Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Jamshedpur)
|
EDS
|
User Agency (sohni_s@hindustancopper.com)
|
27/02/2023
|
Please Submit Essential Documents
|
|
2
|
User Agency (sohni_s@hindustancopper.com)
|
REPLY
|
DFO (Jamshedpur)
|
02/03/2023
|
The correction have been made as per the instruction received
|
|
3
|
CF (Jamshedpur)
|
EDS
|
DFO (Jamshedpur)
|
18/03/2023
|
Please take note on following issue-
1. Part II needs to be uploaded.
2. CA Guidelines need to be re-uploaded
|
|
4
|
DFO (Jamshedpur)
|
REPLY
|
CF (Jamshedpur)
|
18/03/2023
|
EDS has been Compiled
|
|
5
|
State secretary
|
EDS
|
Nodal Officer
|
22/05/2023
|
Reply of query raised by GoJ letter dated 19.05.2023 on three points has been sought.
|
|
6
|
Nodal Officer
|
EDS
|
CF (Jamshedpur)
|
25/05/2023
|
Please take note on EDS by GOJ
|
|
7
|
CF (Jamshedpur)
|
EDS
|
DFO (Jamshedpur)
|
09/06/2023
|
Please take note on EDS.
|
|
8
|
DFO (Jamshedpur)
|
EDS
|
User Agency (sohni_s@hindustancopper.com)
|
14/06/2023
|
Please submit essential docunent.
|
|
9
|
User Agency (sohni_s@hindustancopper.com)
|
REPLY
|
DFO (Jamshedpur)
|
14/08/2023
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Jamshedpur)
|
REPLY
|
CF (Jamshedpur)
|
20/08/2023
|
EDS has been Compiled
|
|
11
|
CF (Jamshedpur)
|
REPLY
|
Nodal Officer
|
20/08/2023
|
EDS has been complied.
|
|
12
|
Nodal Officer
|
REPLY
|
State secretary
|
29/08/2023
|
EDS Reply
|
|
13
|
Head Office
|
EDS
|
State secretary
|
27/10/2023
|
EDS
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
08/11/2023
|
Reply of query raised by GoI letter dated 27.10.2023 has been sought.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Jamshedpur)
|
14/11/2023
|
Please take note on EDS by GOI
|
|
16
|
CF (Jamshedpur)
|
EDS
|
DFO (Jamshedpur)
|
05/12/2023
|
Please take note on EDS.
|
|
17
|
DFO (Jamshedpur)
|
EDS
|
User Agency (sohni_s@hindustancopper.com)
|
06/12/2023
|
Please Submit Essential Documents
|
|
18
|
User Agency (sohni_s@hindustancopper.com)
|
REPLY
|
DFO (Jamshedpur)
|
07/12/2023
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Jamshedpur)
|
EDS
|
User Agency (sohni_s@hindustancopper.com)
|
11/12/2023
|
Please Submit Essential Documents
|
|
20
|
User Agency (sohni_s@hindustancopper.com)
|
REPLY
|
DFO (Jamshedpur)
|
13/12/2023
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Jamshedpur)
|
REPLY
|
CF (Jamshedpur)
|
27/12/2023
|
EDS has been Compiled
|
|
22
|
CF (Jamshedpur)
|
REPLY
|
Nodal Officer
|
10/01/2024
|
EDS has been complied
|
|
23
|
Nodal Officer
|
EDS
|
CF (Jamshedpur)
|
02/02/2024
|
Please take note on EDS by Nodal officer
|
|
24
|
CF (Jamshedpur)
|
EDS
|
DFO (Jamshedpur)
|
09/02/2024
|
Please take note on EDS.
|
|
25
|
DFO (Jamshedpur)
|
EDS
|
User Agency (sohni_s@hindustancopper.com)
|
09/02/2024
|
Please Submit Essential Documents
|
|
26
|
User Agency (sohni_s@hindustancopper.com)
|
REPLY
|
DFO (Jamshedpur)
|
15/02/2024
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Jamshedpur)
|
REPLY
|
CF (Jamshedpur)
|
19/02/2024
|
EDS has been Compiled
|
|
28
|
CF (Jamshedpur)
|
REPLY
|
Nodal Officer
|
20/02/2024
|
EDS has been complied
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
01/03/2024
|
EDS Reply
|
|
30
|
State secretary
|
REPLY
|
Head Office
|
20/03/2024
|
Reply of EDS dated 27.10.2023 being submitted.
|
|