Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
31/05/2021
|
Please provide the proposal folders before sending the case online to this office
|
|
2
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
22/06/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
23/06/2021
|
Please attend the observations as raised by the undersigned and re-submit the case after doing the needful.
|
|
4
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
25/06/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
02/07/2021
|
Folders and hard copies not received in this office
|
|
6
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
24/07/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
24/07/2021
|
The proposal folders yet not received in this office please ensure the submission of the proposal folders
|
|
8
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
24/07/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
26/07/2021
|
Please ensure the submission of folders to this office before sending the case online
|
|
10
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
28/07/2021
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
29/07/2021
|
The proposal folders not yet received
|
|
12
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
31/07/2021
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
02/08/2021
|
Please submit the proposal folders
|
|
14
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
05/08/2021
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
06/08/2021
|
Dumping sites not mentioned in KML file please do the needful and re-submit the case oniline to this office after doing the needful
|
|
16
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
07/08/2021
|
The correction have been made as per the instruction received
|
|
17
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
18/08/2021
|
Hard copy of proposal folders are not received.
|
|
18
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
19/08/2021
|
Proposal folders had already sent to your good office
|
|
19
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
22/08/2021
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
23/08/2021
|
proposal folders had already sent to your good office. Submitted for further necessary action at your end please.
|
|
21
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
26/08/2021
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
07/09/2021
|
The proposal folders had already been sent to your good office for further necessary action at your end please.
|
|
23
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
10/09/2021
|
Please attend the EDS.
|
|
24
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
15/09/2021
|
Please attend the EDS as raised by the worthy CCF Chamba at the earliest
|
|
25
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
19/09/2021
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
01/10/2021
|
As desired the necessary correction have been made, submitted for further necessary action at your end please.
|
|
27
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
08/10/2021
|
EDS is not found attended except point No. 2. Please once check the proposal before sending the reply to this office. It is utterly wastage of time. Please attend the at the earliest and re-submit the case to this office.
|
|
28
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
11/10/2021
|
EDS is not found attended except point No.2 please once check before sending the reply to this office. It is utterly wastage of time, please attend at the earliest and re-submit the case to this office.
|
|
29
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
11/10/2021
|
The correction have been made as per the instruction received
|
|
30
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
11/10/2021
|
As desired the necessary correction have been made submitted for further necessary action at your end please.
|
|
31
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
12/10/2021
|
Still point No. 3 & 5 is not found attended.
|
|
32
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
12/10/2021
|
Still point No.3 & 5 is not found attend please attend at the earliest as desired by the worthy CCF Chamba
|
|
33
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
14/10/2021
|
The correction have been made as per the instruction received
|
|
34
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
16/10/2021
|
EDS attended pls.
|
|
35
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
15/11/2021
|
EDS
|
|
36
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
16/11/2021
|
Please attend the EDS.
|
|
37
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
16/11/2021
|
Please attend the observations as raised by the worthy Nodal Officer at the earliest please.
|
|
38
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
22/11/2021
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
22/11/2021
|
Point No. 3 have not been attended by your office, please upload the digital map in online part-I against column No. C iv
|
|
40
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
03/12/2021
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
03/12/2021
|
As desired necessary correction have been made submitted for further necessary action at your end please.
|
|
42
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
09/12/2021
|
EDS has been attended please.
|
|
43
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
21/12/2021
|
Incomplete reply received in this office EDS dated 12.11.2021, point No. 3,4 and 5 has not been attended.
|
|
44
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
21/12/2021
|
Incomplete reply received in this office EDS dated 12.11.2021, point No. 3,4 and 5 has not been attended.
|
|
45
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
22/12/2021
|
Please attend the point No. 3 of last EDS raised dated 12.11.2021 and upload the digital map with shown the alternative alignment against column No. C iv at the earliest please
|
|
46
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
30/12/2021
|
The correction have been made as per the instruction received
|
|
47
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
31/12/2021
|
Please upload the land use map on the online portal part-I
|
|
48
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
01/01/2022
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
11/01/2022
|
As desired the necessary correction have been made submitted for further necessary action at your end please.
|
|
50
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
13/01/2022
|
Recommendation is not found uploaded against additional information.
|
|
51
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
13/01/2022
|
The recommendation has been now uploaded against additional information Part-II submitted for further necessary action at your end please.
|
|
52
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
18/01/2022
|
EDS has been attended.
|
|
53
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
08/02/2022
|
Saplings 186 as mentioned in the enumeration list may also be mentioned in online part II as well as in the general abstract of the trees.
|
|
54
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
08/02/2022
|
Saplings 186 as mentioned in the enumeration list may also be mentioned in online part II as well as in the general abstract of the trees.
|
|
55
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
13/02/2022
|
As desired the saplings as mentioned in the enumeration list are updated in online part-II and also uploaded the abstract in additional information.
|
|
56
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
14/02/2022
|
As desired, DFO Dalhousie has added the saplings as mentioned in the enumeration list in online part-II and also uploaded the abstract against additional information in online part-II.
|
|
57
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
24/02/2022
|
All the Saplings 186 as mentioned in the enumeration list have still not been mentioned in online part II as well as in the general abstract of the trees.
|
|
58
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
24/02/2022
|
All the Saplings 186 as mentioned in the enumeration list have still not been mentioned in online part II as well as in the general abstract of the trees. Please look into this carefully and do the needful at the earliest.
