Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
23/11/2019
|
Please provide Reclamation plan for Dumping sites
|
|
2
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
14/12/2019
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Solan)
|
10/02/2020
|
EDS
|
|
4
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
19/02/2020
|
DFO Solan to attend to the observations and submit complete case online immediately
|
|
5
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
06/03/2020
|
please submit the reply of the observation
|
|
6
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
26/10/2020
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
25/11/2020
|
please submit the reply of the observation
|
|
8
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
25/01/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
15/02/2021
|
Needful has been done please.
|
|
10
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
15/02/2021
|
The observation is uncomplete
|
|
11
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
15/02/2021
|
Needful has been done
|
|
12
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
18/02/2021
|
Kindly needful has been done.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Solan)
|
25/02/2021
|
EDS
|
|
14
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
05/03/2021
|
the observation raisd by Nadal Officer may be completed.
|
|
15
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
05/03/2021
|
The Observation raised by Nodal Officer may be completed please.
|
|
16
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
10/06/2021
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
16/06/2021
|
Kindly the required information has been done
|
|
18
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
22/06/2021
|
All the observations attended successfully.
|
|
19
|
Nodal Officer
|
EDS
|
CF (Solan)
|
23/07/2021
|
EDS
|
|
20
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
29/07/2021
|
The observation may be fulfilled immediately
|
|
21
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
31/07/2021
|
The observations raised by Nodal officer may be attended please.
|
|
22
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
24/08/2021
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
07/09/2021
|
Needful has been done.
|
|
24
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
07/09/2021
|
Attended the observation raised by your good office
|
|
25
|
Nodal Officer
|
EDS
|
CF (Solan)
|
08/09/2021
|
EDS
|
|
26
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
08/09/2021
|
re-submitted the same please
|
|
27
|
Nodal Officer
|
EDS
|
CF (Solan)
|
29/09/2021
|
The distance from the protected area is less than 10 km hence PCCF WL has been requested for their comments which will be uploaded in online part II. on the receipt of the same will be mailed to u for uploading.
|
|
28
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
12/10/2021
|
As observed by Nodal officer, the distance from the protected area is less than 10 km hence PCCF WL has been requested for their comments which will be uploaded in online part II. on the receipt of the same will be mailed to u for uploading.
|
|
29
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
13/10/2021
|
The obsersvation has been fulfulled please.
|
|
30
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
13/10/2021
|
The shortcoming may be attanded
|
|
31
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
13/10/2021
|
the observation has been done vide this office memo No. 3420 dated 13.10.2021.
|
|
32
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
21/10/2021
|
Needful has been done
|
|
33
|
Nodal Officer
|
EDS
|
CF (Solan)
|
18/11/2021
|
The distance from the protected area is less than 10 km hence PCCF WL has been requested for their comments which will be uploaded in online part II. on the receipt of the same will be mailed to u for uploading.
|
|
34
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
13/12/2021
|
The distance from the protected area is less than 10 km. Hence PCCF WL has been requested for their comments by Nodal Officer FCA. This will be uploaded in online part II on the receipt of the same will be mailed to u for uploading.
|
|
35
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
22/03/2022
|
Needful has been done please
|
|
36
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
05/04/2022
|
Needful has been done and re-submitted the same.
|
|
37
|
Nodal Officer
|
EDS
|
CF (Solan)
|
13/04/2022
|
The distance from the protected area is less than 10 km hence PCCF WL has been requested for their comments which will be uploaded in online part II. on the receipt of the same will be mailed to u for uploading.
|
|
38
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
18/04/2022
|
nodal officer cum APCCF FCA has raised some observations
|
|
39
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
23/04/2022
|
the requisite information is enclosed herewith for information and necessary actin please.
|
|
40
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
13/05/2022
|
positive Comments have been obtained from CWLW as the area falls in ESZ of Chail WLS, may kindly approve proposal for diversion.
|
|
41
|
Nodal Officer
|
EDS
|
CF (Solan)
|
26/05/2022
|
please upload the comments of CWLW in online additional information details in Part-II. and The Bill of NPV submitted revised rate as per the GoI letter dated 06.01.2022
|
|
42
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
26/05/2022
|
please upload the comments of CWLW in online additional information details in Part-II. and The Bill of NPV submitted revised rate as per the GoI letter dated 06.01.2022
|
|
43
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
26/05/2022
|
Needful has been done please.
|
|
44
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
26/05/2022
|
Comments of CWLW has been uploadeded by DFO. Also revised rates of NPV has been uploaded.
|
|
45
|
Nodal Officer
|
EDS
|
CF (Solan)
|
06/06/2022
|
please mentioned the details of violation at para -II in online part-II and uploaded the bill of Penal NPV in additional information details in online Part-II and submit hard copy to this office at the earliest.
|
|
46
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
06/06/2022
|
please mentioned the details of violation at para -II in online part-II and uploaded the bill of Penal NPV in additional information details in online Part-II and submit hard copy to this office at the earliest
|
|
47
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
10/06/2022
|
needfull has been done please
|
|
48
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
10/06/2022
|
the obervation may be attendd
|
|
49
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
10/06/2022
|
The observation has been done/uploaded in e-parivesh for necessary action please.
|
|
50
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
13/06/2022
|
The observations raised by your good office has been removed and re-submitted the same please.
|
|
51
|
Regional Office
|
EDS
|
State secretary
|
11/08/2022
|
The State Govt. may attend the shortcomings attached herewith
|
|
52
|
State secretary
|
EDS
|
Nodal Officer
|
16/08/2022
|
EDS
|
|
53
|
Nodal Officer
|
EDS
|
CF (Solan)
|
16/08/2022
|
EDS
|
|
54
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
20/08/2022
|
the observations raised by higher ups please attend
|
|
55
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
20/08/2022
|
The observation raided by Gol may be attended immediately.
|
|
56
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
15/02/2023
|
The correction have been made as per the instruction received
|
|
57
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
03/03/2023
|
The observation raised by Nodal offiecer may properly be attended according please.
|
|
58
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
21/06/2023
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
03/07/2023
|
Needful has been done
|
|
60
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
18/10/2023
|
The correction have been made as per the instruction received
|
|
61
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
03/11/2023
|
Kindly all document alongwith letter has been uploaded in additional details. Submitted please.
|
|
62
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
08/11/2023
|
The observations as raised has been attended please.
|
|
63
|
Nodal Officer
|
EDS
|
CF (Solan)
|
25/11/2023
|
EDS
|
|
64
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
01/12/2023
|
Please attend the observations as raised by the Nodal.
|
|
65
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
21/12/2023
|
The Nodal Officer Shimla has raised the following observations in the proposal. It is therefore, requested that the observations may be attended immediately.
|
|
66
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
14/02/2024
|
The correction have been made as per the instruction received
|
|
67
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
27/02/2024
|
Observation 4 and 5 and 6 raised by Nodal officer has not been attended please
|
|
68
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
21/03/2024
|
The correction have been made as per the instruction received
|
|
69
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
28/03/2024
|
The observation raised by Nodal Officer dated 23.11.2023 has been attended please.
|
|
70
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
01/04/2024
|
Please attend the observations as raised by the Nodal Officer
|
|
71
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
02/04/2024
|
Observation has already been sent vide this office letter No. 8757 dt. 28.3.2024 please.
|
|
72
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
05/04/2024
|
On the scrutiny of the proposal distance certificate at Sr.No.9 shown 150 Mtrs. whereas reply submitted by you Sr.No.2 shown 0.80 Km. Please rectify and re-submit the proposal.
|
|
73
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
05/04/2024
|
Kindly correction has been done/uploaded at sr. no. 19 in additional information.
|
|
74
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
05/04/2024
|
Distance certificate as uploaded in Part-II at Sr. No.19 be uploaded in Part-I please.
|
|
75
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
05/04/2024
|
On the scrutiny of the proposal distance certificate at Sr.No.9 shown 150 Mtrs. whereas reply submitted by you Sr.No.2 shown 0.80 Km. Please rectify and re-submit the proposal.
|
|
76
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
05/04/2024
|
The correction have been made as per the instruction received
|
|
77
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
05/04/2024
|
Kindly observation raised by you has been done/uploaded by the user agency at sr. no. 26 in additional detail part-I.
|
|
78
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
19/04/2024
|
Needful has been done
|
|
79
|
Nodal Officer
|
EDS
|
CF (Solan)
|
29/04/2024
|
EDS
|
|
80
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
30/04/2024
|
Please attend the observations as raised by Nodal office and re-submit the case in propoer.
|
|
81
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
03/05/2024
|
Nodal Office has raised the following shortcoming in the proposal. The shortcoming pertins to your level. It is therefore, requested to attend the same immediately.
|
|
82
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
13/12/2024
|
The correction have been made as per the instruction received
|
|
83
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
20/12/2024
|
May attend the shortcoming as per discussion with the DFO concerned dated 19.12.2024.
|
|
84
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
30/12/2024
|
The correction have been made as per the instruction received
|
|
85
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
07/01/2025
|
Reply of observations raised by Nodal officer has been attended for favaour of kind information and necessary action please.
|
|
86
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
16/01/2025
|
Needful has been done please.
|
|
87
|
Nodal Officer
|
EDS
|
CF (Solan)
|
22/01/2025
|
The documents regarding violation are not acceptable, the govt. record such as revenue record etc be provided .Further, the EROW and PROW are not properly marked in KML file. Please mark KML file properly.
|
|
88
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
30/01/2025
|
The documents regarding violation are not acceptable, the govt. record such as revenue record etc be provided .Further, the EROW and PROW are not properly marked in KML file. Please mark KML file properly.
|
|
89
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
31/01/2025
|
The documents regarding violation are not acceptable, the govt. record such as revenue record etc be provided .Further, the EROW and PROW are not properly marked in KML file. Please mark KML file properly.
|
|
90
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
02/05/2025
|
The correction have been made as per the instruction received
|
|
91
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
09/05/2025
|
The observation raised by Nodal officer has been attended please
|
|
92
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
14/05/2025
|
The correction have been made as per the instruction received
|
|
93
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
15/05/2025
|
Nodal officer had raised the shortcomings dated on 22.01.2025. Further UA has attended the same in the KML file and uploaded the certificate in additional information at Sr. No. 19. It is therefore, requested to kindly take necessary action at your level please.
|
|
94
|
CF (Solan)
|
EDS
|
DFO (Solan)
|
17/05/2025
|
The additional information as uploaded is not in a order. EROW and PROW has not been marked properly in KML file. You are requested to upload the same in a proper manner.
|
|
95
|
DFO (Solan)
|
EDS
|
User Agency (ee-sol-hp@nic.in)
|
17/05/2025
|
EROW and PROW has not been marked in the KML file of Proposed road. It is therefore, requested to mark the same in the KML file immediately.
|
|
96
|
User Agency (ee-sol-hp@nic.in)
|
REPLY
|
DFO (Solan)
|
24/05/2025
|
The correction have been made as per the instruction received
|
|
97
|
DFO (Solan)
|
REPLY
|
CF (Solan)
|
02/06/2025
|
The user agency has attended/marked the observation of EROW & PROW in the KML of proposed road. It is therefore, requested that the case may kindly be sent to higher ups for necessary action.
|
|
98
|
CF (Solan)
|
REPLY
|
Nodal Officer
|
24/06/2025
|
The user agency has attended/marked the observation of EROW & PROW in the KML of proposed road. It is therefore, requested that the case may kindly be sent to higher ups for necessary action.
|
|
99
|
Nodal Officer
|
EDS
|
CF (Solan)
|
05/07/2025
|
EDS
|
|