| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Garhwa North)
|
EDS
|
User Agency (eenhmedini-jhr@nic.in)
|
04/10/2021
|
Certficate from the Deputy Commisisioner with regard to the process under FRA has been completed for the proposed forest land for diversion is not annexed in the application.
|
|
|
2
|
User Agency (eenhmedini-jhr@nic.in)
|
REPLY
|
DFO (Garhwa North)
|
12/01/2022
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Garhwa)
|
17/02/2022
|
Please take note on EDS by Nodal office
|
|
|
4
|
CF (Garhwa)
|
EDS
|
DFO (Garhwa North)
|
02/03/2022
|
Please take note of EDS and comply it.
|
|
|
5
|
DFO (Garhwa North)
|
REPLY
|
CF (Garhwa)
|
03/03/2022
|
Please find the compliance of the EDS raised by the nodal officer is enclosed herewith.
|
|
|
6
|
CF (Garhwa)
|
REPLY
|
Nodal Officer
|
03/03/2022
|
Compliance of the EDS has been submitted by the D.F.O. Garhwa North.
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (Garhwa)
|
24/03/2022
|
Please take note on EDS by Nodal Office
|
|
|
8
|
CF (Garhwa)
|
EDS
|
DFO (Garhwa North)
|
11/04/2022
|
Comply the Query raised by PCCF-ED-Nodal Office.
|
|
|
9
|
DFO (Garhwa North)
|
REPLY
|
CF (Garhwa)
|
11/04/2022
|
Please find the reply of eds enclosed herewith.
|
|
|
10
|
CF (Garhwa)
|
REPLY
|
Nodal Officer
|
11/04/2022
|
Please find the compliance of eds by CF.
|
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
13/06/2022
|
FRA certificate in format for linear project and comment of CWLW has been sought.
|
|
|
12
|
Nodal Officer
|
EDS
|
CF (Garhwa)
|
17/06/2022
|
Please take note on EDS by GOJ
|
|
|
13
|
CF (Garhwa)
|
EDS
|
DFO (Garhwa North)
|
28/07/2022
|
Comply the query raised in the EDS.
|
|
|
14
|
DFO (Garhwa North)
|
EDS
|
User Agency (eenhmedini-jhr@nic.in)
|
03/08/2022
|
Comply the query raised in the EDS.
|
|
|
15
|
User Agency (eenhmedini-jhr@nic.in)
|
REPLY
|
DFO (Garhwa North)
|
03/08/2022
|
The correction have been made as per the instruction received
|
|
|
16
|
DFO (Garhwa North)
|
REPLY
|
CF (Garhwa)
|
03/08/2022
|
Query raised in eds has been complied.
|
|
|
17
|
CF (Garhwa)
|
REPLY
|
Nodal Officer
|
03/08/2022
|
Query raised in eds has been complied.
|
|
|
18
|
Nodal Officer
|
REPLY
|
State secretary
|
18/08/2022
|
EDS Reply
|
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
29/11/2022
|
some query raised
|
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
27/12/2022
|
Reply of query raise by latter dated-29.11.2022.
|
|
|
21
|
Nodal Officer
|
EDS
|
CF (Garhwa)
|
03/01/2023
|
Please take note on EDS by IRO, Ranchi.
|
|
|
22
|
CF (Garhwa)
|
EDS
|
DFO (Garhwa North)
|
03/01/2023
|
Please take note on EDS by IRO, Ranchi.
|
|
|
23
|
DFO (Garhwa North)
|
EDS
|
User Agency (eenhmedini-jhr@nic.in)
|
03/01/2023
|
Please take note of EDS
|
|
|
24
|
User Agency (eenhmedini-jhr@nic.in)
|
REPLY
|
DFO (Garhwa North)
|
11/01/2023
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Garhwa North)
|
REPLY
|
CF (Garhwa)
|
11/01/2023
|
EDS Compliance is annexed.
|
|
|
26
|
CF (Garhwa)
|
REPLY
|
Nodal Officer
|
11/01/2023
|
Compliance has been made for the query raised by IRO Ranchi.
|
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
01/02/2023
|
EDS Reply
|
|
|
28
|
State secretary
|
REPLY
|
Regional Office
|
09/02/2023
|
Reply of query raised by GoI letter dated 29.11.2023 being submitted.
|
|