| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
10/05/2022
|
Please demarcate the area along with forest field staff of Mashobra Range so that the enumeration could be papered accordingly
|
|
|
2
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla(shimla))
|
16/05/2022
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
27/05/2022
|
In this regard it is submitted that the CA sites are not available in jurisdiction of Shimla Forest Division and the matter has already been taken up with the higher-ups to provide the CA sites which is still awaited. Therefore unless and until the CA sites are not provided to this office it is not possible to proceed further. This is for your kind information please.
|
|
|
4
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla(shimla))
|
29/06/2022
|
The correction have been made as per the instruction received
|
|
|
5
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
03/08/2022
|
EDS
|
|
|
6
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
03/08/2022
|
EDS
|
|
|
7
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
04/08/2022
|
Please do the needful as per attachment
|
|
|
8
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla(shimla))
|
17/08/2022
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
24/08/2022
|
The reply given as per attachment
|
|
|
10
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
26/08/2022
|
Reply given as per attachment
|
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
15/10/2022
|
the State Government may attend the shortcomings attached herewith.
|
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
18/10/2022
|
EDS
|
|
|
13
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
18/10/2022
|
EDS
|
|
|
14
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
18/10/2022
|
EDS
|
|
|
15
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
20/10/2022
|
Please do the needful as per attachment
|
|
|
16
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla(shimla))
|
05/11/2022
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
07/11/2022
|
Please do the need full as per attachment
|
|
|
18
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla(shimla))
|
19/11/2022
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
26/12/2022
|
The point wise reply given as per attachment
|
|
|
20
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
29/12/2022
|
Needful has been done.
|
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
11/01/2023
|
Complete reply is submitted please.
|
|
|
22
|
State secretary
|
REPLY
|
Regional Office
|
11/01/2023
|
Complete reply is submitted please.
|
|
|
23
|
Regional Office
|
EDS
|
State secretary
|
17/01/2023
|
EDS
|
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
24/01/2023
|
eds
|
|
|
25
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
24/01/2023
|
eds
|
|
|
26
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
27/01/2023
|
EDS
|
|
|
27
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
27/01/2023
|
Please do the needful as per attachment
|
|
|
28
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla(shimla))
|
01/02/2023
|
The correction have been made as per the instruction received
|
|
|
29
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
09/02/2023
|
The reply given as per attachment
|
|
|
30
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
13/02/2023
|
eds
|
|
|
31
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
13/02/2023
|
Necessary certificate has been uploaded
|
|
|
32
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
13/02/2023
|
The reply given as per attachment
|
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
15/02/2023
|
Complete reply is submitted please.
|
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
15/02/2023
|
Complete reply is submitted please.
|
|
|
35
|
Regional Office
|
EDS
|
State secretary
|
25/02/2023
|
The State Government may attend the shortcomings attached herewith.
|
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
27/02/2023
|
EDS
|
|
|
37
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
27/02/2023
|
EDS
|
|
|
38
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
27/02/2023
|
EDS
|
|
|
39
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (pdpiushimla@gmail.com)
|
02/03/2023
|
Please do the needful as per attachment
|
|
|
40
|
User Agency (pdpiushimla@gmail.com)
|
REPLY
|
DFO (Shimla(shimla))
|
02/03/2023
|
The correction have been made as per the instruction received
|
|
|
41
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
07/03/2023
|
The point wise reply given as per attachment please.
|
|
|
42
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
09/03/2023
|
The point wise reply given as per attachment please.
|
|
|
43
|
Nodal Officer
|
REPLY
|
State secretary
|
15/03/2023
|
Complete reply is submitted
|
|
|
44
|
State secretary
|
REPLY
|
Regional Office
|
15/03/2023
|
Complete reply is submitted
|
|