TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/TRANS/150441/2021              (ii). Name of Project for which Forest Land is required : 132 KV D/C Chhatarpur Japla Transmission Line              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 132 KV D/C Chhatarpur Japla Transmission Line              (iv). State : Jharkhand              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 23.2676
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JH/TRANS/150441/202122/12/202127/12/2021   11/01/2022   18/01/2022   25/02/2022 Medininagar :28/02/2022Medininagar:
  27/06/2024 (Medininagar)

Jharkhand:
17/08/2024
Jharkhand:
10/09/2024
Ranchi:
27/12/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Ranchi) on:14/01/2025  
Query raised by State Government (Jharkhand) on:15/10/2024  
Replied by Nodal Officer (Jharkhand) on:24/10/2024  
Query raised by State Government (Jharkhand) on:29/01/2025  
Query raised by Nodal Officer (Jharkhand) on:13/02/2025  
Query raised by Circle (Medininagar) on:11/03/2025  
Query raised by DFO (Medininagar) on:13/07/2022  
Replied by UA on :31/01/2023  
Query raised by DFO (Medininagar) on:20/02/2023  
Replied by UA on :03/07/2023  
Query raised by DFO (Medininagar) on:05/10/2023  
Replied by UA on :21/03/2024  
Query raised by DFO (Medininagar) on:12/04/2025  
Replied by UA on :21/05/2025  
Query raised by DFO (Medininagar) on:02/06/2025  
Replied by UA on :10/06/2025  
Query raised by DFO (Medininagar) on:05/07/2025  
Replied by UA on :15/07/2025  
Query raised by DFO (Medininagar) on:27/12/2025  
Replied by UA on :13/02/2026  
Query raised by DFO (Medininagar) on:20/02/2026  
Replied by UA on :31/03/2026  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .