| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Hamirpur)
|
EDS
|
User Agency (ee-bar-hp@nic.in)
|
02/11/2018
|
Please attend to the observation as per letter attached
|
|
|
2
|
User Agency (ee-bar-hp@nic.in)
|
REPLY
|
DFO (Hamirpur)
|
04/02/2019
|
The correction have been made as per the instruction received
|
|
|
3
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
01/07/2019
|
Please complete the proposal as per EDS attached.
|
|
|
4
|
DFO (Hamirpur)
|
EDS
|
User Agency (ee-bar-hp@nic.in)
|
22/10/2019
|
Please complete the proposal
|
|
|
5
|
User Agency (ee-bar-hp@nic.in)
|
REPLY
|
DFO (Hamirpur)
|
22/10/2019
|
The correction have been made as per the instruction received
|
|
|
6
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
04/11/2019
|
Needful has been done and resubmitted.
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
16/11/2019
|
EDS
|
|
|
8
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
20/11/2019
|
EDS
|
|
|
9
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
01/02/2020
|
needful has been done and resubmitted.
|
|
|
10
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
05/02/2020
|
Needful has been done by the user agency/DFO. Hence the proposal is resubmitted please.
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
14/02/2020
|
Shortcomings have been noticed in the proposal, which may be completed.
|
|
|
12
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
15/02/2020
|
Shortcomings have been noticed in the proposal, which may be completed.
|
|
|
13
|
DFO (Hamirpur)
|
EDS
|
User Agency (ee-bar-hp@nic.in)
|
31/05/2020
|
Please complete the proposal
|
|
|
14
|
User Agency (ee-bar-hp@nic.in)
|
REPLY
|
DFO (Hamirpur)
|
31/05/2020
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
23/06/2020
|
Needful has been done and resubmitted.
|
|
|
16
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
24/06/2020
|
Reply EDS
|
|
|
17
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
24/06/2020
|
needful has been done and resubmitted
|
|
|
18
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
25/06/2020
|
Shortcoming has been noticed
|
|
|
19
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
25/06/2020
|
Needful Done
|
|
|
20
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
25/06/2020
|
Needful has been done by the user agency/DFO. Hence the proposal is resubmitted please.
|
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
07/08/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
07/08/2020
|
EDS
|
|
|
23
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
07/08/2020
|
EDS
|
|
|
24
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
10/08/2020
|
EDS
|
|
|
25
|
DFO (Hamirpur)
|
EDS
|
User Agency (ee-bar-hp@nic.in)
|
25/08/2020
|
Shortcoming has been noticed
|
|
|
26
|
User Agency (ee-bar-hp@nic.in)
|
REPLY
|
DFO (Hamirpur)
|
11/04/2022
|
The correction have been made as per the instruction received
|
|
|
27
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
12/05/2022
|
Needful has been done and resubmitted
|
|
|
28
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
13/05/2022
|
Hard copy not received
|
|
|
29
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
18/05/2022
|
needful has been done and resubmitted.
|
|
|
30
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
18/05/2022
|
Needful Done please.
|
|
|
31
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
06/06/2022
|
Hard copy of the reply have not been received in this office till date.
|
|
|
32
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
17/06/2022
|
Hard copy has been already submitted vide this office memo No. 791 dated 09.05.2022 which has been already received in your office on dated 12.05.2022
|
|
|
33
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
22/07/2022
|
The reply to point No.3 is not in order. The detailed CA has neither been uploaded nor submitted with the reply. Only a bill of CA scheme has been submitted with the reply. Further the CA scheme has not been calculated on current wage rates.Further penal NPV has now been calculated on revised rates. The NPV and penal NPV both are required to be calculated on revised rates of GoI.
|
|
|
34
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
22/07/2022
|
The reply to point No.3 is not in order. The detailed CA has neither been uploaded nor submitted with the reply. Only a bill of CA scheme has been submitted with the reply. Further the CA scheme has not been calculated on current wage rates.Further penal NPV has now been calculated on revised rates. The NPV and penal NPV both are required to be calculated on revised rates of GoI.
|
|
|
35
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
21/09/2022
|
Needful has been done and resubmitted
|
|
|
36
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
21/09/2022
|
Needful Done please.
|
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
01/11/2022
|
Complete reply is submitted
|
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
01/11/2022
|
Complete reply is submitted
|
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
09/12/2022
|
The State Government may attend the shortcomings attached herewith.
|
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
14/12/2022
|
eds
|
|
|
41
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
14/12/2022
|
eds
|
|
|
42
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
16/12/2022
|
EDS
|
|
|
43
|
DFO (Hamirpur)
|
EDS
|
User Agency (ee-bar-hp@nic.in)
|
15/02/2023
|
eds
|
|
|
44
|
User Agency (ee-bar-hp@nic.in)
|
REPLY
|
DFO (Hamirpur)
|
27/02/2023
|
The correction have been made as per the instruction received
|
|
|
45
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
28/03/2023
|
needful has been done and resubmitted
|
|
|
46
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
29/03/2023
|
Needful Done by DFO Hamirpur please.
|
|
|
47
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
29/04/2023
|
Please uploaded the forwarding letter alongwith annexures.
|
|
|
48
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
01/05/2023
|
As per the instructions received from your office vide letter No. Ft.48-3537/2017(FCA) dated 23.01.2023, the reply/correspondence is required to be made online and not through hard copies. The case is again resubmitted alongwith the reply of DFO Hamirpur and its enclosures please.
|
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
17/05/2023
|
Complete reply is submitted
|
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
17/05/2023
|
Complete reply is submitted
|
|
|
51
|
Regional Office
|
EDS
|
State secretary
|
01/12/2023
|
The State Government may attend the shortcomings attached herewith.
|
|
|
52
|
State secretary
|
EDS
|
Nodal Officer
|
02/12/2023
|
Kindly attend the observation
|
|
|
53
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
04/12/2023
|
EDS
|
|
|
54
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
05/12/2023
|
EDS
|
|
|
55
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
08/12/2023
|
reply was already submitted on dated 28.03.2023
|
|
|
56
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
18/12/2023
|
The reply has already been submitted on 1-5-2023 ( copy again enclosed)
|
|
|
57
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
19/12/2023
|
reply is not accepted. Please upload the correct reply.
|
|
|
58
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
19/12/2023
|
violation certificate alongwith list of violators.
|
|
|
59
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
11/01/2024
|
needful has been done and resubmitted
|
|
|
60
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
15/01/2024
|
Enclosure has not been attached with the case
|
|
|
61
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
15/01/2024
|
needful has been done and resubmitted on dated 11.01.2024
|
|
|
62
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
18/01/2024
|
on your telephonic massage dated 20-12-2023 necessary violation certificate has been attached. resubmitted pl.
|
|
|
63
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
20/01/2024
|
Please submitt the complete reply as per the GoI observation raised on 2-12-2023 so and proposal be forwarded alongwith forwarding memo.
|
|
|
64
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
20/01/2024
|
Please submitt the complete reply as per the GoI observation raised on 2-12-2023 so and proposal be forwarded alongwith forwarding memo.
|
|
|
65
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
23/01/2024
|
In this context, the violation reports of the committee in the instant case is at Sr No 8 in additional information in online part I
Further the list & orders of 2183 roads is uploaded against Sr No 14 & 15 against additional information in online part I
In addition to this appearance of name in the list was already reported in earlier I/309110/2023
|
|
|
66
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
24/01/2024
|
As per report of DFO Hamirpur the violation reports of the committee in the instant case is at Sr No 8 in additional information in online part I. Further the list & orders of 2183 roads is uploaded against Sr No 14 & 15 against additional information in online part I. In addition to this appearance of name in the list was already reported in earlier I/309110/2023 dated 18-01-2024.
|
|
|
67
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
29/01/2024
|
Specific Recommendation by the DFO with correct
information regarding violation duly signed and dated by the concerned DFO has still not been uploaded on portal.
|
|
|
68
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
29/01/2024
|
Specific Recommendation by the DFO with correct information regarding violation duly signed and dated by the concerned DFO has still not been uploaded on portal.
|
|
|
69
|
DFO (Hamirpur)
|
REPLY
|
CF (Hamirpur)
|
12/04/2024
|
specific recommendation of DFO is enclosed herewith.
|
|
|
70
|
CF (Hamirpur)
|
REPLY
|
Nodal Officer
|
16/04/2024
|
Specific recommendation of DFO is enclosed herewith.
|
|
|
71
|
Nodal Officer
|
REPLY
|
State secretary
|
02/05/2024
|
Complete reply is submitted
|
|
|
72
|
State secretary
|
REPLY
|
Regional Office
|
02/05/2024
|
Complete reply is submitted
|
|
|
73
|
Regional Office
|
EDS
|
State secretary
|
29/04/2025
|
The State Govt may attend the shortcomings attached hereiwith.
|
|
|
74
|
State secretary
|
EDS
|
Nodal Officer
|
30/04/2025
|
EDS
|
|
|
75
|
Nodal Officer
|
EDS
|
CF (Hamirpur)
|
30/04/2025
|
EDS
|
|
|
76
|
CF (Hamirpur)
|
EDS
|
DFO (Hamirpur)
|
01/05/2025
|
EDS
|
|
|
77
|
DFO (Hamirpur)
|
EDS
|
User Agency (ee-bar-hp@nic.in)
|
13/05/2025
|
EDS
|
|
|
78
|
User Agency (ee-bar-hp@nic.in)
|
REPLY
|
DFO (Hamirpur)
|
04/05/2026
|
The correction have been made as per the instruction received
|
|