Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/GJ/ROAD/15157/2015              (ii). Name of Project for which Forest Land is required : New R.O.B. on Savli-Timba Road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : the project of construction of New ROB on Savli-Timba Road Km. 37/1-.00 To 38/00 Near Udalpur Village at LC. No.58 Railway Crossing.              (iv). State : Gujarat              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.05875
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/GJ/ROAD/15157/201503/09/201511/03/2016  01/02/2016  09/10/2015  30/09/2015  09/09/2015   19/03/2016  09/03/2016  09/12/2015  03/10/2015  23/09/2015   21/12/2015   27/01/2016 Vadodara SF :22/03/2016Godhara SF Circle:
  25/03/2016 (Vadodara SF)

Gujarat:
05/04/2016
Gujarat:
30/05/2017
Gandhinagar:
30/10/2017
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Gandhinagar) on:05/12/2017  
Query raised by State Government (Gujarat) on:17/06/2017  
Replied by Nodal Officer (Gujarat) on:09/10/2017  
Query raised by State Government (Gujarat) on:06/02/2018  
Query raised by Nodal Officer (Gujarat) on:06/04/2016  
Replied by Circle(Bharuch SF Circle) on:06/04/2016  
Query raised by Nodal Officer (Gujarat) on:25/04/2016  
Replied by Circle(Bharuch SF Circle) on:10/05/2017  
Query raised by Nodal Officer (Gujarat) on:04/09/2017  
Replied by Circle(Bharuch SF Circle) on:28/09/2017  
Query raised by Nodal Officer (Gujarat) on:09/04/2018  
Replied by Circle(Godhara SF Circle) on:22/01/2021  
Query raised by Nodal Officer (Gujarat) on:28/01/2021  
Replied by Circle() on:  
Query raised by Circle (Godhara SF Circle) on:01/04/2016  
Replied by DFO (Vadodara SF) on:02/04/2016  
Query raised by Circle (Godhara SF Circle) on:06/04/2016  
Replied by DFO (Vadodara SF) on:06/04/2016  
Query raised by Circle (Godhara SF Circle) on:26/04/2016  
Replied by DFO (Vadodara SF) on:02/05/2017  
Query raised by Circle (Godhara SF Circle) on:08/09/2017  
Replied by DFO (Vadodara SF) on:12/09/2017  
Query raised by Circle (Godhara SF Circle) on:14/09/2017  
Replied by DFO (Vadodara SF) on:25/09/2017  
Query raised by Circle (Godhara SF Circle) on:03/12/2020  
Replied by DFO (Vadodara SF) on:21/01/2021  
Query raised by Circle (Godhara SF Circle) on:29/01/2021  
Replied by DFO (Vadodara SF) on:11/02/2021  
Query raised by Circle (Godhara SF Circle) on:12/02/2021  
Replied by DFO () on:  
Query raised by DFO (Vadodara SF) on:01/04/2016  
Replied by UA on :01/04/2016  
Query raised by DFO (Vadodara SF) on:22/09/2017  
Replied by UA on :22/09/2017  
Query raised by DFO (Vadodara SF) on:25/09/2017  
Replied by UA on :25/09/2017  
Query raised by DFO (Vadodara SF) on:11/01/2021  
Replied by UA on :11/01/2021  
Query raised by DFO (Vadodara SF) on:02/03/2021  
Replied by UA on :24/05/2023  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .