TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/HYD/36018/2018              (ii). Name of Project for which Forest Land is required : Kandhi Top 100 KW Hydel Project.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Micro Hydel Project Kandhi Top 100 KW. This will improve state finances from sales revenue earned from supplying surplus power to be national grid. It will lead to improve the power supply situation in the HP as well as entire Northern electric Grid of the country. On commissioning              (iv). File no. : Ft. 48-3797/2018 (FCA)              (v). State : Himachal Pradesh              (vi). Category of the Project : Hydel              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.2186
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/HP/HYD/36018/201818/09/201804/10/2018  25/09/2018   04/10/2018  03/10/2018   05/10/2018   05/10/2018 Suket :05/10/2018Mandi:
  01/03/2019 (Suket)

Himachal Pradesh:
29/04/2019
Himachal Pradesh:
02/11/2020
23/11/2020
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Himachal Pradesh) on:02/05/2019  
Replied by Circle(Mandi) on:01/07/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:06/07/2019  
Replied by Circle(Mandi) on:05/09/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:12/09/2019  
Replied by Circle(Mandi) on:20/11/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:28/11/2019  
Replied by Circle(Mandi) on:30/11/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:21/12/2019  
Replied by Circle(Mandi) on:12/10/2020  
Query raised by Circle (Mandi) on:08/03/2019  
Replied by DFO (Suket) on:25/04/2019  
Query raised by Circle (Mandi) on:03/05/2019  
Replied by DFO (Suket) on:28/06/2019  
Query raised by Circle (Mandi) on:08/07/2019  
Replied by DFO (Suket) on:31/08/2019  
Query raised by Circle (Mandi) on:13/09/2019  
Replied by DFO (Suket) on:18/11/2019  
Query raised by Circle (Mandi) on:26/12/2019  
Replied by DFO (Suket) on:01/10/2020  
Query raised by DFO (Mandi) on:06/10/2018  
Replied by UA on :25/10/2018  
Query raised by DFO (Mandi) on:25/10/2018  
Replied by UA on :18/11/2018  
Query raised by DFO (Mandi) on:19/11/2018  
Replied by UA on :23/11/2018  
Query raised by DFO (Mandi) on:24/11/2018  
Replied by UA on :24/11/2018  
Query raised by DFO (Mandi) on:24/11/2018  
Replied by UA on :26/11/2018  
Query raised by DFO (Mandi) on:27/11/2018  
Replied by UA on :27/11/2018  
Query raised by DFO (Mandi) on:27/11/2018  
Replied by UA on :03/12/2018  
Query raised by DFO (Suket) on:20/02/2019  
Replied by UA on :27/02/2019  
Query raised by DFO (Suket) on:09/05/2019  
Replied by UA on :10/06/2019  
Query raised by DFO (Suket) on:14/08/2019  
Replied by UA on :16/08/2019  
Query raised by DFO (Suket) on:19/09/2019  
Replied by UA on :22/10/2019  
Query raised by DFO (Suket) on:04/01/2020  
Replied by UA on :19/05/2020  
Query raised by DFO (Suket) on:03/06/2020  
Replied by UA on :27/09/2020  
Query raised by DFO (Suket) on:28/09/2020  
Replied by UA on :30/09/2020  
NOTE:- Stage-I Approval accorded by : State Government .