| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
16/12/2022
|
On the scrutiny of the case it has been found that the all the documents related to the project has not been uploaded as per GoI instruction Please do the needful.
|
|
|
2
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
18/01/2023
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
17/02/2023
|
Please do the Needful as per Attachment
|
|
|
4
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
25/11/2023
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
19/12/2023
|
The User Agency is requested to please mark the villages going to be directly benefited from the project in the KML file, please.
|
|
|
6
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
19/12/2023
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
23/12/2023
|
User Agency may please go through the attachment and act accordingly, please.
|
|
|
8
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
09/07/2024
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
29/07/2024
|
Please refer to the shortcomings noticed in this office letter No. RK/FCA/Link road Ghaini Dayal Dabog/1861 dated 29.07.2024. a copy of which is attached and take the necessary appropriate actions accordingly.
|
|
|
10
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
10/09/2024
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
03/03/2025
|
Please refer to the shortcomings Points No. 4noticed in this office letter No. RK/FCA/Link road Ghaini Dayal Dabog/1861 dated 29.07.2024.
|
|
|
12
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
12/03/2025
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
29/09/2025
|
From the perusal of the proposal, the proposal is required to be processed on PARIVESH 2.0 as per the FCA Rules, 2023. You are therefore requested to upload the proposal on PARIVESH 2.0.
|
|