Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kinnaur)
|
EDS
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
01/11/2021
|
your proposal folder is uncompleate ,please compleate the proposal folder as direction by the MoEF
|
|
2
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
REPLY
|
DFO (Kinnaur)
|
01/12/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Kinnaur)
|
EDS
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
27/12/2021
|
Kindly attend the following observation.
|
|
4
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
REPLY
|
DFO (Kinnaur)
|
27/12/2021
|
The correction have been made as per the instruction received
|
|
5
|
CF (Rampur)
|
EDS
|
DFO (Kinnaur)
|
11/01/2022
|
Returned with the remarks that hard copy of the case as well as online documents are not appearing on the online web portal. Please see to it and resubmitted
|
|
6
|
DFO (Kinnaur)
|
REPLY
|
CF (Rampur)
|
11/01/2022
|
with the hard copy of proposal folder has now been send in triplicate to your office for further process
|
|
7
|
CF (Rampur)
|
EDS
|
DFO (Kinnaur)
|
03/02/2022
|
EDS
|
|
8
|
DFO (Kinnaur)
|
EDS
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
14/02/2022
|
Please attend the observatin Vide Memo No. 6066 dated 03.02.2022 by worthy CCF Rampur , at the earliest please.
|
|
9
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
REPLY
|
DFO (Kinnaur)
|
15/02/2022
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Kinnaur)
|
EDS
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
17/02/2022
|
lease attend the observatin Vide Memo No. 6066 dated 03.02.2022 by worthy CCF Rampur , at the earliest please.
|
|
11
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
REPLY
|
DFO (Kinnaur)
|
18/02/2022
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Kinnaur)
|
REPLY
|
CF (Rampur)
|
22/02/2022
|
The compliane has been needful as raised by worth,CCF,Rampur memo No. 6066 dated 3.02.2022
|
|
13
|
CF (Rampur)
|
EDS
|
DFO (Kinnaur)
|
17/03/2022
|
EDS
|
|
14
|
DFO (Kinnaur)
|
REPLY
|
CF (Rampur)
|
23/03/2022
|
Observation raised vide your letter No. 7125 dated 17.03.2022 needful has been done and hard copy is being sent to your office please.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
07/04/2022
|
EDS
|
|
16
|
CF (Rampur)
|
EDS
|
DFO (Kinnaur)
|
19/04/2022
|
EDS
|
|
17
|
DFO (Kinnaur)
|
REPLY
|
CF (Rampur)
|
21/04/2022
|
kindly attend the above observations raised by Nodal
|
|
18
|
CF (Rampur)
|
EDS
|
DFO (Kinnaur)
|
23/04/2022
|
The case is returned as the DFO has forwarded without doing needful .
|
|
19
|
DFO (Kinnaur)
|
EDS
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
23/04/2022
|
kindly attend the above observations raised by Nodal
|
|
20
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
REPLY
|
DFO (Kinnaur)
|
23/04/2022
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Kinnaur)
|
REPLY
|
CF (Rampur)
|
28/04/2022
|
The correction have been made as per the instruction received.
|
|
22
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
07/05/2022
|
EDS
|
|
23
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
13/05/2022
|
Upload revise bill of NPV in additional documents
|
|
24
|
CF (Rampur)
|
EDS
|
DFO (Kinnaur)
|
13/05/2022
|
Upload revise bill of NPV in additional documents
|
|
25
|
DFO (Kinnaur)
|
REPLY
|
CF (Rampur)
|
13/05/2022
|
Needful has been uploaded
|
|
26
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
13/05/2022
|
Needful has been done
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
10/06/2022
|
The State Government may attend the shortcomings as per attachment.
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
15/06/2022
|
eds
|
|
29
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
15/06/2022
|
eds
|
|
30
|
CF (Rampur)
|
EDS
|
DFO (Kinnaur)
|
17/06/2022
|
EDS
|
|
31
|
DFO (Kinnaur)
|
EDS
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
22/06/2022
|
Attend the observation enclosed as addtional information please.
|
|
32
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
REPLY
|
DFO (Kinnaur)
|
24/06/2022
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Kinnaur)
|
REPLY
|
CF (Rampur)
|
07/07/2022
|
The observation raised vide your Office Endst. No. 254 dated 19.4.2022 has been complied and submitted to your office in hard copy also for further necessary action please.
|
|
34
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
11/07/2022
|
Reply of EDS is enclosed
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
16/07/2022
|
Complete reply is submitted
|
|
36
|
State secretary
|
REPLY
|
Regional Office
|
16/07/2022
|
Complete reply is submitted
|
|
37
|
Regional Office
|
EDS
|
State secretary
|
16/08/2022
|
The State Govt. may attend the shortcomings attached herewith as desired by REC
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
17/08/2022
|
EDS
|
|
39
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
18/08/2022
|
EDS
|
|
40
|
CF (Rampur)
|
EDS
|
DFO (Kinnaur)
|
18/08/2022
|
EDS
|
|
41
|
DFO (Kinnaur)
|
EDS
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
23/08/2022
|
kindly attend the above observations raised by IRO Shimla
|
|
42
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
REPLY
|
DFO (Kinnaur)
|
23/08/2022
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Kinnaur)
|
EDS
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
06/10/2022
|
The observation raised vide the meeting held with REC on 12 Aug. 2022 has been compliance by this office and submitted to worthy, CCF Rampur for further necessary action please.
|
|
44
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
REPLY
|
DFO (Kinnaur)
|
06/10/2022
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Kinnaur)
|
REPLY
|
CF (Rampur)
|
07/10/2022
|
The observation raised vide the meeting held with REC on 12 Aug. 2022 has been compliance by this office and submitted to worthy, CCF Rampur for further necessary action please.
|
|
46
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
11/10/2022
|
Reply of EDS is enclosed
|
|
47
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
18/10/2022
|
EDS
|
|
48
|
CF (Rampur)
|
EDS
|
DFO (Kinnaur)
|
01/11/2022
|
EDS is attached
|
|
49
|
DFO (Kinnaur)
|
EDS
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
01/11/2022
|
Please attend the observation immediately.
|
|
50
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
REPLY
|
DFO (Kinnaur)
|
02/11/2022
|
The correction have been made as per the instruction received
|
|
51
|
DFO (Kinnaur)
|
REPLY
|
CF (Rampur)
|
04/01/2023
|
The correction have been made as per the instruction received.
|
|
52
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
16/01/2023
|
Reply of EDS is enclosed
|
|
53
|
Nodal Officer
|
REPLY
|
State secretary
|
07/02/2023
|
Complete reply is submitted
|
|
54
|
State secretary
|
REPLY
|
Regional Office
|
07/02/2023
|
Complete reply is submitted
|
|
55
|
Regional Office
|
EDS
|
State secretary
|
25/02/2023
|
the State Government may attend the shortcomings attached herewith.
|
|
56
|
State secretary
|
EDS
|
Nodal Officer
|
27/02/2023
|
EDS
|
|
57
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
27/02/2023
|
EDS
|
|
58
|
CF (Rampur)
|
EDS
|
DFO (Kinnaur)
|
01/03/2023
|
EDs
|
|
59
|
DFO (Kinnaur)
|
EDS
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
02/03/2023
|
kindly attend the observations by REC,IRO Shimla meeting held on 21th February 2023 . immediately
|
|
60
|
User Agency (hpee-icbrpd3@cpwd.gov.in)
|
REPLY
|
DFO (Kinnaur)
|
02/03/2023
|
The correction have been made as per the instruction received
|
|
61
|
DFO (Kinnaur)
|
REPLY
|
CF (Rampur)
|
05/03/2023
|
As per the REC meeting was held on 22/02/2023, some shortcomings was raised by nodal FCA. in compliance of that shortcomings after doing the needful of all compliance has been made end point wise reply has been finished also upload in parivesh portal.
|
|
62
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
13/03/2023
|
Reply of EDS is attached
|
|
63
|
Nodal Officer
|
REPLY
|
State secretary
|
23/03/2023
|
Complete reply is submitted
|
|
64
|
State secretary
|
REPLY
|
Regional Office
|
23/03/2023
|
Complete reply is submitted
|
|