  (i). Proposal No. : FP/JH/TRANS/120412/2021              (ii). Name of Project for which Forest Land is required : 132 KV Double Circuit DVC’S Hazaribagh (Sindhur) substation to proposed TSS of East Central Railway Dhanbad at Hazaribagh transmission line.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : For Construction of 132KV DC Hazaribagh(Sindhur) substation of DVC to TSS Hazaribagh of ECR Dhanbad transmission line.              (iv). State : Jharkhand              (v). Category of the Project : Transmission Line              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 10.106
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JH/TRANS/120412/202122/01/202115/07/2021  01/02/2021   28/07/2021  06/07/2021   03/08/2021   09/02/2022 Hazaribagh West :11/02/2022Hazaribagh:
  22/10/2022 (Hazaribagh West)

Jharkhand:
03/04/2023
Jharkhand:
27/04/2023
Ranchi:
15/06/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Ranchi) on:12/07/2023  
Replied by State Government(Jharkhand) on:05/04/2024  
Query raised by Regional Office (Ranchi) on:13/05/2024  
Query raised by State Government (Jharkhand) on:24/07/2023  
Replied by Nodal Officer (Jharkhand) on:04/03/2024  
Query raised by State Government (Jharkhand) on:27/06/2024  
Replied by Nodal Officer (Jharkhand) on:06/06/2025  
Query raised by Nodal Officer (Jharkhand) on:27/07/2023  
Replied by Circle(Hazaribagh) on:28/02/2024  
Query raised by Nodal Officer (Jharkhand) on:02/07/2024  
Replied by Circle(Hazaribagh) on:22/04/2025  
Query raised by Circle (Hazaribagh) on:02/11/2022  
Replied by DFO (Hazaribagh West) on:14/03/2023  
Query raised by Circle (Hazaribagh) on:28/07/2023  
Replied by DFO (Hazaribagh West) on:12/10/2023  
Query raised by Circle (Hazaribagh) on:28/10/2023  
Replied by DFO (Hazaribagh West) on:18/11/2023  
Query raised by Circle (Hazaribagh) on:23/12/2023  
Replied by DFO (Hazaribagh West) on:10/02/2024  
Query raised by Circle (Hazaribagh) on:08/07/2024  
Replied by DFO (Hazaribagh West) on:15/01/2025  
Query raised by Circle (Hazaribagh) on:30/01/2025  
Replied by DFO (Hazaribagh West) on:11/03/2025  
Query raised by Circle (Hazaribagh) on:22/03/2025  
Replied by DFO (Hazaribagh West) on:07/04/2025  
Query raised by DFO (Hazaribagh West) on:10/03/2022  
Replied by UA on :29/06/2022  
Query raised by DFO (Hazaribagh West) on:09/07/2022  
Replied by UA on :26/08/2022  
Query raised by DFO (Hazaribagh West) on:01/10/2022  
Replied by UA on :17/10/2022  
Query raised by DFO (Hazaribagh West) on:12/11/2022  
Replied by UA on :03/03/2023  
Query raised by DFO (Hazaribagh West) on:04/08/2023  
Replied by UA on :08/08/2023  
Query raised by DFO (Hazaribagh West) on:27/09/2023  
Replied by UA on :06/10/2023  
Query raised by DFO (Hazaribagh West) on:01/11/2023  
Replied by UA on :03/11/2023  
Query raised by DFO (Hazaribagh West) on:12/07/2024  
Replied by UA on :04/01/2025  
Query raised by DFO (Hazaribagh West) on:24/02/2025  
Replied by UA on :05/03/2025  
Query raised by DFO (Hazaribagh West) on:03/04/2025  
Replied by UA on :07/04/2025  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .