TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/OFC/154998/2022              (ii). Name of Project for which Forest Land is required : LAYING OF UNDERGOUND OFC BY JIO DIGITAL FIBRE PRIVATE LIMITED IN HISSAR DIVISION              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : LAYING OF UNDERGROUND OFC BY JIO DIGITAL FIBRE PRIVATE LIMITED IN HANSI CITY, DISTRICT & FOREST DIVISION HISSAR. TOTAL ROUTE LENGHT WOULD BE REQUIRED 1468 METERS (0.0661 HECTARE) (HNSI 0106 & 0111)              (iv). State : Haryana              (v). Category of the Project : Optical Fibre Cable              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.0661
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/OFC/154998/202229/04/202223/05/2022   23/05/2022   27/05/2022   13/06/2022 Hisar :20/06/2022West Circle Hissar:
  16/09/2023 (Hisar)

Haryana:
26/09/2023
Haryana:
20/12/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Haryana) on:31/10/2023  
Replied by Circle(West Circle Hissar) on:23/05/2024  
Query raised by Nodal Officer (Haryana) on:10/10/2024  
Replied by Circle(West Circle Hissar) on:05/11/2024  
Query raised by Circle (West Circle Hissar) on:03/11/2023  
Replied by DFO (Hisar) on:23/05/2024  
Query raised by Circle (West Circle Hissar) on:10/10/2024  
Replied by DFO (Hisar) on:05/11/2024  
Query raised by DFO (Hisar) on:22/06/2022  
Replied by UA on :09/07/2022  
Query raised by DFO (Hisar) on:12/07/2022  
Replied by UA on :07/06/2023  
Query raised by DFO (Hisar) on:20/06/2023  
Replied by UA on :08/07/2023  
Query raised by DFO (Hisar) on:27/07/2023  
Replied by UA on :02/08/2023  
Query raised by DFO (Hisar) on:04/08/2023  
Replied by UA on :04/08/2023  
Query raised by DFO (Hisar) on:07/11/2023  
Replied by UA on :14/03/2024  
Query raised by DFO (Hisar) on:27/03/2024  
Replied by UA on :18/05/2024  
Query raised by DFO (Hisar) on:20/05/2024  
Replied by UA on :21/05/2024  
NOTE:- Proposal is pending at State Government .