TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/Others/50688/2020              (ii). Name of Project for which Forest Land is required : Construction of R.C.C. Box Type Drain along on Hisar-Bagla Road up New NH-52 By Pass Hisar.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 1.6147 Hac forest land along on Hisar-Bagla Road up to New NH-52 By Pass Hisar.              (iv). File no. : 9-HRB059-2021-CHA              (v). State : Haryana              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.6147
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/Others/50688/202008/10/2020aa13/10/2020   19/10/2020 Hisar :21/10/2020West Circle Hissar:
  30/12/2020 (Hisar)

Haryana:
19/04/2021
Haryana:
30/04/2021
Chandigarh:
30/04/2021
18/08/2021
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:10/05/2021  
Replied by State Government(Haryana) on:12/08/2021  
Query raised by State Government (Haryana) on:02/06/2021  
Replied by Nodal Officer (Haryana) on:12/08/2021  
Query raised by Nodal Officer (Haryana) on:02/06/2021  
Replied by Circle(West Circle Hissar) on:26/07/2021  
Query raised by Circle (West Circle Hissar) on:12/01/2021  
Replied by DFO (Hisar) on:12/01/2021  
Query raised by Circle (West Circle Hissar) on:14/01/2021  
Replied by DFO (Hisar) on:28/02/2021  
Query raised by Circle (West Circle Hissar) on:18/03/2021  
Replied by DFO (Hisar) on:07/04/2021  
Query raised by Circle (West Circle Hissar) on:07/04/2021  
Replied by DFO (Hisar) on:13/04/2021  
Query raised by Circle (West Circle Hissar) on:03/06/2021  
Replied by DFO (Hisar) on:22/07/2021  
Query raised by DFO (Hisar) on:22/10/2020  
Replied by UA on :26/10/2020  
Query raised by DFO (Hisar) on:18/01/2021  
Replied by UA on :26/02/2021  
Query raised by DFO (Hisar) on:18/03/2021  
Replied by UA on :05/04/2021  
Query raised by DFO (Hisar) on:04/06/2021  
Replied by UA on :11/06/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .