Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Chatra South)
|
EDS
|
User Agency (neeraj.tirupati@gmail.com)
|
12/08/2022
|
The proposal has been examined in the light of the GoI guidelines in this regard and the same has been found having many shortcomings, the list of which is communicated to the user agency vide DFO letter no. 1697 dated 12.08.2022 for pointwise compliance and to submit the proposal complete in all respects online and offline.
|
|
2
|
User Agency (neeraj.tirupati@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
11/01/2023
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Chatra South)
|
EDS
|
User Agency (neeraj.tirupati@gmail.com)
|
27/02/2023
|
The proposal has been examined in the light of the GoI guidelines in this regard and the same has been found having many shortcomings, the list of which is communicated to the user agency vide DFO letter no. 478 dated 26.02.2023 for pointwise compliance and to submit the proposal complete in all respects online and offline.
|
|
4
|
User Agency (neeraj.tirupati@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
10/05/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Chatra South)
|
EDS
|
User Agency (neeraj.tirupati@gmail.com)
|
23/06/2023
|
After lapse of 45 days, hard copy not yet submitted vide DFO Letter No. 1423 dated 23.06.2023
|
|
6
|
User Agency (neeraj.tirupati@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
06/07/2023
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Chatra South)
|
EDS
|
User Agency (neeraj.tirupati@gmail.com)
|
31/07/2023
|
The proposal has been examined in the light of the GoI guidelines in this regard and the same has been found having many shortcomings, the list of which is communicated to the user agency vide DFO letter no. 1753 dated 31.07.2023 for pointwise compliance and to submit the proposal complete in all respects online and offline.
|
|
8
|
User Agency (neeraj.tirupati@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
17/08/2023
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Chatra South)
|
EDS
|
User Agency (raajan08@gmail.com)
|
14/09/2023
|
The proposal has been examined in the light of the GoI guidelines in this regard and the same has been found having many shortcomings, the list of which is communicated to the user agency vide DFO letter no. 2241 dated 13.09.2023 for pointwise compliance and to submit the proposal complete in all respects online and offline.
|
|
10
|
User Agency (raajan08@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
11/11/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Chatra South)
|
EDS
|
User Agency (raajan08@gmail.com)
|
22/12/2023
|
The proposal has been examined in the light of the GoI guidelines in this regard and the same has been found having many shortcomings, the list of which is communicated to the user agency vide DFO letter no. 2961 dated 20.12.2023 for pointwise compliance and to submit the proposal complete in all respects online and offline.
|
|
12
|
User Agency (raajan08@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
12/02/2024
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Chatra South)
|
EDS
|
User Agency (raajan08@gmail.com)
|
20/02/2024
|
Pls upload the query compliance letter
|
|
14
|
User Agency (raajan08@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
20/02/2024
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Chatra South)
|
EDS
|
User Agency (raajan08@gmail.com)
|
21/02/2024
|
On request of User Agency, the proposal is returned to their portal for correction of KML file.
|
|
16
|
User Agency (raajan08@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
21/02/2024
|
The correction have been made as per the instruction received
|
|
17
|
CF (Chatra)
|
EDS
|
DFO (Chatra South)
|
30/03/2024
|
Please take note query raised by CF
|
|
18
|
DFO (Chatra South)
|
EDS
|
User Agency (raajan08@gmail.com)
|
04/04/2024
|
Please take note of queries and send compliance accordingly.
|
|
19
|
User Agency (raajan08@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
22/04/2024
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Chatra South)
|
REPLY
|
CF (Chatra)
|
08/05/2024
|
Reply of EDS dated 30-3-24 is being submitted with comments of DFO Chatra South for kind perusal.
|
|
21
|
CF (Chatra)
|
EDS
|
DFO (Chatra South)
|
13/05/2024
|
Please take note query raised by CF
|
|
22
|
DFO (Chatra South)
|
REPLY
|
CF (Chatra)
|
28/05/2024
|
Query has been complied with.
|
|
23
|
State secretary
|
EDS
|
Nodal Officer
|
12/08/2024
|
Reply of query raised by letter dated-29.07.2024.
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
14/08/2024
|
EDS Reply
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
10/09/2024
|
Some query raised
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
01/10/2024
|
Submit reply of EDS by IRO
|
|
27
|
Nodal Officer
|
EDS
|
CF (Chatra)
|
21/10/2024
|
Please take note on EDS by IRO
|
|
28
|
CF (Chatra)
|
EDS
|
DFO (Chatra South)
|
23/10/2024
|
Please take note on EDS By IRO
|
|
29
|
DFO (Chatra South)
|
EDS
|
User Agency (raajan08@gmail.com)
|
24/10/2024
|
Pls comply the query raised by IRO, Ranchi, GoI
|
|
30
|
User Agency (raajan08@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
26/10/2024
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Chatra South)
|
EDS
|
User Agency (raajan08@gmail.com)
|
29/10/2024
|
NFL is required for CA. Pls comply the respective query of MoEF&CC, GoI.
|
|
32
|
User Agency (raajan08@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
09/12/2024
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Chatra South)
|
REPLY
|
CF (Chatra)
|
24/12/2024
|
pointwise reply of EDS vide letter no-2470 dated-21.12.2024
|
|
34
|
CF (Chatra)
|
EDS
|
DFO (Chatra South)
|
07/01/2025
|
Please upload the documents required by this office letter no. 17 dated 03.01.2025 details attached
|
|
35
|
DFO (Chatra South)
|
REPLY
|
CF (Chatra)
|
22/01/2025
|
The correction have been made as per the instruction received.
|
|
36
|
CF (Chatra)
|
EDS
|
DFO (Chatra South)
|
04/02/2025
|
Please upload the documents required by this office letter no. 90 dated 01.02.2025 details attached
|
|
37
|
DFO (Chatra South)
|
EDS
|
User Agency (raajan08@gmail.com)
|
05/02/2025
|
Vide letter no-264 dated-05-02-2025
|
|
38
|
User Agency (raajan08@gmail.com)
|
REPLY
|
DFO (Chatra South)
|
09/02/2025
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Chatra South)
|
REPLY
|
CF (Chatra)
|
15/02/2025
|
Required corrections have been made.
|
|
40
|
CF (Chatra)
|
REPLY
|
Nodal Officer
|
03/03/2025
|
Required corrections have been made.
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
12/03/2025
|
EDS Reply
|
|
42
|
State secretary
|
REPLY
|
Regional Office
|
26/03/2025
|
Reply of query raised by letter dated-06.09.2024 is being submitted.
|
|