| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
28/12/2022
|
Please send the case folder to this office
|
|
|
2
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
04/03/2023
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
24/04/2023
|
EDS
|
|
|
4
|
CF (Shimla)
|
EDS
|
DFO (Chopal)
|
25/04/2023
|
EDS
|
|
|
5
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
01/05/2023
|
EDS
|
|
|
6
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
23/06/2023
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Chopal)
|
REPLY
|
CF (Shimla)
|
27/06/2023
|
The request received by HPPWD Chopal submitted for further action please.
|
|
|
8
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
27/06/2023
|
The request received from HPPWD Chopal for area change, as per attachment.
|
|
|
9
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
03/07/2023
|
Area can be rectify at user agency level. proposal sent to user agency for change.
|
|
|
10
|
CF (Shimla)
|
EDS
|
DFO (Chopal)
|
03/07/2023
|
Area can be rectify at user agency level. proposal sent to user agency for change.
|
|
|
11
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
04/07/2023
|
Area can be rectify at user agency level. proposal sent to user agency for change.
|
|
|
12
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
19/07/2023
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Chopal)
|
REPLY
|
CF (Shimla)
|
19/07/2023
|
The request again received by HPPWD Chopal submitted for further action please.
|
|
|
14
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
20/07/2023
|
The request again received by HPPWD Chopal submitted for further action please.
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
20/07/2023
|
As per request area has been changed. Please update the revised area of non forest land in the village wise breakup & Component wise breakup etc.
|
|
|
16
|
CF (Shimla)
|
EDS
|
DFO (Chopal)
|
20/07/2023
|
As per request area has been changed. Please update the revised area of non forest land in the village wise breakup & Component wise breakup etc
|
|
|
17
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
21/07/2023
|
Area can be rectify at user agency level. proposal sent to user agency for change.
|
|
|
18
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
05/08/2023
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
08/08/2023
|
1. Toposheet of alternative not countersigned by the DFO uploaded.
|
|
|
20
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
16/08/2023
|
The correction have been made as per the instruction received
|
|
|
21
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
17/08/2023
|
You are therefore once again requested to ensure the proper upload the requisite document online by mentioning the reference of uploaded document Sr. No. Column No. & Part
|
|
|
22
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
18/08/2023
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Chopal)
|
REPLY
|
CF (Shimla)
|
24/08/2023
|
The correction have been made as per the instruction received
|
|
|
24
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
31/08/2023
|
Reply given as per attachment
|
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
29/12/2023
|
EDS
|
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
08/01/2024
|
EDS
|
|
|
27
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
08/01/2024
|
EDS
|
|
|
28
|
CF (Shimla)
|
EDS
|
DFO (Chopal)
|
10/01/2024
|
eds
|
|
|
29
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
15/01/2024
|
EDS
|
|
|
30
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
24/05/2024
|
The correction have been made as per the instruction received
|
|
|
31
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
24/05/2024
|
The proper upload the requisite document online by mentioning the reference of uploaded document Sr. No. Column No. & Part and counter singed not violation shown sheet by the DFO
|
|
|
32
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
30/06/2024
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
01/07/2024
|
The case sent for information
|
|
|
34
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
03/07/2024
|
The correction have been made as per the instruction received
|
|
|
35
|
DFO (Chopal)
|
REPLY
|
CF (Shimla)
|
23/07/2024
|
The correction have been made as per the instruction received
|
|
|
36
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
02/08/2024
|
Reply given as per attachment
|
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
09/08/2024
|
EDS Reply
|
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
09/08/2024
|
EDS Reply
|
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
12/11/2024
|
State govt. may attend the shortcomings attached herewith.
|
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
14/11/2024
|
eds
|
|
|
41
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
14/11/2024
|
eds
|
|
|
42
|
CF (Shimla)
|
EDS
|
DFO (Chopal)
|
20/11/2024
|
eds
|
|
|
43
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
23/11/2024
|
EDS
|
|
|
44
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
27/11/2024
|
The correction have been made as per the instruction received
|
|
|
45
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
28/11/2024
|
The reply letter not uplodaed by the user anency on dated 23/11/2024
|
|
|
46
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
30/11/2024
|
The correction have been made as per the instruction received
|
|
|
47
|
DFO (Chopal)
|
REPLY
|
CF (Shimla)
|
11/12/2024
|
The correction have been made as per instruction recived
|
|
|
48
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
13/12/2024
|
Reply given as per attachment.
|
|
|
49
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
17/12/2024
|
None of the observations have been attended.
|
|
|
50
|
CF (Shimla)
|
EDS
|
DFO (Chopal)
|
18/12/2024
|
eds
|
|
|
51
|
DFO (Chopal)
|
EDS
|
User Agency (ee-cho-hp@nic.in)
|
20/12/2024
|
EDS
|
|
|
52
|
User Agency (ee-cho-hp@nic.in)
|
REPLY
|
DFO (Chopal)
|
17/12/2025
|
The correction have been made as per the instruction received
|
|
|
53
|
DFO (Chopal)
|
REPLY
|
CF (Shimla)
|
19/02/2026
|
The correction have been made as per the instruction received
|
|
|
54
|
CF (Shimla)
|
EDS
|
DFO (Chopal)
|
21/02/2026
|
Reply is given as per attachment.
|
|
|
55
|
DFO (Chopal)
|
REPLY
|
CF (Shimla)
|
21/02/2026
|
The correction have been made as per the instruction received
|
|
|
56
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
21/02/2026
|
Reply is given as per attachment.
|
|
|
57
|
Nodal Officer
|
REPLY
|
State secretary
|
26/02/2026
|
Complete reply is submitted please.
|
|
|
58
|
State secretary
|
REPLY
|
Regional Office
|
26/02/2026
|
Complete reply is submitted please.
|
|