Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dhanbad)
|
EDS
|
User Agency (envbastacolla@outlook.com)
|
19/11/2018
|
Please submit FRA report, NOC of DC- Dhanbad, CA land DGPS Map/Kml File and Nature of Jungal- Jhari area. Letter attached .
|
|
2
|
User Agency (envbastacolla@outlook.com)
|
REPLY
|
DFO (Dhanbad)
|
21/06/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Dhanbad)
|
EDS
|
User Agency (envbastacolla@outlook.com)
|
05/07/2019
|
Please submit the hard copy of the proposal.
|
|
4
|
User Agency (envbastacolla@outlook.com)
|
REPLY
|
DFO (Dhanbad)
|
29/07/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Dhanbad)
|
EDS
|
User Agency (envbastacolla@outlook.com)
|
05/08/2019
|
Kindly do the DGPS survey and submit the KML File and Shape File of CA Land Takipur and Bhurahi.
|
|
6
|
User Agency (envbastacolla@outlook.com)
|
REPLY
|
DFO (Dhanbad)
|
07/09/2019
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Dhanbad)
|
EDS
|
User Agency (envbastacolla@outlook.com)
|
11/09/2019
|
CD of KML file & DGPS map of the CA land is not attached with your letter no 102 dated 07-09-2019. Please submit CD in 7 set so that your application can be processed.
|
|
8
|
User Agency (envbastacolla@outlook.com)
|
REPLY
|
DFO (Dhanbad)
|
16/09/2019
|
The correction have been made as per the instruction received
|
|
9
|
State secretary
|
EDS
|
Nodal Officer
|
06/01/2021
|
Reply on queries raised by GoJ on two points has been sought
|
|
10
|
Nodal Officer
|
REPLY
|
State secretary
|
09/02/2021
|
EDS Reply
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
18/03/2021
|
FRA Certificate along with proceeding of meetings has been sought
|
|
12
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
13/04/2021
|
Please take note of EDS by GOJ
|
|
13
|
CF (Bokaro)
|
EDS
|
DFO (Dhanbad)
|
20/04/2021
|
In the given guidelines, please be pleased to provide certificates related to FRA.
|
|
14
|
DFO (Dhanbad)
|
EDS
|
User Agency (envbastacolla@outlook.com)
|
23/04/2021
|
PCCF& ED, Wasteland Development Board, Jharkhand Ranchi has asked vide his office memo no. 573 dt. 13.04.2021 to submit FRA report. User Agency has been asked vide this office memo no. 882 dt. 23.04.2021 to submit the FRA report and comply the instruction of the State Govt.
|
|
15
|
User Agency (envbastacolla@outlook.com)
|
REPLY
|
DFO (Dhanbad)
|
10/02/2023
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Dhanbad)
|
REPLY
|
CF (Bokaro)
|
14/02/2023
|
Letter no. 404 Dated 14.02.2023 attached.
|
|
17
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
25/02/2023
|
Compliance has been done.
|
|
18
|
Nodal Officer
|
REPLY
|
State secretary
|
23/03/2023
|
EDS Reply
|
|
19
|
Head Office
|
EDS
|
State secretary
|
14/09/2023
|
EDS
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
10/10/2023
|
Reply on queries raised by GoI letter dated 03.10.2023 has been sought
|
|
21
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
31/10/2023
|
Please take note on EDS by MoEF&CC Delhi
|
|
22
|
CF (Bokaro)
|
EDS
|
DFO (Dhanbad)
|
03/11/2023
|
It is requested that the resolution report of the queries made vide Government of India letter dated 14.09.2023 may be kindly provided to this office as soon as possible.
|
|
23
|
DFO (Dhanbad)
|
EDS
|
User Agency (envbastacolla@outlook.com)
|
08/12/2023
|
Kindly compliance Query raised by GOI vide letter no 8-44/2009-FC Pt Dt- 14-09-2023 on 21 points.
|
|
24
|
User Agency (envbastacolla@outlook.com)
|
REPLY
|
DFO (Dhanbad)
|
14/02/2024
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Dhanbad)
|
EDS
|
User Agency (amenv.bstcla.bccl@coalindia.in)
|
27/03/2024
|
Kindly provide resolution report of the queries.
|
|
26
|
User Agency (amenv.bstcla.bccl@coalindia.in)
|
REPLY
|
DFO (Dhanbad)
|
13/09/2024
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Dhanbad)
|
EDS
|
User Agency (amenv.bstcla.bccl@coalindia.in)
|
24/10/2024
|
1. Mismatch between CA Area of KML file & document submitted.
2. Tree enumeration list was found to be incorrect.
|
|
28
|
User Agency (amenv.bstcla.bccl@coalindia.in)
|
REPLY
|
DFO (Dhanbad)
|
06/11/2024
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Dhanbad)
|
EDS
|
User Agency (amenv.bstcla.bccl@coalindia.in)
|
13/12/2024
|
Tree enumeration list is not correct
|
|
30
|
User Agency (amenv.bstcla.bccl@coalindia.in)
|
REPLY
|
DFO (Dhanbad)
|
04/01/2025
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Dhanbad)
|
REPLY
|
CF (Bokaro)
|
21/05/2025
|
Compliance Report
|
|
32
|
CF (Bokaro)
|
REPLY
|
Nodal Officer
|
13/06/2025
|
Compliance has been done.
|
|
33
|
Nodal Officer
|
EDS
|
CF (Bokaro)
|
20/06/2025
|
Please take note on EDS by Nodal Officer
|
|