CF (Chatra)
|
REPLY
|
Nodal Officer
|
26/04/2023
|
The correction has been bade as per the instruction received
|
|
53
|
Nodal Officer
|
REPLY
|
State secretary
|
03/05/2023
|
EDS Reply
|
|
54
|
State secretary
|
REPLY
|
Regional Office
|
19/05/2023
|
Reply of query raised by letter dated 07.03.2023 being submitted.
|
|