TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/HR/ROAD/146475/2021
(ii). Name of Project for which Forest Land is required :
Construction of 3 lane ROB at village jharli.
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Construction of 3 lane ROB at village jharli in lieu of LC No. 27-SPL at Km 41/4-5 (Jharli yard) on Rewari-HisarRailway Line on Chhuchhakwas-Matanhail-Bahu-Karoli Road in Jhajjar District.
(iv). File no. :
9-HRB002-2022-CHA
(v). State :
Haryana
(vi). Category of the Project :
Road
(vii). Shape of forest land proposed to be diverted :
Linear
(viii). Area of forest land proposed for diversion(in ha.):
0.948
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Regional Office
Stage-I Approval on
Compliance Report Submitted by State on
Stage-II Approval on
FP/HR/ROAD/146475/2021
28/08/2021
16/09/2021
07/09/2021
22/09/2021
14/09/2021
28/09/2021
12/10/2021
Jhajjar(Central Rohtak)
:
13/10/2021
Central Circle Rohtak
:
25/11/2021 (
Jhajjar(Central Rohtak)
)
Haryana
:
16/12/2021
Haryana
:
03/01/2022
Chandigarh
:
03/01/2022
20/01/2022
By :Regional Office
Haryana
01/08/2022
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
Query raised by Circle (Central Circle Rohtak) on:
26/11/2021
Replied by DFO (Jhajjar(Central Rohtak)) on:
26/11/2021
D.
Essential Details Sought History (Stage-II)
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & User Agency
Query raised by Regional Office (Chandigarh) on:
12/08/2022
Query raised by State Government (Haryana) on:
08/02/2023
Query raised by Nodal Officer on:
23/02/2023
NOTE:-
Proposal is pending at
User Agency
due to EDS raised by
RO for Stage-II
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
1
CF (Central Circle Rohtak)
EDS
DFO (Jhajjar(Central Rohtak))
26/11/2021
case down
2
DFO (Jhajjar(Central Rohtak))
REPLY
CF (Central Circle Rohtak)
26/11/2021
As per letter attached
EDS History(Stage-II)
×