| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Jamnagar)
|
EDS
|
User Agency (shobha.muni@powericaltd.com)
|
02/09/2021
|
non forest area detail not match with hard copy
|
|
|
2
|
User Agency (shobha.muni@powericaltd.com)
|
REPLY
|
DFO (Jamnagar)
|
15/09/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Junagadh Circle)
|
05/10/2021
|
PL UPLOAD 100 plant scheme as per new guideline pear 2.6
|
|
|
4
|
CF (Junagadh Circle)
|
EDS
|
DFO (Jamnagar)
|
08/10/2021
|
PL UPLOAD 100 plant scheme as per new guideline pear 2.6
|
|
|
5
|
DFO (Jamnagar)
|
REPLY
|
CF (Junagadh Circle)
|
08/10/2021
|
scheme send by APCCF land 100 plant scheme as per new guideline pear 2.6 is uploaded
|
|
|
6
|
CF (Junagadh Circle)
|
REPLY
|
Nodal Officer
|
08/10/2021
|
scheme send by APCCF land 100 plant scheme as per new guideline pear 2.6 is uploaded
|
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
25/01/2022
|
EDS letter dated 25.01.2022
|
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
10/02/2022
|
GoI Query
|
|
|
9
|
Nodal Officer
|
EDS
|
CF (Junagadh Circle)
|
10/02/2022
|
as per GoI Query
|
|
|
10
|
CF (Junagadh Circle)
|
EDS
|
DFO (Jamnagar)
|
10/02/2022
|
as per letter
|
|
|
11
|
DFO (Jamnagar)
|
REPLY
|
CF (Junagadh Circle)
|
22/03/2022
|
The required report is uploaded here.
|
|
|
12
|
CF (Junagadh Circle)
|
REPLY
|
Nodal Officer
|
31/03/2022
|
Quary solve
|
|
|
13
|
Nodal Officer
|
REPLY
|
State secretary
|
19/04/2022
|
as per single file
|
|
|
14
|
State secretary
|
REPLY
|
Regional Office
|
30/05/2022
|
query solved
|
|