  (i). Proposal No. : FP/HR/ROAD/41383/2019              (ii). Name of Project for which Forest Land is required : Diversion of 0.165 ha of forest land for widening & strengthening of Ambala Hisar road to Balana to Punjab (Km. 0.927 to 1.827) in Ambala District              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.165 ha of forest land for widening & strengthening of Ambala Hisar road to Balana to Punjab (Km. 0.927 to 1.827) in Ambala District              (iv). File no. : 9-HRB154-2021-CHA              (v). State : Haryana              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.165
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/ROAD/41383/201903/09/2019aa17/09/2019   04/10/2019 Ambala :09/10/2019North Circle Panchkula:
  18/03/2020 (Ambala)

Haryana:
12/05/2020
Haryana:
10/09/2021
Chandigarh:
10/09/2021
04/01/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:24/09/2021  
Replied by State Government(Haryana) on:22/12/2021  
Query raised by State Government (Haryana) on:09/11/2021  
Replied by Nodal Officer (Haryana) on:22/12/2021  
Query raised by Nodal Officer (Haryana) on:29/05/2020  
Replied by Circle(North Circle Panchkula) on:01/09/2020  
Query raised by Nodal Officer (Haryana) on:23/06/2021  
Replied by Circle(North Circle Panchkula) on:27/08/2021  
Query raised by Nodal Officer (Haryana) on:09/11/2021  
Replied by Circle(North Circle Panchkula) on:25/11/2021  
Query raised by Nodal Officer (Haryana) on:02/12/2021  
Replied by Circle(North Circle Panchkula) on:03/12/2021  
Query raised by Circle (North Circle Panchkula) on:21/04/2020  
Replied by DFO (Ambala) on:30/04/2020  
Query raised by Circle (North Circle Panchkula) on:01/06/2020  
Replied by DFO (Ambala) on:17/08/2020  
Query raised by Circle (North Circle Panchkula) on:23/06/2021  
Replied by DFO (Ambala) on:26/08/2021  
Query raised by Circle (North Circle Panchkula) on:16/11/2021  
Replied by DFO (Ambala) on:16/11/2021  