| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
05/08/2022
|
Please do the needful as per attachment
|
|
|
2
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla(shimla))
|
24/08/2022
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Shimla MC)
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
29/08/2022
|
In countinuation to this office letter No FCA-Vol.V/2022-23/1083 the documents related to part-I sent to your vide above communiction may be uploaded on PARIVESH on line portal and hard copy of the same may be sent to this office for taking further action into the matter
|
|
|
4
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla MC)
|
30/08/2022
|
The correction have been made as per the instruction received
|
|
|
5
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
11/10/2022
|
Page no. has not mentioned in recommendation
|
|
|
6
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
11/10/2022
|
necessary correctio have been done as per the instruction received
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
18/10/2022
|
EDS
|
|
|
8
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
18/10/2022
|
EDS
|
|
|
9
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
18/10/2022
|
EDS
|
|
|
10
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
20/10/2022
|
Please de the needful as per attachment
|
|
|
11
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla(shimla))
|
26/10/2022
|
The correction have been made as per the instruction received
|
|
|
12
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
01/11/2022
|
point wise reply given as per attachment
|
|
|
13
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
01/11/2022
|
As per report of DFO (W.L) Shimla that the aerial distance of proposed project site is approx. 29.28 mtrs from Shimla Water Catchment Wildlife Sanctuary, but inside the Eco Sensitive Zone of Shimla Water Catchment Sanctuary & there is no option to edit the same online.
|
|
|
14
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
01/11/2022
|
as per attachment
|
|
|
15
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
01/11/2022
|
Necessary correction has been done online
|
|
|
16
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
03/11/2022
|
Reply as per attachment
|
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
23/12/2022
|
The State Government may attend the shortcomings attached herewith.
|
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
26/12/2022
|
eds
|
|
|
19
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
31/12/2022
|
To upload the minute of 2nd meeting of PSC against the proposal in additional information Detail.
|
|
|
20
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
03/01/2023
|
To upload the minute of 2nd meeting of PSC against the proposal in additional information Detail.
|
|
|
21
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
03/01/2023
|
To upload the minute of 2nd meeting of PSC against the proposal in additional information Detail.
|
|
|
22
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
03/01/2023
|
The minutes of the 2 nd Meeting of the Project has been uploaded.
|
|
|
23
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
04/01/2023
|
The Minutes of 2nd meeting has been uploaded
|
|
|
24
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
04/01/2023
|
The Minutes of 2nd meeting has been uploaded
|
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
10/01/2023
|
Complete reply is submitted
|
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
10/01/2023
|
Complete reply is submitted
|
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
18/01/2023
|
EDS
|
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
24/01/2023
|
eds
|
|
|
29
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
24/01/2023
|
eds
|
|
|
30
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
27/01/2023
|
EDS
|
|
|
31
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
27/01/2023
|
EDS
|
|
|
32
|
DFO (Shimla MC)
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
27/01/2023
|
EDS attached
|
|
|
33
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla MC)
|
30/01/2023
|
The correction have been made as per the instruction received
|
|
|
34
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
30/01/2023
|
Correction have been made as per the instruction received
|
|
|
35
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
06/02/2023
|
Necessary comments pertains to the Nodal Officer
|
|
|
36
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
06/02/2023
|
Necessary comments pertains to the Nodal Officer
|
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
16/02/2023
|
Proceedings of PSC
|
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
16/02/2023
|
Proceedings of PSC
|
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
06/03/2023
|
Shortcomings may be atttended
|
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
06/03/2023
|
EDS
|
|
|
41
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
06/03/2023
|
EDS
|
|
|
42
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
06/03/2023
|
EDS
|
|
|
43
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
06/03/2023
|
EDS
|
|
|
44
|
DFO (Shimla MC)
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
07/03/2023
|
EDS attached
|
|
|
45
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla MC)
|
22/03/2023
|
The correction have been made as per the instruction received
|
|
|
46
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
24/03/2023
|
The reply given as per attachment
|
|
|
47
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
24/03/2023
|
Necessary correction has been done
|
|
|
48
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
24/03/2023
|
as per attachment
|
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
28/03/2023
|
Complete reply is submitted
|
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
28/03/2023
|
Complete reply is submitted
|
|
|
51
|
Regional Office
|
EDS
|
State secretary
|
03/04/2023
|
EDS
|
|
|
52
|
State secretary
|
EDS
|
Nodal Officer
|
04/04/2023
|
EDS
|
|
|
53
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
04/04/2023
|
EDS
|
|
|
54
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
04/04/2023
|
EDS
|
|
|
55
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
04/04/2023
|
EDS
|
|
|
56
|
DFO (Shimla MC)
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
05/04/2023
|
EDS attached
|
|
|
57
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla MC)
|
11/04/2023
|
The correction have been made as per the instruction received
|
|
|
58
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
12/04/2023
|
As desired site inspection report hof DFO Urban Shimla has been attached.
|
|
|
59
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
13/04/2023
|
The reply given as per attachment
|
|
|
60
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
13/04/2023
|
EDS
|
|
|
61
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
13/04/2023
|
EDS
|
|
|
62
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
13/04/2023
|
Necessary correction has been done
|
|
|
63
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
13/04/2023
|
Necessary correction has been done
|
|
|
64
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
13/04/2023
|
Reply given as per attachment
|
|
|
65
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
24/04/2023
|
Shortcomings have been noticed in the proposal, which may be completed.
|
|
|
66
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
25/04/2023
|
EDS
|
|
|
67
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
25/04/2023
|
EDS
|
|
|
68
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
26/04/2023
|
Please do tte needful as per attachment
|
|
|
69
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla(shimla))
|
26/04/2023
|
The correction have been made as per the instruction received
|
|
|
70
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
27/04/2023
|
The reply in respect of the observation raised by the Nodal Officer-cum-APCCF (FCA) dated 24th April, 2023 is attached, please.
|
|
|
71
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
28/04/2023
|
EDS attached
|
|
|
72
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
28/04/2023
|
reply given as per attachment
|
|
|
73
|
Nodal Officer
|
REPLY
|
State secretary
|
29/04/2023
|
Complete reply is submitted
|
|
|
74
|
State secretary
|
REPLY
|
Regional Office
|
29/04/2023
|
Complete reply is submitted
|
|
|
75
|
Regional Office
|
EDS
|
State secretary
|
26/05/2023
|
The State Government may attend the shortcomings attached herewith.
|
|
|
76
|
State secretary
|
EDS
|
Nodal Officer
|
26/05/2023
|
EDS
|
|
|
77
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
26/05/2023
|
EDS
|
|
|
78
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
26/05/2023
|
EDS
|
|
|
79
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
26/05/2023
|
EDS
|
|
|
80
|
DFO (Shimla MC)
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
29/05/2023
|
EDS attached
|
|
|
81
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla MC)
|
02/06/2023
|
The correction have been made as per the instruction received
|
|
|
82
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
02/06/2023
|
Correction have been made as per the instruction received
|
|
|
83
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
06/06/2023
|
Reply given as per attachment
|
|
|
84
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
06/06/2023
|
Please correct documents upload
|
|
|
85
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
06/06/2023
|
Please correct documents upload
|
|
|
86
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
06/06/2023
|
Necessary correction has been done as per attachment
|
|
|
87
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
07/06/2023
|
Necessary correction has been done
|
|
|
88
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
07/06/2023
|
Needful has been done.
|
|
|
89
|
Nodal Officer
|
REPLY
|
State secretary
|
08/06/2023
|
Complete reply is submitted
|
|
|
90
|
State secretary
|
REPLY
|
Regional Office
|
08/06/2023
|
Complete reply is submitted
|
|
|
91
|
Regional Office
|
EDS
|
State secretary
|
21/06/2023
|
The State Government may attend the shortcomings attached herewith.
|
|
|
92
|
State secretary
|
EDS
|
Nodal Officer
|
22/06/2023
|
EDS
|
|
|
93
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
22/06/2023
|
EDS
|
|
|
94
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
22/06/2023
|
EDS
|
|
|
95
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
22/06/2023
|
EDS
|
|
|
96
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
26/06/2023
|
Reply with respect to the observation raised by the IRO vide letter No. FC/HPC/06/1812022 dated 21st June, 2023
|
|
|
97
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
26/06/2023
|
Necessary correction has been done
|
|
|
98
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
26/06/2023
|
Reply given as per attachment
|
|
|
99
|
Nodal Officer
|
REPLY
|
State secretary
|
27/06/2023
|
Complete reply is submitted
|
|
|
100
|
State secretary
|
REPLY
|
Regional Office
|
27/06/2023
|
Complete reply is submitted
|
|
|
101
|
Regional Office
|
EDS
|
State secretary
|
13/07/2023
|
The State Government may attend the shortcomings attached herewith.
|
|
|
102
|
State secretary
|
EDS
|
Nodal Officer
|
17/07/2023
|
EDS
|
|
|
103
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
17/07/2023
|
EDS
|
|
|
104
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
17/07/2023
|
EDS
|
|
|
105
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
17/07/2023
|
EDS
|
|
|
106
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
18/07/2023
|
In compliance to the Integrated Regional Office letter No. FC/HPC/06/181/2022 dated 12th July, 2023 reply is attached, please.
|
|
|
107
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
18/07/2023
|
necessary correction has been done
|
|
|
108
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
18/07/2023
|
Reply given as per attachment
|
|
|
109
|
Nodal Officer
|
REPLY
|
State secretary
|
20/07/2023
|
Complete reply is submitted
|
|
|
110
|
State secretary
|
REPLY
|
Regional Office
|
20/07/2023
|
Complete reply is submitted
|
|