|
|
59
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
02/03/2022
|
As desired the revised enumeration list and its abstract are sent to your office vide this office letter No. 6643 dated 28.02.2022 and also endorsed Nodal Officer vide this office endst. No. 6644 dated 28.02.2022. Submitted for your information and further necessary action at your end please.
|
|
60
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
05/03/2022
|
Needful has been done by DFO Dalhousie, and hard copies in duplicate has also been sent to your office through DFO Dalhousie.
|
|
61
|
State secretary
|
EDS
|
Nodal Officer
|
21/03/2022
|
observations
|
|
62
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
22/03/2022
|
ACS Forests raised some observations.
|
|
63
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
23/03/2022
|
Please attend the EDS.
|
|
64
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
01/04/2022
|
Please attend the EDS at the earliest
|
|
65
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
20/05/2022
|
The correction have been made as per the instruction received
|
|
66
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
24/05/2022
|
As desired necessary correction have been made submitted for further necessary action at your end please.
|
|
67
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
31/05/2022
|
EDS has been attended please.
|
|
68
|
Nodal Officer
|
REPLY
|
State secretary
|
07/07/2022
|
Complete reply is submitted
|
|
69
|
Regional Office
|
EDS
|
State secretary
|
30/08/2022
|
The State Government may kindly attend the shortcomings attached herewith.
|
|
70
|
State secretary
|
EDS
|
Nodal Officer
|
31/08/2022
|
EDS
|
|
71
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
31/08/2022
|
EDS
|
|
72
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
05/09/2022
|
Please Attend the EDS.
|
|
73
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
07/09/2022
|
Please attend the EDS at the earliest.
|
|
74
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
27/04/2023
|
The correction have been made as per the instruction received
|
|
75
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
27/04/2023
|
please attend the EDS
|
|
76
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
07/05/2023
|
The correction have been made as per the instruction received
|
|
77
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
26/05/2023
|
Please attend the EDS at the earliest and resubmit the case after doing the needful
|
|
78
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
21/07/2023
|
The correction have been made as per the instruction received
|
|
79
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
12/09/2023
|
As desired the all observations have been attended by the user agency as well as this office. Submitted for further necessary action at your end please.
|
|
80
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
28/09/2023
|
EDS is not found attended to complete.
|
|
81
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
29/09/2023
|
Please attend the EDS
|
|
82
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
13/12/2023
|
The correction have been made as per the instruction received
|
|
83
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
16/12/2023
|
Please attend the EDS as per discussion
|
|
84
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
16/12/2023
|
The correction have been made as per the instruction received
|
|
85
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
22/12/2023
|
attend the EDS
|
|
86
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
27/01/2024
|
The correction have been made as per the instruction received
|
|
87
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
23/02/2024
|
As desired needful has been done
|
|
88
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
07/03/2024
|
EDS has been attended please.
|
|
89
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
23/03/2024
|
EDS
|
|
90
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
27/03/2024
|
EDS from Nodal Office
|
|
91
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
28/03/2024
|
attend the EDS
|
|
92
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
13/05/2024
|
The correction have been made as per the instruction received
|
|
93
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
15/06/2024
|
Please provide the point wise reply as raised by the Nodal Officer
|
|
94
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
09/09/2024
|
The correction have been made as per the instruction received
|
|
95
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
02/10/2024
|
EDS not attended and also point wise reply not uploaded
|
|
96
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
13/03/2025
|
The correction have been made as per the instruction received
|
|
97
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
20/03/2025
|
Attend the EDS
|
|
98
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
06/04/2025
|
The correction have been made as per the instruction received
|
|
99
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
26/04/2025
|
As desired EDS has been attended
|
|
100
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
05/05/2025
|
Eds attended by DFO and UA
|
|
101
|
Nodal Officer
|
EDS
|
CF (Chamba)
|
13/05/2025
|
The layout plan is rough and not signed by DFO, digitalized lay out plan duly signed by DFO be uploaded. Further, Muck Management plan is not signed by DFO concerned.
|
|
102
|
CF (Chamba)
|
EDS
|
DFO (Dalhousie)
|
17/05/2025
|
The layout plan is rough and not signed by DFO, digitalized lay out plan duly signed by DFO be uploaded. Further, Muck Management plan is not signed by DFO concerned.
|
|
103
|
DFO (Dalhousie)
|
EDS
|
User Agency (ee-dal-hp@nic.in)
|
20/05/2025
|
The layout plan is rough and not signed by DFO, digitalized lay out plan duly signed by DFO be uploaded. Further, Muck Management plan is not signed by DFO concerned.
|
|
104
|
User Agency (ee-dal-hp@nic.in)
|
REPLY
|
DFO (Dalhousie)
|
10/06/2025
|
The correction have been made as per the instruction received
|
|
105
|
DFO (Dalhousie)
|
REPLY
|
CF (Chamba)
|
13/06/2025
|
EDS reply Saila Mathla to Lohani
|
|
106
|
CF (Chamba)
|
REPLY
|
Nodal Officer
|
13/06/2025
|
The layout plan and muck management plan duly signed by DFO and same has been uploaded in additional information part -I by user agency please.
|
|
107
|
Nodal Officer
|
REPLY
|
State secretary
|
21/06/2025
|
Complete reply is submitted
|
|
108
|
State secretary
|
REPLY
|
Regional Office
|
21/06/2025
|
Complete reply is submitted
|
|