| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
05/04/2016
|
Please supply the hard copy of the proposal folders.
|
|
|
2
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
08/04/2016
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Kotgarh)
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
18/04/2016
|
EDS Enclose
|
|
|
4
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Kotgarh)
|
29/04/2016
|
The correction have been made as per the instruction received
|
|
|
5
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
29/06/2016
|
Shortcomings noticed as per attachment.
|
|
|
6
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
30/06/2016
|
please attend the observations raised by C.F shimla as per attachment
|
|
|
7
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
08/07/2016
|
The correction have been made as per the instruction received
|
|
|
8
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
18/07/2016
|
The observations has been attended as per attachment.
|
|
|
9
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
19/07/2016
|
As advised please upload the correct certificate w.r.t land suitability for CA
|
|
|
10
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
19/07/2016
|
Revised land suitability certificate for CA is uploaded now.
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
27/07/2016
|
Please complete the proposal as per copy of EDS attached.
|
|
|
12
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
27/07/2016
|
Please complete the proposal as per copy of EDS attached.
|
|
|
13
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
28/07/2016
|
Shortcomings noticed as per attachment.
|
|
|
14
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
30/07/2016
|
please attend the observation at the earliest.
|
|
|
15
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
30/07/2016
|
The correction have been made as per the instruction received
|
|
|
16
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
11/08/2016
|
The point wise reply has been given as per attachment.
|
|
|
17
|
CF (Rampur)
|
EDS
|
DFO (Kotgarh)
|
16/08/2016
|
Copy of EDS is attached
|
|
|
18
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
17/08/2016
|
Reply of EDS is attached.
|
|
|
19
|
DFO (Kotgarh)
|
REPLY
|
CF (Rampur)
|
23/08/2016
|
Please resend the case.
|
|
|
20
|
CF (Rampur)
|
EDS
|
DFO (Kotgarh)
|
23/08/2016
|
re-submit the case Copy of EDS is attached
|
|
|
21
|
DFO (Kotgarh)
|
REPLY
|
CF (Rampur)
|
23/08/2016
|
The online correction have been made as per instruction . EDS enclosed.
|
|
|
22
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
29/08/2016
|
After attending the observations, copy of EDS is attached.
|
|
|
23
|
Regional Office
|
EDS
|
State secretary
|
20/10/2016
|
State Govt. may attend the following shortcomings as per the attachment.
|
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
21/10/2016
|
EDS
|
|
|
25
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
21/10/2016
|
EDS
|
|
|
26
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
21/10/2016
|
EDS
|
|
|
27
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
22/10/2016
|
Shortcomings noticed as per attachment.
|
|
|
28
|
DFO (Shimla(shimla))
|
EDS
|
User Agency (ee-sml2-hp@nic.in)
|
24/10/2016
|
Shortcomings noticed as per attachment.
|
|
|
29
|
User Agency (ee-sml2-hp@nic.in)
|
REPLY
|
DFO (Shimla(shimla))
|
29/10/2016
|
The correction have been made as per the instruction received
|
|
|
30
|
CF (Rampur)
|
EDS
|
DFO (Kotgarh)
|
02/11/2016
|
Copy of EDS is attached
|
|
|
31
|
DFO (Kotgarh)
|
REPLY
|
CF (Rampur)
|
03/11/2016
|
The online correction have been made as per instruction received. EDS Enclosed
|
|
|
32
|
CF (Rampur)
|
EDS
|
DFO (Kotgarh)
|
11/11/2016
|
EDS
|
|
|
33
|
DFO (Kotgarh)
|
REPLY
|
CF (Rampur)
|
11/11/2016
|
The online correction have been made as per instruction received. EDS Enclosed.
|
|
|
34
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
11/11/2016
|
reply submit
|
|
|
35
|
CF (Shimla)
|
EDS
|
DFO (Shimla(shimla))
|
11/11/2016
|
EDS
|
|
|
36
|
DFO (Shimla(shimla))
|
REPLY
|
CF (Shimla)
|
15/11/2016
|
The point wise reply has been given as per attachment.
|
|
|
37
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
15/11/2016
|
Reply of
EDS is attached.
|
|
|
38
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
15/11/2016
|
Necesay correction has been done now
|
|
|
39
|
Nodal Officer
|
REPLY
|
State secretary
|
30/11/2016
|
Complete reply is submitted.
|
|
|
40
|
State secretary
|
REPLY
|
Regional Office
|
30/11/2016
|
Complete reply is submitted.
|
|