| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
25/06/2022
|
kinldy prove 4 set of the proposal folders to this office for further necessary action
|
|
|
2
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
23/11/2022
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
24/11/2022
|
kindly upload all the relevant documents on part-I
|
|
|
4
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
25/11/2022
|
The correction have been made as per the instruction received
|
|
|
5
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
06/01/2023
|
Singnature,date and place is missiong in many documents. Proper page numbering is required to be given. detail list enumeration of tress with scientific name is required to be attached .
|
|
|
6
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
07/01/2023
|
Date place is missing in some documents and enumeration of trees required to be attached . UA is requested to be present for demarcation of tree with forest department.
|
|
|
7
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
18/01/2023
|
The correction have been made as per the instruction received
|
|
|
8
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
21/01/2023
|
The correction has have been made as per the instruction received
|
|
|
9
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
13/03/2023
|
List of Enumeration of trees showes 392 but on onile part-II showing total tress 387
|
|
|
10
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
13/03/2023
|
The correction has been done
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
31/03/2023
|
The shortcomings have been noticed in the proposal, which may be completed.
|
|
|
12
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
01/04/2023
|
EDS
|
|
|
13
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
11/04/2023
|
Kindly enclosed find herewith the EDS .
|
|
|
14
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
19/04/2023
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
29/04/2023
|
Kindly enclosed find herewith the EDS reply raised by Nodal office
|
|
|
16
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
20/05/2023
|
observations have been attended.
|
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
04/08/2023
|
Part-IV may be revised
|
|
|
18
|
Nodal Officer
|
REPLY
|
State secretary
|
05/08/2023
|
Needful has been Done
|
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
04/03/2024
|
State Govt may find the observations attached herewith.
|
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
05/03/2024
|
EDS
|
|
|
21
|
Nodal Officer
|
EDS
|
CF (Kullu)
|
05/03/2024
|
EDS
|
|
|
22
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
06/03/2024
|
EDS
|
|
|
23
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
11/03/2024
|
Kindly enclosed find here with EDS raised by Regional Office
|
|
|
24
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
31/05/2024
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
03/06/2024
|
letter No. 898 dated 29.05.2024 may be attached as pdf
|
|
|
26
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
06/06/2024
|
The correction have been made as per the instruction received
|
|
|
27
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
18/07/2024
|
Needful may be done as discussed.
|
|
|
28
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
23/10/2024
|
The correction have been made as per the instruction received
|
|
|
29
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
30/10/2024
|
EDS
|
|
|
30
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
31/01/2025
|
The correction have been made as per the instruction received
|
|
|
31
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
19/02/2025
|
EDS-1. Justification land requisition as per Rural Places defined by Competent authority under the name for Diplomas is given as 5 hac. However the land is hilly terrain and Udaipur there is very less land which is suitable for any infrastructure .Also the proposed land is dense patch of important species. Therefore land may be revised and the 1.5 Acres and other suitable land may be identified with the communication to Competent Authority.
2.Revised Joint Inspection to be done in accordance with the Law for- 1. Possibility of merging the land with other school and colleges.2.Exploring the land parcel near patch-2 as the aff. land does not involve the felling of trees
3. NOC from BRO is not enclosed.
4. Possibilities of Vertical Expension of Blocks may be considered in Patch-2
|
|
|
32
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
12/03/2025
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
10/04/2025
|
corrections have been made as per instruction received
|
|
|
34
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
11/04/2025
|
Letter from DFO has not been found uploaded in parivesh pportal
|
|
|
35
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
02/07/2025
|
Revised Joint inspection through SDM Udaipur to be conducted as per letter enclosed
|
|
|
36
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
08/09/2025
|
The correction have been made as per the instruction received
|
|
|
37
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
02/12/2025
|
EDS
|
|
|
38
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
04/12/2025
|
eds
|
|
|
39
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
04/12/2025
|
EDS attached for doing the needful
|
|
|
40
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
10/12/2025
|
The correction have been made as per the instruction received
|
|
|
41
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
16/12/2025
|
Undertaking reagading to deposit the whole amount for the preparation of Wildlife Management Plan after approved by competent authority.
|
|
|
42
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
23/12/2025
|
The correction have been made as per the instruction received
|
|
|
43
|
DFO (Lahaul)
|
EDS
|
User Agency (iti.udaipurls@gmail.com)
|
30/12/2025
|
The revised joint inspection and Undertaking regarding Non Availability Certificate which is duly received from UA has been uploaded
|
|
|
44
|
User Agency (iti.udaipurls@gmail.com)
|
REPLY
|
DFO (Lahaul)
|
31/12/2025
|
The correction have been made as per the instruction received
|
|
|
45
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
31/12/2025
|
The revised joint inspection and Non Avaibility certificate has been uploaded
|
|
|
46
|
CF (Kullu)
|
EDS
|
DFO (Lahaul)
|
03/01/2026
|
observation on dated 11.04.2025, still not attended. Letter from Concerned DFO still not found uploaded.
|
|
|
47
|
DFO (Lahaul)
|
REPLY
|
CF (Kullu)
|
08/01/2026
|
As per direction needfull has been done
|
|
|
48
|
CF (Kullu)
|
REPLY
|
Nodal Officer
|
13/01/2026
|
Eds attended please
|
|