TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/Approach/41473/2019              (ii). Name of Project for which Forest Land is required : Access Permission (Entry & Exist) for Affordable Residential Plotted Colony (Under Deen Dayal Jan Awas Yojana (DDJAY-2016)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposal is for seeking diversion of forest strip for laying means of entry and exit to our proposed Affordable Residential Plotted Colony (Under Deen Dayal Jan Awas Yojana (DDJAY-2016),along Sohna Daula road KM 1-2/ Left Hand Side & Right Hand Side at village Sohna , sector-5, Sohna, Gurgaon              (iv). File no. : 9-HRB036-2022-CHA              (v). State : Haryana              (vi). Category of the Project : Approach Access              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.014
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/HR/Approach/41473/201904/08/201908/08/2019   24/01/2021   11/02/2021   23/07/2021 Gurgaon :23/07/2021South Circle Gurgaon:
  28/07/2021 (Gurgaon)

Haryana:
10/08/2021
Haryana:
12/04/2022
Chandigarh:
12/04/2022
13/07/2022
By :Regional Office
Haryana
17/10/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:25/04/2022  
Replied by State Government(Haryana) on:24/06/2022  
Query raised by State Government (Haryana) on:28/04/2022  
Replied by Nodal Officer (Haryana) on:24/06/2022  
Query raised by Nodal Officer (Haryana) on:31/08/2021  
Replied by Circle(South Circle Gurgaon) on:16/12/2021  
Query raised by Nodal Officer (Haryana) on:04/01/2022  
Replied by Circle(South Circle Gurgaon) on:10/01/2022  
Query raised by Nodal Officer (Haryana) on:21/01/2022  
Replied by Circle(South Circle Gurgaon) on:22/02/2022  
Query raised by Nodal Officer (Haryana) on:28/04/2022  
Replied by Circle(South Circle Gurgaon) on:10/06/2022  
Query raised by Circle (South Circle Gurgaon) on:01/09/2021  
Replied by DFO (Gurgaon) on:13/12/2021  
Query raised by Circle (South Circle Gurgaon) on:04/01/2022  
Replied by DFO (Gurgaon) on:06/01/2022  
Query raised by Circle (South Circle Gurgaon) on:24/01/2022  
Replied by DFO (Gurgaon) on:18/02/2022  
Query raised by Circle (South Circle Gurgaon) on:06/05/2022  
Replied by DFO (Gurgaon) on:09/06/2022  
Query raised by DFO (Gurgaon) on:22/09/2021  
Replied by UA on :07/12/2021  
Query raised by DFO (Gurgaon) on:09/05/2022  
Replied by UA on :19/05/2022  
Query raised by DFO (Gurgaon) on:31/05/2022  
Replied by UA on :01/06/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Chandigarh) on:21/11/2023  
Query raised by State Government (Haryana) on:28/11/2023  
Query raised by Nodal Officer on:04/12/2023  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .