Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
26/02/2022
|
pls comply the EDS
|
|
2
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
05/03/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
16/03/2022
|
1.Pls submit page-wise index as per the checklist.
2.Pls submit CBA based on revised NPV of MOEFCC , GOI, Dated 06 Jan 2022
3.pls submit detailed CA Scheme for compensatory afforestation.
REGARDS
DFO CHAIBASA
|
|
4
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
22/04/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
27/04/2022
|
pls prepare index as per the checklist and submit hard copy of proposal
|
|
6
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
28/04/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
30/04/2022
|
land identify for CA is in Giridih ..so accordingly rectify Part-I Form-A
|
|
8
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
30/04/2022
|
The correction have been made as per the instruction received
|
|
9
|
CF (Chaibasa)
|
EDS
|
DFO (Chaibasa)
|
31/05/2022
|
Queries raised by C.F.
|
|
10
|
DFO (Chaibasa)
|
REPLY
|
CF (Chaibasa)
|
31/05/2022
|
eds has been complied by this office vide letter no 902 dated 31/05/22
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
01/08/2022
|
Reply of quarry letter dated-26.07.2022 has been sought.
|
|
12
|
Nodal Officer
|
EDS
|
CF (Chaibasa)
|
02/08/2022
|
Please take note on EDS by GOJ.
|
|
13
|
CF (Chaibasa)
|
EDS
|
DFO (Chaibasa)
|
04/08/2022
|
Queries raised by Nodal
|
|
14
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
28/09/2022
|
pls comply to the query raised by jharkhand govt.
|
|
15
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
18/05/2023
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Chaibasa)
|
REPLY
|
CF (Chaibasa)
|
02/06/2023
|
RAISED QUERIES IS BEING COMPLIED
|
|
17
|
CF (Chaibasa)
|
EDS
|
DFO (Chaibasa)
|
15/06/2023
|
Please Compliance the Conditions.
|
|
18
|
DFO (Chaibasa)
|
REPLY
|
CF (Chaibasa)
|
27/06/2023
|
complained has been done.
|
|
19
|
CF (Chaibasa)
|
REPLY
|
Nodal Officer
|
22/07/2023
|
Compliance of queries raised by IRO.
|
|
20
|
Nodal Officer
|
REPLY
|
State secretary
|
28/08/2023
|
EDS Reply
|
|
21
|
State secretary
|
EDS
|
Nodal Officer
|
25/01/2024
|
Reply of quarry letter dated-02.11.2023 has been sought.
|
|
22
|
Nodal Officer
|
EDS
|
CF (Chaibasa)
|
29/01/2024
|
Please take note on EDS by GOJ
|
|
23
|
CF (Chaibasa)
|
EDS
|
DFO (Chaibasa)
|
08/02/2024
|
Please Compliance the Queries.
|
|
24
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
15/03/2024
|
pls comply the queries raised by pccf ed vide letter no 1113dated 07-11-23
|
|
25
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
15/04/2024
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
22/05/2024
|
In point no 20 of additional documnts,pdf of suitability certificate issued by DFO Giridih is not downloaded, pls upload it again
|
|
27
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
01/06/2024
|
The correction have been made as per the instruction received
|
|
28
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
19/06/2024
|
In point no 21 of additional documnts,pdf of suitability certificate issued by DFO Giridih is not downloaded, pls upload it again
|
|
29
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
21/06/2024
|
The correction have been made as per the instruction received
|
|
30
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
26/06/2024
|
In point no 22 of additional documnts,pdf of suitability certificate issued by DFO Giridih is not downloaded, pls upload it again
|
|
31
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
27/06/2024
|
The correction have been made as per the instruction received
|
|
32
|
DFO (Chaibasa)
|
REPLY
|
CF (Chaibasa)
|
29/06/2024
|
The correction have been made as per the instruction received.
|
|
33
|
CF (Chaibasa)
|
REPLY
|
Nodal Officer
|
03/08/2024
|
Compliance of queries raised by Nodal.
|
|
34
|
Nodal Officer
|
REPLY
|
State secretary
|
14/08/2024
|
EDS Reply
|
|
35
|
Regional Office
|
EDS
|
State secretary
|
13/01/2025
|
EDS may be replied.
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
30/01/2025
|
Reply of quarry letter dated-13.01.2025 has been sought.
|
|
37
|
Nodal Officer
|
EDS
|
CF (Chaibasa)
|
27/02/2025
|
Please take note on EDS by RO, Ranchi
|
|
38
|
CF (Chaibasa)
|
EDS
|
DFO (Chaibasa)
|
08/03/2025
|
Plz Compliance again.
|
|
39
|
DFO (Chaibasa)
|
REPLY
|
CF (Chaibasa)
|
12/03/2025
|
The correction have been made as per the instruction received
|
|
40
|
CF (Chaibasa)
|
EDS
|
DFO (Chaibasa)
|
03/04/2025
|
Please Compliance the Queries.
|
|
41
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
11/04/2025
|
Please insure compliance of latter no 576 date 07.04.2025 issued by this office.
|
|
42
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
01/05/2025
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Chaibasa)
|
EDS
|
User Agency (kumararunranchi2019@gmail.com)
|
05/05/2025
|
The document uploaded by U.A. in the parivesh portal on 11.04.2025 is unclear.Please upload the clear document again in parivesh portal.
|
|
44
|
User Agency (kumararunranchi2019@gmail.com)
|
REPLY
|
DFO (Chaibasa)
|
07/05/2025
|
The correction have been made as per the instruction received
|
|