TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/HYD/52179/2020              (ii). Name of Project for which Forest Land is required : HAIL HEP              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : HAIL HEP on chenni Nallah , a tributary of baira nallah and sub tributary of River ravi in tehsil churah Dist chamba H.P.              (iv). File no. : 8B/HP/01/45/2021              (v). State : Himachal Pradesh              (vi). Category of the Project : Hydel              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 9.3408
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeROHQ, New DelhiStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/HP/HYD/52179/202005/11/202024/11/2020  13/11/2020   24/11/2020  24/11/2020   24/11/2020   15/12/2020 Churah :16/12/2020Chamba:
  17/12/2020 (Churah)

Himachal Pradesh:
23/12/2020
Himachal Pradesh:
08/03/2021
Shimla:
22/04/2021
Received: 04/01/2022
Decision: 26-05-2022
07/06/2022
By :Regional Office
Himachal Pradesh
20/04/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:29/05/2021  
Replied by State Government(Himachal Pradesh) on:11/10/2021  
Query raised by Regional Office (Shimla) on:08/11/2021  
Replied by State Government(Himachal Pradesh) on:09/12/2021  
Query raised by State Government (Himachal Pradesh) on:29/05/2021  
Replied by Nodal Officer (Himachal Pradesh) on:11/10/2021  
Query raised by State Government (Himachal Pradesh) on:09/11/2021  
Replied by Nodal Officer (Himachal Pradesh) on:09/12/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:20/01/2021  
Replied by Circle(Chamba) on:08/02/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:16/02/2021  
Replied by Circle(Chamba) on:25/02/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:29/05/2021  
Replied by Circle(Chamba) on:05/07/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:09/07/2021  
Replied by Circle(Chamba) on:20/07/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:21/09/2021  
Replied by Circle(Chamba) on:22/09/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:09/11/2021  
Replied by Circle(Chamba) on:04/12/2021  
Query raised by Circle (Chamba) on:17/12/2020  
Replied by DFO (Churah) on:17/12/2020  
Query raised by Circle (Chamba) on:21/12/2020  
Replied by DFO (Churah) on:22/12/2020  
Query raised by Circle (Chamba) on:22/01/2021  
Replied by DFO (Churah) on:06/02/2021  
Query raised by Circle (Chamba) on:06/02/2021  
Replied by DFO (Churah) on:07/02/2021  
Query raised by Circle (Chamba) on:17/02/2021  
Replied by DFO (Churah) on:23/02/2021  
Query raised by Circle (Chamba) on:24/02/2021  
Replied by DFO (Churah) on:24/02/2021  
Query raised by Circle (Chamba) on:30/05/2021  
Replied by DFO (Churah) on:29/06/2021  
Query raised by Circle (Chamba) on:09/07/2021  
Replied by DFO (Churah) on:19/07/2021  
Query raised by Circle (Chamba) on:10/11/2021  
Query raised by DFO (Churah) on:17/12/2020  
Replied by UA on :17/12/2020  
Query raised by DFO (Churah) on:22/01/2021  
Replied by UA on :29/01/2021  
Query raised by DFO (Churah) on:06/02/2021  
Replied by UA on :07/02/2021  
Query raised by DFO (Churah) on:10/06/2021  
Replied by UA on :26/06/2021  
Query raised by DFO (Churah) on:12/07/2021  
Replied by UA on :17/07/2021  
Query raised by DFO (Churah) on:12/11/2021  
Replied by UA on :02/12/2021  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Shimla) on:01/06/2023  
Query raised by State Government (Himachal Pradesh) on:05/06/2023  
Query raised by Nodal Officer on:05/06/2023  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .