TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/TRANS/41236/2019              (ii). Name of Project for which Forest Land is required : Construction of 400 kV D/C North Karanpura to Gaya transmission line (Jharkhand Portion)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Ministry of Power, Govt. of India has initiated a scheme for establishment of Transmission System for “Immediate Evacuation for North Karanpura (3X660MW) generation project of M/s NTPC North Karanpura. As a part of the said project a SPV is formed for Construction of Transmission system              (iv). File no. : FP/JH/TRANS/41236/2019              (v). State : Jharkhand              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 197.0115
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/JH/TRANS/41236/201920/07/201917/07/2020  14/09/2019  29/07/2019   17/07/2020  17/01/2020  13/08/2019   06/08/2020   27/08/2020 Latehar:  28/08/2020
Chatra South:  28/08/2020
Chatra North:  28/08/2020
Chatra:
  26/02/2022 (Chatra South)

Chatra:
  07/09/2022 (Chatra North)

Daltonganj:
  28/06/2021 (Latehar)

Jharkhand:
20/09/2022
Jharkhand:
29/09/2022
Ranchi:
27/01/2023
06/06/2023
By :Regional Office
Jharkhand
13/06/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Ranchi) on:07/03/2023  
Replied by State Government(Jharkhand) on:19/05/2023  
Query raised by State Government (Jharkhand) on:21/10/2022  
Replied by Nodal Officer (Jharkhand) on:29/11/2022  
Query raised by State Government (Jharkhand) on:14/03/2023  
Replied by Nodal Officer (Jharkhand) on:03/05/2023  
Query raised by Nodal Officer (Jharkhand) on:02/11/2022  
Replied by Circle(Chatra) on:19/11/2022  
Query raised by Nodal Officer (Jharkhand) on:02/11/2022  
Replied by Circle(Daltonganj) on:21/11/2022  
Query raised by Nodal Officer (Jharkhand) on:15/03/2023  
Replied by Circle(Daltonganj) on:24/04/2023  
Query raised by Nodal Officer (Jharkhand) on:15/03/2023  
Replied by Circle(Chatra) on:26/04/2023  
Query raised by Circle (Chatra) on:07/09/2022  
Replied by DFO (Chatra South) on:13/09/2022  
Query raised by Circle (Chatra) on:16/09/2022  
Replied by DFO (Chatra North) on:16/09/2022  
Query raised by Circle (Chatra) on:04/11/2022  
Replied by DFO (Chatra North) on:14/11/2022  
Query raised by Circle (Chatra) on:04/11/2022  
Replied by DFO (Chatra South) on:19/11/2022  
Query raised by Circle (Chatra) on:16/03/2023  
Replied by DFO (Chatra North) on:19/04/2023  
Query raised by Circle (Chatra) on:16/03/2023  
Replied by DFO (Chatra South) on:24/04/2023  
Query raised by DFO (Latehar) on:01/09/2020  
Replied by UA on :11/02/2021  
Query raised by DFO (Chatra South) on:03/02/2021  
Replied by UA on :11/02/2021  
Query raised by DFO (Latehar) on:20/02/2021  
Replied by UA on :22/02/2021  
Query raised by DFO (Latehar) on:24/02/2021  
Replied by UA on :12/03/2021  
Query raised by DFO (Chatra South) on:13/03/2021  
Replied by UA on :22/04/2021  
Query raised by DFO (Chatra South) on:27/05/2021  
Replied by UA on :28/06/2021  
Query raised by DFO (Chatra South) on:08/07/2021  
Replied by UA on :13/07/2021  
Query raised by DFO (Chatra South) on:20/07/2021  
Replied by UA on :14/09/2021  
Query raised by DFO (Chatra North) on:19/10/2021  
Replied by UA on :11/12/2021  
Query raised by DFO (Chatra South) on:23/12/2021  
Replied by UA on :16/02/2022  
Query raised by DFO (Chatra North) on:06/08/2022  
Replied by UA on :18/08/2022  
Query raised by DFO (Chatra North) on:22/08/2022  
Replied by UA on :30/08/2022  
Query raised by DFO (Chatra South) on:08/09/2022  
Replied by UA on :11/09/2022  
Query raised by DFO (Chatra North) on:18/03/2023  
Replied by UA on :23/03/2023  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Ranchi) on:18/07/2024  
Query raised by State Government (Jharkhand) on:31/07/2024  
Query raised by Nodal Officer on:12/08/2024  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .