  (i). Proposal No. : FP/HR/WATER/124769/2021              (ii). Name of Project for which Forest Land is required : Diversion of 0.7570 Ha. Forest land for laying of 600mm/450mm DI pipe line for Raw water from (Gurugram District Boundary) Hari Nagar Dooma to Musaidpur water works & Musaidpur water works to Mehchana water works in Dist.Gurgaon.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : laying of 600mm/450mm DI pipe line for Raw water from (Gurugram District Boundary) Hari Nagar Dooma to Musaidpur water works & Musaidpur water works to Mehchana water works in Dist.Gurgaon.C.M.Announcement code No.25510).              (iv). File no. : 9-HRB188-2021-CHA              (v). State : Haryana              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.757
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/WATER/124769/202101/03/202105/07/2021  31/03/2021   11/07/2021  04/07/2021   13/07/2021   29/07/2021 Gurgaon :30/07/2021South Circle Gurgaon:
  29/10/2021 (Gurgaon)

Haryana:
29/10/2021
Haryana:
20/11/2021
Chandigarh:
20/11/2021
14/03/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:20/12/2021  
Replied by State Government(Haryana) on:14/01/2022  
Query raised by Regional Office (Chandigarh) on:31/01/2022  
Replied by State Government(Haryana) on:23/02/2022  
Query raised by State Government (Haryana) on:09/02/2022  
Replied by Nodal Officer (Haryana) on:23/02/2022  
Query raised by Nodal Officer (Haryana) on:09/02/2022  
Replied by Circle(South Circle Gurgaon) on:11/02/2022  
Query raised by Circle (South Circle Gurgaon) on:10/02/2022  
Replied by DFO (Gurgaon) on:10/02/2022  
Query raised by DFO (Gurgaon) on:20/08/2021  
Replied by UA on :28/10/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .