TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/ROAD/144574/2021              (ii). Name of Project for which Forest Land is required : Construction of Link Road to Village Gujrehra in District Kangra              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposal involves construction of link road to Village Gujrehra Rd 0/0 to 1/341 km in Tehsil Kangra, District Kangra within the Jurisdiction of HPPWD Kangra Division. The proposed road falls in Mohal Chakban Rajiana and Mohal Gujrehra in Tehsil Kangra, District Kangra (H.P.).              (iv). State : Himachal Pradesh              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.4156
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HP/ROAD/144574/202115/07/202130/07/2021   22/09/2021   27/09/2021   04/10/2021 D/sala :05/10/2021D/Sala:
  04/11/2021 (D/sala)

Himachal Pradesh:
15/11/2021
Himachal Pradesh:
30/11/2021
Shimla:
13/12/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:20/01/2022  
Replied by State Government(Himachal Pradesh) on:04/07/2025  
Query raised by State Government (Himachal Pradesh) on:21/01/2022  
Replied by Nodal Officer (Himachal Pradesh) on:04/07/2025  
Query raised by Nodal Officer (Himachal Pradesh) on:21/01/2022  
Replied by Circle(D/Sala) on:18/05/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:20/05/2024  
Replied by Circle(D/Sala) on:24/06/2025  
Query raised by Circle (D/Sala) on:31/01/2022  
Replied by DFO (D/sala) on:18/03/2024  
Query raised by Circle (D/Sala) on:21/05/2024  
Replied by DFO (D/sala) on:01/06/2025  
Query raised by DFO (D/sala) on:05/02/2022  
Replied by UA on :07/05/2023  
Query raised by DFO (D/sala) on:23/05/2023  
Replied by UA on :18/03/2024  
Query raised by DFO (D/sala) on:27/05/2024  
Replied by UA on :23/05/2025  
NOTE:- Proposal is pending at Regional Office .